Capacitated lot sizing with parallel machines, sequence-dependent setups, and a common setup operator

被引:24
|
作者
Tempelmeier, Horst [1 ]
Copil, Karina [1 ]
机构
[1] Univ Cologne, Dept Supply Chain Management & Prod, Cologne, Germany
关键词
Lotsizing; Setup operator; Shelf life; Parallel machines; TIMES; RESOURCES; WINDOWS;
D O I
10.1007/s00291-015-0410-2
中图分类号
C93 [管理学]; O22 [运筹学];
学科分类号
070105 ; 12 ; 1201 ; 1202 ; 120202 ;
摘要
In this paper, we consider a special variant of a capacitated dynamic lot sizing problem which, despite its practical relevance, has not been treated sufficiently in the literature. In addition to the significant complexity introduced by the sequence dependency of setup times, the problem is further complicated by the fact that there is only one single setup operator which is responsible for all setups on all machines. Hence, the multi-machine problem cannot be decomposed into multiple single machine problems, as the setup operations must be coordinated among the different machines. In addition, lots are produced in batches whereby the processing time of a lot is a step-wise function of the number of batches per lot. Due to perishability and quarantine issues, time windows for the production are given. We formulate a big-bucket lot sizing model and apply MIP-based heuristics to two industrial data sets.
引用
收藏
页码:819 / 847
页数:29
相关论文
共 50 条
  • [41] Scheduling jobs on dynamic parallel machines with sequence-dependent setup times
    Lee, Zne-Jung
    Lin, Shih-Wei
    Ying, Kuo-Ching
    INTERNATIONAL JOURNAL OF ADVANCED MANUFACTURING TECHNOLOGY, 2010, 47 (5-8): : 773 - 781
  • [42] Scheduling the capacitated identical parallel machines problem: a new formulation with sequence-dependent setup costs and different due dates
    Esmaelian, Majid
    Sobhani, Ahmad
    Shahmoradi, Hadi
    Mohammadi, Milad
    EUROPEAN JOURNAL OF INDUSTRIAL ENGINEERING, 2021, 15 (05) : 643 - 674
  • [43] A hybrid Lagrangian-simulated annealing-based heuristic for the parallel-machine capacitated lot-sizing and scheduling problem with sequence-dependent setup times
    Xiao, Jing
    Yang, Huasheng
    Zhang, Canrong
    Zheng, Li
    Gupta, Jatinder N. D.
    COMPUTERS & OPERATIONS RESEARCH, 2015, 63 : 72 - 82
  • [44] Joint rolling-horizon scheduling of materials processing and lot-sizing with sequence-dependent setups
    de Araujo, Silvio A.
    Arenales, Marcos N.
    Clark, Alistair R.
    JOURNAL OF HEURISTICS, 2007, 13 (04) : 337 - 358
  • [45] Joint rolling-horizon scheduling of materials processing and lot-sizing with sequence-dependent setups
    Silvio A. de Araujo
    Marcos N. Arenales
    Alistair R. Clark
    Journal of Heuristics, 2007, 13 : 337 - 358
  • [46] Multiple machine continuous setup lotsizing with sequence-dependent setups
    Almada-Lobo, Bernardo
    Klabjan, Diego
    Carravilla, Maria Antonia
    Oliveira, Jose F.
    COMPUTATIONAL OPTIMIZATION AND APPLICATIONS, 2010, 47 (03) : 529 - 552
  • [47] Capacitated Lot-Sizing and Scheduling with Parallel Machines, Back-Orders, and Setup Carry-Over
    Quadt, Daniel
    Kuhn, Heinrich
    NAVAL RESEARCH LOGISTICS, 2009, 56 (04) : 366 - 384
  • [48] MULTIPLE-STAGE MULTIPLE-MACHINE CAPACITATED LOT-SIZING AND SCHEDULING WITH SEQUENCE-DEPENDENT SETUP: A CASE STUDY IN THE WHEEL INDUSTRY
    Deeratanasrikul, Lalida
    Mizuno, Shinji
    JOURNAL OF INDUSTRIAL AND MANAGEMENT OPTIMIZATION, 2017, 13 (01) : 411 - 426
  • [49] Three stage dynamic heuristic for multiple plants capacitated lot sizing with sequence-dependent transient costs
    Abdullah, Sari
    Shamayleh, Abdulrahim
    Ndiaye, Malick
    COMPUTERS & INDUSTRIAL ENGINEERING, 2019, 127 : 1024 - 1036
  • [50] Multiple machine continuous setup lotsizing with sequence-dependent setups
    Bernardo Almada-Lobo
    Diego Klabjan
    Maria Antónia Carravilla
    José F. Oliveira
    Computational Optimization and Applications, 2010, 47 : 529 - 552