Solving Fuzzy Time–Cost Trade-Off in Construction Projects Using Linear Programming

被引:3
|
作者
Elkalla I. [1 ]
Elbeltagi E. [1 ]
El Shikh M. [1 ]
机构
[1] Structural Engineering Department, Faculty of Engineering, Mansoura University, Mansoura
关键词
Fuzzy time–cost trade-off; Linear programming; Nearest symmetric trapezoidal fuzzy number; Simplex method;
D O I
10.1007/s40030-020-00489-7
中图分类号
学科分类号
摘要
The time–cost trade-off has been recognized as a very significant aspect of construction management. Generally, time–cost trade-off can be modeled as a fuzzy linear programming problem with symmetric or non-symmetric fuzzy numbers. However, it was successfully solved when the fuzzy membership functions are only symmetric. In the present work, a novel approach is introduced to solve fuzzy linear programming problem with non-symmetric fuzzy membership functions by transforming it to its corresponding nearest symmetric one. The transformed problem is then converted to its crisp linear programming problem and then solved by the standard primal simplex method. Two examples are presented to show the effectiveness of the proposed approach, and the results are discussed. © 2020, The Institution of Engineers (India).
引用
收藏
页码:267 / 278
页数:11
相关论文
共 50 条
  • [41] Time-cost-quality-risk Trade-off Project Scheduling Problem in Oil and Gas Construction Projects: Fuzzy Logic and Genetic Algorithm
    Banihashemi, Sayyid Ali
    Khalilzadeh, Mohammad
    [J]. JORDAN JOURNAL OF CIVIL ENGINEERING, 2022, 16 (02) : 355 - 364
  • [42] Time-cost-quality trade-off analysis for highway construction
    El-Rayes, K
    Kandil, A
    [J]. JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT, 2005, 131 (04) : 477 - 486
  • [43] Fuzzy Multi-objective Programming Application for Time-Cost Trade-off of CPM in Project Management
    Yang, Gino K.
    [J]. COMPUTATIONAL COLLECTIVE INTELLIGENCE: TECHNOLOGIES AND APPLICATIONS, PT I, 2010, 6421 : 215 - 229
  • [44] An integrated multi-objective optimization model for solving the construction time-cost trade-off problem
    Koo, Choongwan
    Hong, Taehoon
    Kim, Sangbum
    [J]. JOURNAL OF CIVIL ENGINEERING AND MANAGEMENT, 2015, 21 (03) : 323 - 333
  • [45] Utility of Genetic Algorithms for Solving Large-Scale Construction Time-Cost Trade-Off Problems
    Agdas, Duzgun
    Warne, David J.
    Osio-Norgaard, Jorge
    Masters, Forrest J.
    [J]. JOURNAL OF COMPUTING IN CIVIL ENGINEERING, 2018, 32 (01)
  • [46] Fuzzy random time-cost trade-off model based on the philosophy of dependent-chance programming
    Ma, Jun-Jie
    Ke, Hua
    Ma, Wei-Min
    [J]. Xitong Gongcheng Lilun yu Shijian/System Engineering Theory and Practice, 2013, 33 (04): : 886 - 892
  • [47] Utilizing artificial intelligence to solving time - cost - quality trade-off problem
    Pham Vu Hong Son
    Luu Ngoc Quynh Khoi
    [J]. SCIENTIFIC REPORTS, 2022, 12 (01)
  • [48] Utilizing artificial intelligence to solving time – cost – quality trade-off problem
    Pham Vu Hong Son
    Luu Ngoc Quynh Khoi
    [J]. Scientific Reports, 12
  • [49] An Integer Grey Goal Programming For Project Time, Cost and Quality Trade-Off
    Hajiagha, Seyed Hossein Razavi
    Akrami, Hadi
    Hashemi, Shide Sadat
    Mahdiraji, Hannan Amoozad
    [J]. INZINERINE EKONOMIKA-ENGINEERING ECONOMICS, 2015, 26 (01): : 93 - 100
  • [50] Presenting a goal programming model in the time-cost-quality trade-off
    Hamta, Nima
    Ehsanifar, Mohammad
    Sarikhani, Javad
    [J]. INTERNATIONAL JOURNAL OF CONSTRUCTION MANAGEMENT, 2021, 21 (01) : 1 - 11