Resource levelling in project scheduling with generalized precedence relationships and variable execution intensities

被引:0
|
作者
Lucio Bianco
Massimiliano Caramia
Stefano Giordani
机构
[1] University of Rome “Tor Vergata”,Dipartimento di Ingegneria dell’Impresa
来源
OR Spectrum | 2016年 / 38卷
关键词
Project scheduling; Generalized precedence relationships; Resource levelling;
D O I
暂无
中图分类号
学科分类号
摘要
We study the problem of levelling resources in a project with generalized precedence relationships, given a deadline for the completion of all the activities and variable execution intensities and flexible durations of the activities. Variable execution intensities have been taken into account firstly by Kis (Math Program 103(3):515–539, 2005) applied to a real world scenario in which, due to the physical characteristics of some manufacturing processes, the effort associated with a certain activity for its execution may vary over time. Generalized precedence relationships and variable intensity execution and duration have not been dealt with together to the best of our knowledge. For this novel problem we propose a mixed-integer linear programming formulation, a lower bound based on Lagrangian relaxation, and a branch and bound algorithm. Computational results on known benchmarks are provided.
引用
收藏
页码:405 / 425
页数:20
相关论文
共 50 条
  • [1] Resource levelling in project scheduling with generalized precedence relationships and variable execution intensities
    Bianco, Lucio
    Caramia, Massimiliano
    Giordani, Stefano
    OR SPECTRUM, 2016, 38 (02) : 405 - 425
  • [2] Ant colony optimization for resource-constrained project scheduling with generalized precedence relations
    Luo, SP
    Wang, C
    Wang, JW
    15TH IEEE INTERNATIONAL CONFERENCE ON TOOLS WITH ARTIFICIAL INTELLIGENCE, PROCEEDINGS, 2003, : 284 - 289
  • [3] The effectiveness of resource levelling tools for Resource Constraint Project Scheduling Problem
    Kastor, A.
    Sirakoulis, K.
    INTERNATIONAL JOURNAL OF PROJECT MANAGEMENT, 2009, 27 (05) : 493 - 500
  • [4] The multi-mode resource-constrained project scheduling problem with generalized precedence relations
    De Reyck, B
    Herroelen, W
    EUROPEAN JOURNAL OF OPERATIONAL RESEARCH, 1999, 119 (02) : 538 - 556
  • [5] A new lower bound for the resource-constrained project scheduling problem with generalized precedence relations
    Bianco, Lucio
    Caramia, Massimiliano
    COMPUTERS & OPERATIONS RESEARCH, 2011, 38 (01) : 14 - 20
  • [6] Integrated resource leveling and material procurement with variable execution intensities
    Kazemi, Sajad
    Davari-Ardakani, Hamed
    COMPUTERS & INDUSTRIAL ENGINEERING, 2020, 148
  • [7] A branch-and-bound procedure for the resource-constrained project scheduling problem with generalized precedence relations
    De Reyck, B
    Herroelen, W
    EUROPEAN JOURNAL OF OPERATIONAL RESEARCH, 1998, 111 (01) : 152 - 174
  • [8] An Improved Cuckoo Search Algorithm for Resource-Constrained Project Scheduling Problem with Generalized Precedence Relations
    Jin, Yidong
    Nie, Hui
    Duan, Pengfei
    Yang, Huihua
    PROCEEDINGS OF THE 2016 12TH WORLD CONGRESS ON INTELLIGENT CONTROL AND AUTOMATION (WCICA), 2016, : 1086 - 1090
  • [9] The Fuzzy Project Scheduling Problem with Minimal Generalized Precedence Relations
    Luis Ponz-Tienda, Jose
    Pellicer, Eugenio
    Benlloch-Marco, Javier
    Andres-Romano, Carlos
    COMPUTER-AIDED CIVIL AND INFRASTRUCTURE ENGINEERING, 2015, 30 (11) : 872 - 891
  • [10] Zero-One Formulation for a Partial Resource-Constrained Project Scheduling Problem with Generalized Precedence Relations
    Su, Zhi-Xiong
    Wei, Han-Ying
    Zou, Xin
    Qi, Jian-Xun
    JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT, 2019, 145 (03)