MIP models for resource-constrained project scheduling with flexible resource profiles

被引:81
|
作者
Naber, Anulark [1 ]
Kolisch, Rainer [1 ]
机构
[1] Tech Univ Munich, TUM Sch Management, D-80333 Munich, Germany
关键词
Project scheduling; Flexible profiles; Principal resources; Dependent resources; Discrete-time models; TRADE-OFF PROBLEM; LIMITED RESOURCES; BOUND APPROACH; NETWORKS; BRANCH; ALGORITHM; SEARCH;
D O I
10.1016/j.ejor.2014.05.036
中图分类号
C93 [管理学];
学科分类号
12 ; 1201 ; 1202 ; 120202 ;
摘要
This paper addresses the resource-constrained project scheduling problem with flexible resource profiles (FRCPSP). Such a problem often arises in many real-world applications, in which the resource usage of an activity is not merely constant, but can be adjusted from period to period. The FRCPSP is, therefore, to simultaneously determine the start time, the resource profile, and the duration of each activity in order to minimize the makespan, subject to precedence relationships, limited availability of multiple resources, and restrictions on resource profiles. We propose four discrete-time model formulations and compare their model efficiency in terms of solution quality and computational times. Both preprocessing and priority-based heuristic methods are also applied to compute both upper and lower bounds of the makespan. Our comparative results show significant dominance of one of the models, the so-called "variable-intensity-based" model, in both solution quality and runtimes. (C) 2014 Elsevier B.V. All rights reserved.
引用
收藏
页码:335 / 348
页数:14
相关论文
共 50 条
  • [41] Pre-emption in resource-constrained project scheduling
    Ballestin, Francisco
    Valls, Vicente
    Quintanilla, Sacramento
    EUROPEAN JOURNAL OF OPERATIONAL RESEARCH, 2008, 189 (03) : 1136 - 1152
  • [42] A competitive genetic algorithm for resource-constrained project scheduling
    Hartmann, S
    NAVAL RESEARCH LOGISTICS, 1998, 45 (07) : 733 - 750
  • [43] MILP Formulation for Resource-Constrained Project Scheduling Problems
    Kyriakidis, Thomas S.
    Kopanos, Georgios M.
    Georgiadis, Michael C.
    21ST EUROPEAN SYMPOSIUM ON COMPUTER AIDED PROCESS ENGINEERING, 2011, 29 : 880 - 884
  • [44] The proactive and reactive resource-constrained project scheduling problem
    Morteza Davari
    Erik Demeulemeester
    Journal of Scheduling, 2019, 22 : 211 - 237
  • [45] Ant colony optimization for resource-constrained project scheduling
    Merkle, D
    Middendorf, M
    Schmeck, H
    IEEE TRANSACTIONS ON EVOLUTIONARY COMPUTATION, 2002, 6 (04) : 333 - 346
  • [46] Periodically aggregated resource-constrained project scheduling problem
    Morin, Pierre-Antoine
    Artigues, Christian
    Hait, Alain
    EUROPEAN JOURNAL OF INDUSTRIAL ENGINEERING, 2017, 11 (06) : 792 - 817
  • [47] Network decomposition techniques for resource-constrained project scheduling
    Sprecher, A
    JOURNAL OF THE OPERATIONAL RESEARCH SOCIETY, 2002, 53 (04) : 405 - 414
  • [48] A Neurogenetic approach for the resource-constrained project scheduling problem
    Agarwal, Anurag
    Colak, Selcuk
    Erenguc, Selcuk
    COMPUTERS & OPERATIONS RESEARCH, 2011, 38 (01) : 44 - 50
  • [49] Genetic algorithm for the resource-constrained project scheduling problem
    E. N. Goncharov
    V. V. Leonov
    Automation and Remote Control, 2017, 78 : 1101 - 1114
  • [50] New strategies for stochastic resource-constrained project scheduling
    Salim Rostami
    Stefan Creemers
    Roel Leus
    Journal of Scheduling, 2018, 21 : 349 - 365