A new scheduling technique for the resource-constrained project scheduling problem with discounted cash flows

被引:38
|
作者
Leyman, Pieter [1 ]
Vanhoucke, Mario [1 ,2 ,3 ]
机构
[1] Univ Ghent, Fac Econ & Business Adm, B-9000 Ghent, Belgium
[2] Vlerick Business Sch, Operat & Technol Management Ctr, Ghent, Belgium
[3] UCL, Dept Management Sci & Innovat, London, England
关键词
genetic algorithm; resource-constrained project scheduling; net present value; NET PRESENT VALUE; GENETIC ALGORITHM; BOUND PROCEDURE; MODELS; CLASSIFICATION; SUBJECT; SEARCH;
D O I
10.1080/00207543.2014.980463
中图分类号
T [工业技术];
学科分类号
08 ;
摘要
In this paper, we discuss the resource-constrained project scheduling problem with discounted cash flows. We introduce a new schedule construction technique which moves sets of activities to improve the project net present value and consists of two steps. In particular, the inclusion of individual activities into sets, which are then moved together, is crucial in both steps. The first step groups the activities based on the predecessors and successors in the project network, and adds these activities to a set based on their finish time and cash flow. The second step on the contrary does so based on the neighbouring activities in the schedule, which may but need not include precedence related activities. The proposed scheduling method is implemented in a genetic algorithm metaheuristic and we employ a penalty function to improve the algorithm's feasibility with respect to a tight deadline. All steps of the proposed solution methodology are tested in detail and an extensive computational experiment shows that our results are competitive with existing work.
引用
收藏
页码:2771 / 2786
页数:16
相关论文
共 50 条
  • [41] Genetic algorithm for the resource-constrained project scheduling problem
    Goncharov, E. N.
    Leonov, V. V.
    AUTOMATION AND REMOTE CONTROL, 2017, 78 (06) : 1101 - 1114
  • [42] A multiobjective resource-constrained project-scheduling problem
    Ben Abdelaziz, Fouad
    Krichen, Saoussen
    Dridi, Olfa
    SYMBOLIC AND QUANTITATIVE APPROACHES TO REASONING WITH UNCERTAINTY, PROCEEDINGS, 2007, 4724 : 719 - +
  • [43] On the summary measures for the resource-constrained project scheduling problem
    Van Eynde, Rob
    Vanhoucke, Mario
    Coelho, Jose
    ANNALS OF OPERATIONS RESEARCH, 2024, 337 (02) : 593 - 625
  • [44] The proactive and reactive resource-constrained project scheduling problem
    Davari, Morteza
    Demeulemeester, Erik
    JOURNAL OF SCHEDULING, 2019, 22 (02) : 211 - 237
  • [45] Evaluation of Heuristics for a Resource-Constrained Project Scheduling Problem
    Zhong, Shisheng
    Fu, Xuyun
    Lin, Lin
    Wang, Guolei
    MACHINING AND ADVANCED MANUFACTURING TECHNOLOGY X, 2010, 431-432 : 122 - 125
  • [46] The preemptive stochastic resource-constrained project scheduling problem
    Creemers, Stefan
    EUROPEAN JOURNAL OF OPERATIONAL RESEARCH, 2019, 277 (01) : 238 - 247
  • [47] New Benchmark Results for the Stochastic Resource-Constrained Project Scheduling Problem
    Leus, Roel
    Rostami, Salim
    Creemers, Stefan
    2015 IEEE INTERNATIONAL CONFERENCE ON INDUSTRIAL ENGINEERING AND ENGINEERING MANAGEMENT (IEEM), 2015, : 204 - 208
  • [48] New meta-heuristics for the resource-constrained project scheduling problem
    Lim, Andrew
    Ma, Hong
    Rodrigues, Brian
    Tan, Sun Teck
    Xiao, Fei
    FLEXIBLE SERVICES AND MANUFACTURING JOURNAL, 2013, 25 (1-2) : 48 - 73
  • [49] New meta-heuristics for the resource-constrained project scheduling problem
    Andrew Lim
    Hong Ma
    Brian Rodrigues
    Sun Teck Tan
    Fei Xiao
    Flexible Services and Manufacturing Journal, 2013, 25 : 48 - 73
  • [50] A reactive scheduling approach for the resource-constrained project scheduling problem with dynamic resource disruption
    Xu, Jiaojiao
    Bai, Sijun
    KYBERNETES, 2024, 53 (06) : 2007 - 2028