Randomized Earned Value Method for the rolling assessment of construction projects advancement

被引:2
|
作者
Kasprowicz, Tadeusz [1 ]
Starczyk-Kolbyk, Anna [1 ]
机构
[1] Mil Univ Technol, Fac Civil Engn & Geodesy, Ul Gen Sylwestra Kaliskiego 2, PL-00908 Warsaw, Poland
关键词
construction project; duration; cost; advancement; rolling assessment;
D O I
10.24425/ace.2022.140655
中图分类号
TU [建筑科学];
学科分类号
0813 ;
摘要
The Randomized Earned Value Method enable to control the time and cost of works during the implementation of a construction project. The method allows to assess the compliance of the current advancement in time and actually incurred costs with the adopted plan. It also allows to predict the date and amount of the project completion costs. Individual assessment indicators (BCWS, BCWP, ACWP) are calculated after the ongoing control of the progression of works. In the case of randomly changing of implementation conditions, the calculated in this way values of the indicators may be unacceptable because of overlarge differences in comparison to actual values. Therefore, it is proposed an EVM enhancement and additional risk conditions analysis. In this approach data from the quantity survey of works are randomized based on analysis of variations between actually measured and planned values of duration and cost of implemented works. It is estimated the randomized values of individual indicators after successive controls of the progress of works. After each project advancement control the duration and cost of the works that remain to be performed are estimated. Moreover, new verified overall time and total cost of the project implementation are also estimated. After the last inspection, randomized values of the final date and total cost of completion of the project are calculated, as well as randomized values of time extension and total cost overrun. Of course, for randomized values, standard deviations of individual quantities are calculated. Therefore, the risk of time and the risk of cost of the project implementation are presented in the risk charts. The proposed approach provides a better assessment of the progress of works under risk conditions. It is worth to add that the method does not require significant changes to the typical construction management process, however, it ensures realistic consideration of the influence of random factors on the course and results of individual works and the entire project.
引用
收藏
页码:501 / 520
页数:20
相关论文
共 50 条
  • [1] Simplified Earned Value Analysis Method for Highway Construction Projects
    Son, Junghye
    Khwaja, Nabeel
    Milligan, Duane S. S.
    Honey, Brenan D. D.
    TRANSPORTATION RESEARCH RECORD, 2023, 2677 (10) : 301 - 310
  • [2] Application of Earned Value Method to Progress Control of Construction projects
    Czemplik, Andrzej
    XXIII R-S-P SEMINAR, THEORETICAL FOUNDATION OF CIVIL ENGINEERING (23RSP) (TFOCE 2014), 2014, 91 : 424 - 428
  • [3] Applying Earned Value to Construction Projects
    Al-Fadhli, Suaad Khaleel, I
    Al-Bazaz, Shahlaa Hikmat
    4TH INTERNATIONAL CONFERENCE ON BUILDINGS, CONSTRUCTION AND ENVIRONMENTAL ENGINEERING, 2020, 737
  • [4] Control of construction projects using the Earned Value Method - case study
    Araszkiewicz, Krystyna
    Bochenek, Magdalena
    OPEN ENGINEERING, 2019, 9 (01): : 186 - 195
  • [5] Application of the Randomized Earned Value Method to assess the advancement of the construction of the office building under the unstable implementation conditions
    Kasprowicz, Tadeusz
    Starczyk-Kolbyk, Anna
    ARCHIVES OF CIVIL ENGINEERING, 2024, 70 (01) : 169 - 199
  • [6] Earned Value Method (EVM) for Construction Projects: Current Application and Future Projections
    Proano-Narvaez, Mayra
    Flores-Vazquez, Carlos
    Vasquez Quiroz, Pablo
    Avila-Calle, Marco
    BUILDINGS, 2022, 12 (03)
  • [7] APPLICATION OF MODIFIED EARNED VALUE METHOD FOR ASSESSING THE RISK AND PROGRESS OF CONSTRUCTION PROJECTS
    Zawistowski, Jacek
    MODERN BUILDING MATERIALS, STRUCTURES AND TECHNIQUES, 10TH INTERNATIONAL CONFERENCE 2010, VOL I, 2010, : 557 - 560
  • [8] Earned Value Management System in Indonesian Construction Projects
    Priyo, Mandiyo
    INTERNATIONAL JOURNAL OF INTEGRATED ENGINEERING, 2021, 13 (03): : 37 - 45
  • [9] The application, modification & extension of earned value management in construction projects
    Zhang, Xiaoli
    Lin, Zefu
    Ji, Xue
    Proceedings of 2007 International Conference on Construction & Real Estate Management, Vols 1 and 2, 2007, : 955 - 958
  • [10] The Cost Monitoring of Construction Projects Through Earned Value Analysis
    Khamidi, Mohd Faris
    Khan, Waris Ali
    Idrus, Arazi
    ECONOMICS AND FINANCE RESEARCH, 2011, 4 : 129 - 133