A Heuristic Approach for Rework-Based Product Design Project Scheduling Problem

被引:0
|
作者
lu, Rui [1 ]
Li, Linying [2 ]
机构
[1] Northeastern Univ, Key Lab Proc Ind Automat, Minist Educ, Shenyang 110004, Peoples R China
[2] Chinese Acad Sci, Shenyang Inst Automat, Shenyang 110016, Peoples R China
关键词
Stochastic RCPSP; Overlap; Iteration; Product Design Project; Simulation;
D O I
10.1109/CCDC.2008.4597565
中图分类号
TP [自动化技术、计算机技术];
学科分类号
0812 ;
摘要
Product design project scheduling is a complex problem which involves a large number of tasks and information exchanges in a stochastic, resource-constrained project network where iteration and overlap between tasks often take place. The classical determined RCPSP which has been widely studied is based on assumption of fixed duration of tasks and zero-lag finish-start precedence relationships in acyclic AON network. Very little efforts have been made in project scheduling with stochastic duration, especially in cyclic network with rework possibility. This paper presents an approach for rework-based product design project scheduling problem, taking overlap and iteration which are inherent nature in PDP into account. We consider this problem under the assumption that task duration can be modeled by a triangle distribution and can be sampled by simulation techniques. Three priority rules which are widely used in solving deterministic RCPSP are modified by replacing deterministic duration by a dynamic one. Finally computational experiments for this heuristic approach are provided.
引用
下载
收藏
页码:1486 / 1491
页数:6
相关论文
共 50 条
  • [41] A Heuristic Approach for Vehicle Scheduling Problem with Time and Capacity Constraints
    Masoud, Mohamed
    Lee, Sanghoon
    Belkasim, Saeid
    2016 UKSIM-AMSS 18TH INTERNATIONAL CONFERENCE ON COMPUTER MODELLING AND SIMULATION (UKSIM), 2016, : 230 - 234
  • [42] Heuristic approach for broadcast scheduling, problem in wireless mesh networks
    Arivudainambi, D.
    Rekha, D.
    AEU-INTERNATIONAL JOURNAL OF ELECTRONICS AND COMMUNICATIONS, 2014, 68 (06) : 489 - 495
  • [43] ADDRESSING N-1 SCHEDULING PROBLEM - HEURISTIC APPROACH
    DAVIS, KR
    WALTERS, JE
    COMPUTERS & OPERATIONS RESEARCH, 1977, 4 (02) : 89 - 100
  • [44] A genetic programming hyper-heuristic approach for the multi-skill resource constrained project scheduling problem
    Lin, Jian
    Zhu, Lei
    Gao, Kaizhou
    EXPERT SYSTEMS WITH APPLICATIONS, 2020, 140
  • [45] A branch and bound based heuristic for multi-product resource constrained scheduling problem in FMS environment
    Shanker, K
    Modi, BK
    EUROPEAN JOURNAL OF OPERATIONAL RESEARCH, 1999, 113 (01) : 80 - 90
  • [46] An Integrated Differential Evolution-based Heuristic Method for Product Family Design Problem
    Ali, Ismail M.
    Turan, Hasan H.
    Chakrabortty, Ripon K.
    Elsawah, Sondoss
    Ryan, Michael J.
    2021 IEEE CONGRESS ON EVOLUTIONARY COMPUTATION (CEC 2021), 2021, : 25 - 32
  • [47] A heuristic approach for resource constrained project scheduling with uncertain activity durations
    Bruni, M. E.
    Beraldi, P.
    Guerriero, F.
    Pinto, E.
    COMPUTERS & OPERATIONS RESEARCH, 2011, 38 (09) : 1305 - 1318
  • [48] A GENERALIZED HEURISTIC LEARNING APPROACH TO PROJECT SCHEDULING PROBLEMS WITH RESOURCE CONSTRAINTS
    Shue, Li-Yen
    Li, Sheng-Tun
    JOURNAL OF INDUSTRIAL AND PRODUCTION ENGINEERING, 2008, 25 (03) : 204 - 214
  • [49] Critical Chain Design Structure Matrix Method for Construction Project Scheduling under Rework Scenarios
    Ma, Guofeng
    Hao, Keke
    Xiao, Yu
    Zhu, Tiancheng
    MATHEMATICAL PROBLEMS IN ENGINEERING, 2019, 2019
  • [50] A heuristic project scheduling approach for quick response to maritime disaster rescue
    Yan, Liang
    Jinsong, Bao
    Xiaofeng, Hu
    Ye, Jin
    INTERNATIONAL JOURNAL OF PROJECT MANAGEMENT, 2009, 27 (06) : 620 - 628