Randomized Earned Value Method for the rolling assessment of construction projects advancement

被引:2
|
作者
Kasprowicz, Tadeusz [1 ]
Starczyk-Kolbyk, Anna [1 ]
机构
[1] Mil Univ Technol, Fac Civil Engn & Geodesy, Ul Gen Sylwestra Kaliskiego 2, PL-00908 Warsaw, Poland
关键词
construction project; duration; cost; advancement; rolling assessment;
D O I
10.24425/ace.2022.140655
中图分类号
TU [建筑科学];
学科分类号
0813 ;
摘要
The Randomized Earned Value Method enable to control the time and cost of works during the implementation of a construction project. The method allows to assess the compliance of the current advancement in time and actually incurred costs with the adopted plan. It also allows to predict the date and amount of the project completion costs. Individual assessment indicators (BCWS, BCWP, ACWP) are calculated after the ongoing control of the progression of works. In the case of randomly changing of implementation conditions, the calculated in this way values of the indicators may be unacceptable because of overlarge differences in comparison to actual values. Therefore, it is proposed an EVM enhancement and additional risk conditions analysis. In this approach data from the quantity survey of works are randomized based on analysis of variations between actually measured and planned values of duration and cost of implemented works. It is estimated the randomized values of individual indicators after successive controls of the progress of works. After each project advancement control the duration and cost of the works that remain to be performed are estimated. Moreover, new verified overall time and total cost of the project implementation are also estimated. After the last inspection, randomized values of the final date and total cost of completion of the project are calculated, as well as randomized values of time extension and total cost overrun. Of course, for randomized values, standard deviations of individual quantities are calculated. Therefore, the risk of time and the risk of cost of the project implementation are presented in the risk charts. The proposed approach provides a better assessment of the progress of works under risk conditions. It is worth to add that the method does not require significant changes to the typical construction management process, however, it ensures realistic consideration of the influence of random factors on the course and results of individual works and the entire project.
引用
收藏
页码:501 / 520
页数:20
相关论文
共 50 条
  • [21] Earned Value Management Software Projects
    Hanna, Robert A.
    SMC-IT 2009: THIRD IEEE INTERNATIONAL CONFERENCE ON SPACE MISSION CHALLENGES FOR INFORMATION TECHNOLOGY, PROCEEDINGS, 2009, : 297 - 304
  • [22] Assessing the performance of construction projects: Implementing earned value management at the General Services Administration
    Alvarado, Carlos
    Silverman, Robert
    Wilson, David
    JOURNAL OF FACILITIES MANAGEMENT, 2005, 3 (01) : 92 - +
  • [23] Application of the Earned Value Mathod (EVM) for mining projects assessment - critical approach - part 1 - method assumptions
    Getler, Adam
    Tchorzewski, Seweryn
    INZYNIERIA MINERALNA-JOURNAL OF THE POLISH MINERAL ENGINEERING SOCIETY, 2020, (01): : 265 - 272
  • [24] Increasing earned value analysis efficiency for IT projects
    Stanek, Stanislaw
    Kuchta, Dorota
    JOURNAL OF DECISION SYSTEMS, 2020, 29 (sup1) : 352 - 360
  • [25] Conditions of success for earned value analysis in projects
    Bryde, David
    Unterhitzenberger, Christine
    Joby, Roger
    INTERNATIONAL JOURNAL OF PROJECT MANAGEMENT, 2018, 36 (03) : 474 - 484
  • [26] AgileEVM - Earned Value Management in scrum projects
    Sulaiman, Tamara
    Barton, Brent
    Blackburn, Thomas
    AGILE 2006, Proceedings, 2006, : 7 - 16
  • [27] The Research on Communication Networks Construction Based on Earned Value Analysis Method
    Cai, Juan
    Chen, Zhengshi
    2015 International Conference on Network and Information Systems for Computers (ICNISC), 2015, : 270 - 272
  • [28] Regression Modeling for Prediction of Earned Value Indexes in Public Building Construction Projects: The case of Ethiopia
    Ayalew, Genet Melkamu
    Meharie, Meseret Getnet
    Ayalew, Girmay Getawa
    COGENT ENGINEERING, 2023, 10 (01):
  • [29] Earned Value as a performance measurement tool for small and large construction projects in a South African environment
    Vertenten, M.
    Pretorius, L.
    Pretorius, J. H. C.
    2009 AFRICON, VOLS 1 AND 2, 2009, : 885 - 889
  • [30] Improving the Results of the Earned Value Management Technique Using Artificial Neural Networks in Construction Projects
    Balali, Amirhossein
    Valipour, Alireza
    Antucheviciene, Jurgita
    Saparauskas, Jonas
    SYMMETRY-BASEL, 2020, 12 (10): : 1 - 17