Raising the reliability of water conditioning systems at the Sakhalin State Regional Power Plant

被引:0
|
作者
Slesarenko V.V. [1 ]
Avdeev L.E. [2 ]
Stavniichuk L.A. [2 ]
机构
[1] Center for Boiler Updating, Far-East State Engineering University
关键词
Evaporating units; Qualityof water and steam; Reverse osmosis plants; Water balance; Water conditioning;
D O I
10.1007/s10749-006-0030-8
中图分类号
学科分类号
摘要
Results of a study of the water conditioning unit of the Sakhalin SRPP are presented. Analysis of the operating, regulating, and design documentation and of computations of the flow diagram has shown that a number of measures should be taken for stabilizing the water chemistry of the boilers and producing steam with parameters meeting the scheduled requirements. Variants of updating the WCU are considered, which are expected to raise the reliability of the system of water conditioning due to the use of membrane reverse osmosis plants in the water desalination system. © Springer Science+Business Media, Inc. 2006.
引用
收藏
页码:109 / 112
页数:3
相关论文
共 50 条
  • [31] RELIABLE FLUID POWER PITCH SYSTEMS - A REVIEW OF STATE OF THE ART FOR DESIGN AND RELIABILITY EVALUATION OF FLUID POWER SYSTEMS
    Liniger, Jesper
    Pedersen, Henrik C.
    Soltani, Mohsen
    PROCEEDINGS OF THE ASME/BATH SYMPOSIUM ON FLUID POWER AND MOTION CONTROL, 2015, 2016,
  • [32] PLANT-ENERGY CONTROL OF AIR-CONDITIONING AND CHILLED WATER-SYSTEMS
    KANWISHER, N
    PLASTICS ENGINEERING, 1984, 40 (03) : 38 - 38
  • [33] THE WATER TREATING SYSTEMS OF THE NUCLEAR-POWER-PLANT AT PAKS
    TILKY, P
    DOMA, A
    PINTER, T
    ENERGIA ES ATOMTECHNIKA, 1985, 38 (10-12): : 440 - 446
  • [34] MACROFOULING IN POWER-PLANT SERVICE WATER-SYSTEMS
    BURTON, DT
    GAREY, JF
    TRANSACTIONS OF THE AMERICAN NUCLEAR SOCIETY, 1984, 46 : 698 - 699
  • [35] Bulges in shield pipes of a TM-104A boiler with amine water treatment at the shatura state regional electric power plant
    Bogachev V.A.
    Kirilina A.V.
    Pshechenkova T.P.
    Suslov S.Yu.
    Shkolnikova B.E.
    Power Technology and Engineering, 2011, 45 (2) : 125 - 131
  • [36] Modernization of the 300-MW power generating units at the Konakovo State Regional Electric Power Plant
    Melnikov A.V.
    Avrutsky G.D.
    Lazarev M.V.
    Savenkova I.A.
    Lazareva M.V.
    Simoyu L.L.
    Gaev V.D.
    Melnikov, A.V., 1600, Springer Science and Business Media, LLC (46): : 387 - 391
  • [37] REGIONAL AND FEEDSTOCK EFFECTS ON ECONOMICS OF INTEGRATED COAL GASIFICATION POWER PLANT SYSTEMS
    AHN, YK
    BOLEZ, CA
    ABSTRACTS OF PAPERS OF THE AMERICAN CHEMICAL SOCIETY, 1977, 174 (SEP): : 50 - 50
  • [38] Multi-State Reliability Measures Analysis of Nuclear Power Plant (NPP) System
    Kumar, Amit
    Saxena, Anshumaan
    Ram, Mangey
    INTERNATIONAL JOURNAL OF RELIABILITY QUALITY AND SAFETY ENGINEERING, 2020, 27 (02)
  • [39] The testing activity at post of head of turbine shop of state regional electric power plant
    Shirokova, E.A.
    Energetik, 2002, (10): : 32 - 33
  • [40] The Effect of Alternative Power Distribution Supply to Reliability Indexes at Mahasawat Water Treatment Plant
    Kigsirisin, Soraphon
    Pussawiro, Sirawit
    Noohawm, Onurai
    2017 IEEE 30TH CANADIAN CONFERENCE ON ELECTRICAL AND COMPUTER ENGINEERING (CCECE), 2017,