Key Last Planner System Metrics to Assess Project Performance in High-Rise Building and Industrial Construction Projects

被引:9
|
作者
Perez, Daniel [1 ]
Lagos, Camilo [1 ]
Alarcon, Luis Fernando [1 ]
机构
[1] Pontificia Univ Catolica Chile, Dept Construct Engn & Management, Vicuna Mackenna 4860, Santiago 7820436, Chile
关键词
IMPLEMENTATION; BENEFITS; THINKING;
D O I
10.1061/(ASCE)CO.1943-7862.0002209
中图分类号
TU [建筑科学];
学科分类号
0813 ;
摘要
The Last Planner System (LPS) establishes short cycles of planning and control, comprising LP, the make-ready process, short-term planning commitments, identifying reasons for noncompletion, and implementing corrective actions. Most LPS research has covered longitudinal case studies, but quantitative transversal research is needed to determine the impact of key LPS processes in performance. The researchers aimed to determine the relationships between LPS components and project performance. Twenty three metrics were established to evaluate six components and 253 possible correlations between them. The authors assessed information from 255 projects and found 131 projects, in five categories, with sufficient information to construct the metrics. Two categories had sufficient sample sizes, which produced a sample of 71 high-rise building (HR) and 28 industrial construction (IC) projects. Each sample was assessed separately to test the correlations, and the project categories were compared to determine statistically significant differences. Then, the projects were classified according to their schedule performance outcome, using a clustering algorithm to find differences between high- and low-performance projects. Statistically significant correlations between the six components were found in both samples, six metrics presented statistically significant differences between high and low performance in HR projects and one in IC projects. (C) 2021 American Society of Civil Engineers.
引用
收藏
页数:14
相关论文
共 50 条
  • [21] Safety Risk Prediction Model of High-Rise Building Construction Based on Key Physiological Index
    Chen, Haiyan
    Mao, Yihua
    Wang, Rui
    Buildings, 2024, 14 (12)
  • [22] BIM Technology Application in the Exploration of Super High-rise Office Building Project in Civil Construction
    Li, Yufeng
    Gao, Zheng
    Zhang, Xiaofeng
    PROCEEDINGS OF THE 2016 INTERNATIONAL CONFERENCE ON CIVIL, TRANSPORTATION AND ENVIRONMENT, 2016, 78 : 269 - 272
  • [23] Application of multi-criteria analysis in the selection of formwork material for high-rise building construction projects
    Pham, Vu Hong Son
    Dau, Thuy Dung
    Tran, Le Anh
    COGENT ENGINEERING, 2024, 11 (01):
  • [24] CONSTRUCTION SEQUENCE ANALYSIS OF THE FLAT PLATE SYSTEM IN A HIGH-RISE BUILDING AND ITS IMPACT ON THE CONSTRUCTION CYCLE
    Kim, Jae-Yo
    Abdelrazaq, Ahmad K.
    STRUCTURAL DESIGN OF TALL AND SPECIAL BUILDINGS, 2009, 18 (03): : 341 - 349
  • [25] Feasibility of vertical photovoltaic system on high-rise building in Malaysia: performance evaluation
    Ghazali, Azhar
    Salleh, Elias Ilias
    Haw, Lim Chin
    Mat, Sohif
    INTERNATIONAL JOURNAL OF LOW-CARBON TECHNOLOGIES, 2017, 12 (03) : 263 - 271
  • [26] Discussion on Cost Control Method of Construction Project-Taking High-Rise Residential Building Project in Shijiazhuang as an Example
    Yu Xiangmei
    Xie Zhenbin
    CIVIL ENGINEERING IN CHINA - CURRENT PRACTICE AND RESEARCH REPORT: PROCEEDINGS OF THE 2ND INTERNATIONAL CONFERENCE ON CIVIL ENGINEERING, 2011, : 511 - 516
  • [27] Optimal Location for Tower Crane and Dynamic Trailer Parking in High-Rise Modular Building Construction Project
    Malaikrisanachalee, Suphawut
    Wongwai, Narongrit
    Butsan, Nujet
    INTERNATIONAL JOURNAL OF MATHEMATICAL ENGINEERING AND MANAGEMENT SCIENCES, 2024, 9 (05) : 965 - 987
  • [28] Analysis of the Key and Difficult Points in the Engineering Construction Technology of the Steel Structures of a Super High-rise Building
    Dou, Lijun
    Li, Hengxu
    4TH INTERNATIONAL CONFERENCE ON MECHANICS AND MECHATRONICS RESEARCH (ICMMR 2017), 2017, 224
  • [29] Health Risk Management which are effective on Human Health in High-rise Building construction projects with Fuzzy Approach
    Ardeshir, A.
    Maknoon, R.
    Zadeh, M. Rekab Island
    Jahantab, Z.
    JOURNAL OF HEALTH AND SAFETY AT WORK, 2013, 3 (01) : 69 - +
  • [30] IFC data extension for real-time safety monitoring of automated construction in high-rise building projects
    Hu, Ruibo
    Chen, Ke
    Jiang, Weiguang
    Luo, Hanbin
    AUTOMATION IN CONSTRUCTION, 2024, 162