Royalty Analysis for BOT Projects Based on The Negotiation Viewpoint

被引:0
|
作者
Kang, Chao-Chung [1 ]
Feng, Cheng-Min [2 ]
Kuo, Chiu-Yen [2 ]
机构
[1] Providence Univ, Dept Business Adm, Shalu, Taichung Hsien, Taiwan
[2] Natl Chiao Tung Univ, Inst Traff & Transportat, Taipei, Taiwan
关键词
BOT; royalty; negotiation; bi-level programming;
D O I
10.1109/IEEM.2009.5373178
中图分类号
T [工业技术];
学科分类号
08 ;
摘要
This study constructs three royalty negotiation models, including the lump-sum royalty, operational revenue-based royalty, and operational output-based royalty, using the bi-level programming approach. In addition, this paper also develops the iterative algorithm for bi-level programming problem for the government and the private sector. A number of factors were incorporated into this algorithm including concession rate, time value discount rate, learning rate and number of negotiations.
引用
收藏
页码:1820 / +
页数:2
相关论文
共 50 条
  • [41] Negotiation characteristics in brownfield redevelopment projects
    Yousefi, Saied
    Hipel, Keith W.
    Hegazy, Tarek
    Witmer, James A.
    Gray, Peter
    2007 IEEE INTERNATIONAL CONFERENCE ON SYSTEMS, MAN AND CYBERNETICS, VOLS 1-8, 2007, : 3651 - +
  • [43] Risk Management in Turkish Transport BOT Projects
    Ozcan, Ismail Cagri
    EUROPEAN TRANSPORT-TRASPORTI EUROPEI, 2016, (62):
  • [44] Assessing Lifecycle Success of Petrochemical Projects–based on Client’s Viewpoint
    M. Shariatfar
    H. Beigi
    M. M. Mortaheb
    KSCE Journal of Civil Engineering, 2019, 23 : 21 - 28
  • [45] Shadow tolling model of expressway BOT projects
    Dai Dashuang
    Yang Weihua
    PROCEEDINGS OF 20TH IPMA WORLD CONGRESS ON PROJECT MANAGEMENT, VOLS 1 AND 2, 2006, : 101 - 105
  • [46] A grey evaluation model on bidders for BOT projects
    Yu, YH
    Shan, MY
    Proceedings of 2005 International Conference on Machine Learning and Cybernetics, Vols 1-9, 2005, : 3433 - 3437
  • [47] An integrated method for ranking of risk in BOT projects
    Askari, M.
    Shokrizade, H. R.
    2ND WORLD CONFERENCE ON BUSINESS, ECONOMICS AND MANAGEMENT, 2014, 109 : 1390 - 1394
  • [48] Ownership Structure and Contract Efficiency in BOT Projects
    Shi, Lei
    Xiong, Songping
    Dai, Dashuang
    2008 4TH INTERNATIONAL CONFERENCE ON WIRELESS COMMUNICATIONS, NETWORKING AND MOBILE COMPUTING, VOLS 1-31, 2008, : 7545 - 7548
  • [49] Application of BOT system for infrastructure projects in China
    Shen, LY
    Lee, RKH
    Zhang, ZH
    JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT-ASCE, 1996, 122 (04): : 319 - 323
  • [50] An Alternative Method for Determining BOT Concession Period Negotiation Interval
    Wu, Min
    EBM 2010: INTERNATIONAL CONFERENCE ON ENGINEERING AND BUSINESS MANAGEMENT, VOLS 1-8, 2010, : 2002 - 2004