Fuzzy project scheduling models under inflation condition

被引:2
|
作者
Wang, HF [1 ]
Fu, CC [1 ]
机构
[1] NATL TSING HUA UNIV,DEPT IND ENGN,HSINCHU 30043,TAIWAN
关键词
fuzzy set theory; project scheduling; inflation; NETWORK ANALYSIS; PERT;
D O I
10.1142/S0218488596000275
中图分类号
TP18 [人工智能理论];
学科分类号
081104 ; 0812 ; 0835 ; 1405 ;
摘要
The paper defines four fuzzy project scheduling models under inflation condition without or with budget limit. The activity time is described by fuzzy relation or fuzzy variables. The models can be solved in the forms of crisp LP or NLP after using the concept of alpha-cut.
引用
收藏
页码:497 / 514
页数:18
相关论文
共 50 条
  • [41] Minslack and kangaroo algorithms for fuzzy project scheduling problems
    Atli, Omer
    Kahraman, Cengiz
    Journal of Multiple-Valued Logic and Soft Computing, 2012, 20 (1-2) : 189 - 219
  • [42] Flow Models for Project Scheduling with Transfer Delays
    Quilliot, Alain
    Toussaint, Helene
    2012 FEDERATED CONFERENCE ON COMPUTER SCIENCE AND INFORMATION SYSTEMS (FEDCSIS), 2012, : 439 - 446
  • [43] Project scheduling: Recent models, algorithms and applications
    Rayward-Smith, VJ
    JOURNAL OF THE OPERATIONAL RESEARCH SOCIETY, 2001, 52 (05) : 602 - 603
  • [45] A fuzzy pert approach to evaluate plant construction project scheduling risk under uncertain resources capacity
    Hsiau, Hsian Jong
    Lin, Chun Wei R.
    JOURNAL OF INDUSTRIAL ENGINEERING AND MANAGEMENT-JIEM, 2009, 2 (01): : 31 - 47
  • [46] Models and algorithms for fuzzy random scheduling problems
    Jin, P
    PROCEEDINGS OF THE 2004 INTERNATIONAL CONFERENCE ON MACHINE LEARNING AND CYBERNETICS, VOLS 1-7, 2004, : 1920 - 1925
  • [47] FUZZY ASPECTS OF FORESTRY HARVEST SCHEDULING MODELS
    PICKENS, JB
    HOF, JG
    FUZZY SETS AND SYSTEMS, 1991, 44 (03) : 469 - 470
  • [48] Fuzzy system models for aggregate scheduling analysis
    Turksen, IB
    Zarandi, MHF
    INTERNATIONAL JOURNAL OF APPROXIMATE REASONING, 1998, 19 (1-2) : 119 - 143
  • [49] Chance constrained project scheduling under risk
    Zafra-Cabeza, A
    Ridao, MA
    Camacho, EF
    2004 IEEE INTERNATIONAL CONFERENCE ON SYSTEMS, MAN & CYBERNETICS, VOLS 1-7, 2004, : 1789 - 1794
  • [50] Construction Project Scheduling with Time, Cost, and Material Restrictions Using Fuzzy Mathematical Models and Critical Path Method
    Castro-Lacouture, Daniel
    Suer, Gursel A.
    Gonzalez-Joaqui, Julian
    Yates, J. K.
    JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT, 2009, 135 (10) : 1096 - 1104