Optimization models and a GA-based algorithm for stochastic time-cost trade-off problem

被引:46
|
作者
Ke, Hua [1 ]
Ma, Weimin [1 ]
Ni, Yaodong
机构
[1] Tongji Univ, Sch Econ & Management, Shanghai 200092, Peoples R China
基金
中国国家自然科学基金; 中国博士后科学基金;
关键词
Time-cost trade-off; Chance-constrained programming; Dependent-chance programming; Stochastic programming; Genetic algorithm;
D O I
10.1016/j.amc.2009.05.004
中图分类号
O29 [应用数学];
学科分类号
070104 ;
摘要
In real-life projects, both the trade-off between the project cost and the project completion time, and the uncertainty of the environment are considerable aspects for decision-makers. However, the research on the time-cost trade-off problem seldom concerns stochastic environments. Besides, optimizing the expected value of the objective is the exclusive decision-making criterion in the existing models for the stochastic time-cost trade-off problem. In this paper, two newly developed alternative stochastic time-cost trade-off models are proposed, in which the philosophies of chance-constrained programming and dependent-chance programming are adopted for decision-making. In addition, a hybrid intelligent algorithm integrating stochastic simulations and genetic algorithm is designed to search the quasi-optimal schedules under different decision-making criteria. The goal of the paper is to reveal how to obtain the optimal balance of the project completion time and the project cost in stochastic environments. (C) 2009 Elsevier Inc. All rights reserved.
引用
收藏
页码:308 / 313
页数:6
相关论文
共 50 条
  • [41] Using machine learning and GA to solve time-cost trade-off problems
    Li, H
    Cao, JN
    Love, PED
    JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT, 1999, 125 (05) : 347 - 353
  • [42] Project time-cost trade-off optimization by maximal flow theory
    Liu, JM
    Rahbar, F
    JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT, 2004, 130 (04) : 607 - 609
  • [43] Time-cost trade-off optimization with a new initial population approach
    Toğan V.
    Eirgash M.A.
    Teknik Dergi/Technical Journal of Turkish Chamber of Civil Engineers, 2019, 30 (06): : 9561 - 9580
  • [44] Experimental evaluation of simulated annealing algorithms for the time-cost trade-off problem
    Anagnostopoulos, K. P.
    Kotsikas, L.
    APPLIED MATHEMATICS AND COMPUTATION, 2010, 217 (01) : 260 - 270
  • [45] Modeling Time-Cost Trade-off Problem with Fuzzy Activity Duration Times
    Ma, Weimin
    Ke, Hua
    FOURTH INTERNATIONAL CONFERENCE ON COOPERATION AND PROMOTION OF INFORMATION RESOURCES IN SCIENCE AND TECHNOLOGY (COINFO 2009), 2009, : 344 - 347
  • [46] An integrated multi-objective optimization model for solving the construction time-cost trade-off problem
    Koo, Choongwan
    Hong, Taehoon
    Kim, Sangbum
    JOURNAL OF CIVIL ENGINEERING AND MANAGEMENT, 2015, 21 (03) : 323 - 333
  • [47] A Fuzzy Random Time-Cost Trade-off Model
    Ke, Hua
    Ma, Weimin
    PROCEEDINGS OF THE EIGHTH INTERNATIONAL CONFERENCE ON INFORMATION AND MANAGEMENT SCIENCES, 2009, 8 : 633 - 637
  • [48] Optimizing of Discrete Time-cost Trade-off Problem in Construction Projects Using Advanced Jaya Algorithm
    Albayrak, Guelcag
    PERIODICA POLYTECHNICA-CIVIL ENGINEERING, 2023, 67 (03): : 806 - 818
  • [49] A time-cost trade-off model with resource consideration using genetic algorithm
    Chua, DKH
    Chan, WT
    Govindan, K
    CIVIL ENGINEERING SYSTEMS, 1997, 14 (04): : 291 - 311
  • [50] TIME-COST TRADE-OFF AMONG RELATED ACTIVITIES
    REDA, R
    CARR, RI
    JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT-ASCE, 1989, 115 (03): : 475 - 486