The Fuzzy Project Scheduling Problem with Minimal Generalized Precedence Relations

被引:36
|
作者
Luis Ponz-Tienda, Jose [1 ]
Pellicer, Eugenio [2 ]
Benlloch-Marco, Javier [3 ]
Andres-Romano, Carlos [4 ]
机构
[1] Univ Los Andes, Dept Civil & Environm Engn, Bogota, Colombia
[2] Univ Politecn Valencia, Sch Civil Engn, Valencia 46022, Spain
[3] Univ Politecn Valencia, Dept Architectural Construct, Valencia 46022, Spain
[4] Univ Politecn Valencia, Dept Business Adm, Valencia 46022, Spain
关键词
NEURAL DYNAMICS MODEL; ACTIVITY NETWORKS; MANAGEMENT; OPTIMIZATION; COST; TIME; CRITICALITY; SIMULATION; VARIABLES; NUMBERS;
D O I
10.1111/mice.12166
中图分类号
TP39 [计算机的应用];
学科分类号
081203 ; 0835 ;
摘要
In scheduling, estimations are affected by the imprecision of limited information on future events, and the reduction in the number and level of detail of activities. Overlapping of processes and activities requires the study of their continuity, along with analysis of the risks associated with imprecision. In this line, this article proposes a fuzzy heuristic model for the Project Scheduling Problem with flows and minimal feeding, time and work Generalized Precedence Relations with a realistic approach to overlapping, in which the continuity of processes and activities is allowed in a discretionary way. This fuzzy algorithm handles the balance of process flows, and computes the optimal fragmentation of tasks, avoiding the interruption of the critical path and reverse criticality. The goodness of this approach is tested on several problems found in the literature; furthermore, an example of a 15-story building was used to compare the better performance of the algorithm implemented in Visual Basic for Applications (Excel) over that same example input in Primavera (c) P6 Professional V8.2.0, using five different scenarios.
引用
收藏
页码:872 / 891
页数:20
相关论文
共 50 条
  • [31] Resource levelling in project scheduling with generalized precedence relationships and variable execution intensities
    Bianco, Lucio
    Caramia, Massimiliano
    Giordani, Stefano
    OR SPECTRUM, 2016, 38 (02) : 405 - 425
  • [32] Resource levelling in project scheduling with generalized precedence relationships and variable execution intensities
    Lucio Bianco
    Massimiliano Caramia
    Stefano Giordani
    OR Spectrum, 2016, 38 : 405 - 425
  • [33] Method of Project Scheduling under Fuzzy Estimation of Durations and Precedence Relationships of Activities
    Tseng, H. S.
    Chiou, H. W.
    CRIOCM2009: INTERNATIONAL SYMPOSIUM ON ADVANCEMENT OF CONSTRUCTION MANAGEMENT AND REAL ESTATE, VOLS 1-6, 2009, : 1914 - 1922
  • [34] Two-dedicated-machine scheduling problem with precedence relations to minimize makespan
    Gafarov, Evgeny
    Dolgui, Alexandre
    OPTIMIZATION LETTERS, 2014, 8 (04) : 1443 - 1451
  • [35] Two-dedicated-machine scheduling problem with precedence relations to minimize makespan
    Evgeny Gafarov
    Alexandre Dolgui
    Optimization Letters, 2014, 8 : 1443 - 1451
  • [36] PRECEDENCE RELATIONS OF THE FLOWSHOP PROBLEM
    SZWARC, W
    OPERATIONS RESEARCH, 1981, 29 (02) : 400 - 411
  • [37] REDUCING RENEWABLE RESOURCE DEMAND FLUCTUATION USING SOFT PRECEDENCE RELATIONS IN PROJECT SCHEDULING
    Jaskowski, Piotr
    Biruk, Slawomir
    JOURNAL OF CIVIL ENGINEERING AND MANAGEMENT, 2018, 24 (04) : 355 - 363
  • [38] Preprocessing the Discrete Time-Cost Tradeoff Problem with Generalized Precedence Relations
    Wei, Hanying
    Su, Zhixiong
    Zhang, Yuan
    MATHEMATICAL PROBLEMS IN ENGINEERING, 2020, 2020
  • [39] MINIMAL AND MAXIMAL SOLUTIONS OF A DECOMPOSITION PROBLEM OF FUZZY RELATIONS
    DINOLA, A
    SESSA, S
    PEDRYCZ, W
    HIGASHI, M
    INTERNATIONAL JOURNAL OF GENERAL SYSTEMS, 1985, 11 (02) : 103 - 116
  • [40] A fuzzy time-dependent project scheduling problem
    Huang, Wei
    Oh, Sung-Kwun
    Pedrycz, Witold
    INFORMATION SCIENCES, 2013, 246 : 100 - 114