MIP models for resource-constrained project scheduling with flexible resource profiles

被引:81
|
作者
Naber, Anulark [1 ]
Kolisch, Rainer [1 ]
机构
[1] Tech Univ Munich, TUM Sch Management, D-80333 Munich, Germany
关键词
Project scheduling; Flexible profiles; Principal resources; Dependent resources; Discrete-time models; TRADE-OFF PROBLEM; LIMITED RESOURCES; BOUND APPROACH; NETWORKS; BRANCH; ALGORITHM; SEARCH;
D O I
10.1016/j.ejor.2014.05.036
中图分类号
C93 [管理学];
学科分类号
12 ; 1201 ; 1202 ; 120202 ;
摘要
This paper addresses the resource-constrained project scheduling problem with flexible resource profiles (FRCPSP). Such a problem often arises in many real-world applications, in which the resource usage of an activity is not merely constant, but can be adjusted from period to period. The FRCPSP is, therefore, to simultaneously determine the start time, the resource profile, and the duration of each activity in order to minimize the makespan, subject to precedence relationships, limited availability of multiple resources, and restrictions on resource profiles. We propose four discrete-time model formulations and compare their model efficiency in terms of solution quality and computational times. Both preprocessing and priority-based heuristic methods are also applied to compute both upper and lower bounds of the makespan. Our comparative results show significant dominance of one of the models, the so-called "variable-intensity-based" model, in both solution quality and runtimes. (C) 2014 Elsevier B.V. All rights reserved.
引用
收藏
页码:335 / 348
页数:14
相关论文
共 50 条
  • [21] Resource-constrained project scheduling problem with reworking
    Liao Y.
    Lu Z.
    Jisuanji Jicheng Zhizao Xitong/Computer Integrated Manufacturing Systems, CIMS, 2019, 25 (11): : 2762 - 2774
  • [22] An Extended CPM for Resource-constrained Project Scheduling
    Ju, C. H.
    Xie, Y.
    ULTRA-PRECISION MACHINING TECHNOLOGIES, 2009, 69-70 : 695 - 699
  • [23] NONPREEMPTIVE MULTIMODE RESOURCE-CONSTRAINED PROJECT SCHEDULING
    DREXL, A
    GRUENEWALD, J
    IIE TRANSACTIONS, 1993, 25 (05) : 74 - 81
  • [24] A Practical Approach for Resource-Constrained Project Scheduling
    Manousakis, Konstantinos
    Savva, Giannis
    Papadouri, Nicos
    Mavrovouniotis, Michalis
    Christofides, Athanasios
    Kolokotroni, Nedi
    Ellinas, Georgios
    IEEE ACCESS, 2024, 12 : 12976 - 12991
  • [25] RESOURCE-CONSTRAINED PROJECT SCHEDULING - STATE OF ART
    HERROELEN, WS
    OPERATIONAL RESEARCH QUARTERLY, 1972, 23 (03) : 261 - +
  • [26] A matheuristic for the resource-constrained project scheduling problem
    Vanhoucke, Mario
    Coelho, Jose
    EUROPEAN JOURNAL OF OPERATIONAL RESEARCH, 2024, 319 (03) : 711 - 725
  • [27] Influence of learning in resource-constrained project scheduling
    Van Peteghem, Vincent
    Vanhoucke, Mario
    COMPUTERS & INDUSTRIAL ENGINEERING, 2015, 87 : 569 - 579
  • [28] A SURVEY ON THE RESOURCE-CONSTRAINED PROJECT SCHEDULING PROBLEM
    OZDAMAR, L
    ULUSOY, G
    IIE TRANSACTIONS, 1995, 27 (05) : 574 - 586
  • [29] Extensions of the resource-constrained project scheduling problem
    Ding, Hongyan
    Zhuang, Cunbo
    Liu, Jianhua
    AUTOMATION IN CONSTRUCTION, 2023, 153
  • [30] Resource-Constrained Project Scheduling in Hazardous Environment
    Li, Shuai
    Zhang, Zhicong
    Hu, Kaishun
    Zhao, Shaoyong
    Yan, Xiaohui
    2017 IEEE INTERNATIONAL CONFERENCE ON INDUSTRIAL ENGINEERING AND ENGINEERING MANAGEMENT (IEEM), 2017, : 2266 - 2270