A heuristic solution framework for the resource-constrained multi-aircraft scheduling problem with transfer of resources and aircraft

被引:1
|
作者
Su, Xichao [1 ]
Cui, Rongwei [1 ]
Li, Changjiu [1 ]
Han, Wei [1 ]
Liu, Jie [2 ]
机构
[1] Naval Aviat Univ, Yantai 264001, Shandong, Peoples R China
[2] Acad Mil Sci, War Res Inst, Beijing 100850, Peoples R China
关键词
Project scheduling; Heuristics; Flight deck operation; Carrier aircraft; GENETIC ALGORITHM; RULES;
D O I
10.1016/j.eswa.2023.120430
中图分类号
TP18 [人工智能理论];
学科分类号
081104 ; 0812 ; 0835 ; 1405 ;
摘要
Efficient and feasible flight deck operation scheduling plan is of great significance for improving the sortie rate of carrier aircraft. Oxygen filling, fueling, and other operations of each carrier aircraft are executed in the pre-flight preparation stage. Different personnel, support equipments, and supply resources, are required while different operations are being executed. To date, most approaches proposed in the literature are based on the unrealistic assumption that the transfer process of carrier aircraft can be ignored. To close this gap, the resource-constrained multi-aircraft scheduling problem on the flight deck is examined in this study. The main contributions of the study are as follows. First, by considering the transfer process of aircraft on the flight deck operations, the model formulation of resource-constrained multi-aircraft scheduling problem is established. Second, the parallel and serial scheduling framework are proposed, where parking spot priority rules and resource allocation rules are presented to select the most suitable resources. Third, a modified genetic programming algorithm is presented for obtaining efficient activity priority rules. Fourth, the well-performed scheduling framework, priority rules, and allocation rules are selected by conducting computational experiments. Furthermore, experiment results show that the parallel scheduling framework outperforms the serial framework in most experiments (average out -performance is 10.19%), and the parking spot priority rules slightly affect the serial scheduling framework.
引用
收藏
页数:16
相关论文
共 50 条
  • [1] A Heuristic Algorithm for a Robust Resource-Constrained Project Scheduling Problem with Multi-Skilled Resources
    You, Weibao
    Xu, Zhe
    Lu, Ming
    COMPUTING IN CIVIL ENGINEERING 2023-VISUALIZATION, INFORMATION MODELING, AND SIMULATION, 2024, : 154 - 162
  • [2] GENETIC ALGORITHMS FOR THE RESOURCE-CONSTRAINED PROJECT SCHEDULING PROBLEM IN AIRCRAFT HEAVY MAINTENANCE
    Pimapunsri, Kusol
    Weeranant, Darawan
    Riel, Andreas
    SURANAREE JOURNAL OF SCIENCE AND TECHNOLOGY, 2021, 28 (06):
  • [3] Comparison of Heuristic Priority Rules in the Solution of the Resource-Constrained Project Scheduling Problem
    Turkakin, Osman Hurol
    Arditi, David
    Manisali, Ekrem
    SUSTAINABILITY, 2021, 13 (17)
  • [4] Approximate solution of a resource-constrained scheduling problem
    Sirdey, Renaud
    Carlier, Jacques
    Nace, Dritan
    JOURNAL OF HEURISTICS, 2009, 15 (01) : 1 - 17
  • [5] Approximate solution of a resource-constrained scheduling problem
    Renaud Sirdey
    Jacques Carlier
    Dritan Nace
    Journal of Heuristics, 2009, 15 : 1 - 17
  • [6] A solution framework for the multi-mode resource-constrained cross-dock scheduling problem
    Hermel, Dror
    Hasheminia, Hamed
    Adler, Nicole
    Fry, Michael J.
    OMEGA-INTERNATIONAL JOURNAL OF MANAGEMENT SCIENCE, 2016, 59 : 157 - 170
  • [7] A heuristic solution framework for the resource constrained (multi-)project scheduling problem with sequence-dependent transfer times
    Krueger, Doreen
    Scholl, Armin
    EUROPEAN JOURNAL OF OPERATIONAL RESEARCH, 2009, 197 (02) : 492 - 508
  • [8] HEURISTIC FRAMEWORK FOR THE RESOURCE CONSTRAINED MULTI-PROJECT SCHEDULING PROBLEM
    KIM, SO
    SCHNIEDERJANS, MJ
    COMPUTERS & OPERATIONS RESEARCH, 1989, 16 (06) : 541 - 556
  • [9] Heuristic algorithm for flexible resource-constrained project scheduling problem
    Jia, Yan
    Wang, Zhimin
    Zhang, Yuegang
    Jisuanji Jicheng Zhizao Xitong/Computer Integrated Manufacturing Systems, CIMS, 2015, 21 (07): : 1846 - 1855
  • [10] A NEW HEURISTIC SOLUTION METHOD IN RESOURCE-CONSTRAINED PROJECT SCHEDULING
    BELL, CE
    HAN, J
    NAVAL RESEARCH LOGISTICS, 1991, 38 (03) : 315 - 331