On the efficient modeling and solution of the multi-mode resource-constrained project scheduling problem with generalized precedence relations

被引:0
|
作者
Alexander Schnell
Richard F. Hartl
机构
[1] University of Vienna,Department of Business Administration, Chair of Production and Operations Management
来源
OR Spectrum | 2016年 / 38卷
关键词
Project scheduling; Constraint programming; Multi-mode; Generalized precedence relations; SAT solving;
D O I
暂无
中图分类号
学科分类号
摘要
For variants of the single-mode resource-constrained project scheduling problem, state-of-the-art exact algorithms combine a Branch and Bound algorithm with principles from Constraint Programming and Boolean Satisfiability Solving. In our paper, we propose new exact approaches extending the above principles to the multi-mode RCPSP (MRCPSP) with generalized precedence relations (GPRs). More precisely, we implemented two constraint handlers cumulativemm and gprecedencemm for the optimization framework SCIP. With the latter, one can model renewable resource constraints and GPRs in the context of multi-mode activities, respectively. Moreover, they integrate domain propagation and explanation generation techniques for the above problem characteristics. We formulate three SCIP-models for the MRCPSP with GPRs, two without and one with our constraint handler gprecedencemm. Our computational results on instances from the literature with 30, 50 and 100 activities show that the addition of this constraint handler significantly strengthens the SCIP-model. Moreover, we outperform the state-of-the-art exact approach on instances with 50 activities when imposing time limits of 27 s. In addition, we close (find the optimal solution and prove its optimality for) 289 open instances and improve the best known makespan for 271 instances from the literature.
引用
收藏
页码:283 / 303
页数:20
相关论文
共 50 条
  • [21] Ant colony optimization for resource-constrained project scheduling with generalized precedence relations
    Luo, SP
    Wang, C
    Wang, JW
    15TH IEEE INTERNATIONAL CONFERENCE ON TOOLS WITH ARTIFICIAL INTELLIGENCE, PROCEEDINGS, 2003, : 284 - 289
  • [22] Multi-objective metaheuristic algorithms for the resource-constrained project scheduling problem with precedence relations
    Gomes, Helton Cristiano
    das Neves, Francisco de Assis
    Freitas Souza, Marcone Jamilson
    COMPUTERS & OPERATIONS RESEARCH, 2014, 44 : 92 - 104
  • [23] Resource-constrained project scheduling: a heuristic for the multi-mode case
    Heilmann, R
    OR SPEKTRUM, 2001, 23 (03) : 335 - 357
  • [24] Simulated Annealing for Multi-Mode Resource-Constrained Project Scheduling
    Joanna Józefowska
    Marek Mika
    Rafał Różycki
    Grzegorz Waligóra
    Jan Węglarz
    Annals of Operations Research, 2001, 102 : 137 - 155
  • [25] Modelling and Solving Multi-mode Resource-Constrained Project Scheduling
    Szeredi, Ria
    Schutt, Andreas
    PRINCIPLES AND PRACTICE OF CONSTRAINT PROGRAMMING, CP 2016, 2016, 9892 : 483 - 492
  • [26] Simulated annealing for multi-mode resource-constrained project scheduling
    Józefowska, J
    Mika, M
    Rózycki, R
    Waligóra, G
    Weglarz, J
    ANNALS OF OPERATIONS RESEARCH, 2001, 102 (1-4) : 137 - 155
  • [27] Hybrid Heuristics for Multi-mode Resource-Constrained Project Scheduling
    Tchao, Celso
    Martins, Simone L.
    LEARNING AND INTELLIGENT OPTIMIZATION, 2008, 5313 : 234 - +
  • [28] An Efficient Discrete Particle Swarm Optimization for Solving Multi-mode Resource-constrained Project Scheduling Problem
    Cui, Jianshuang
    Yu, Liruoyang
    2014 IEEE INTERNATIONAL CONFERENCE ON INDUSTRIAL ENGINEERING AND ENGINEERING MANAGEMENT (IEEM), 2014, : 858 - 862
  • [29] Using resource scarceness characteristics to solve the multi-mode resource-constrained project scheduling problem
    Vincent Van Peteghem
    Mario Vanhoucke
    Journal of Heuristics, 2011, 17 : 705 - 728
  • [30] Zero-One Formulation for a Partial Resource-Constrained Project Scheduling Problem with Generalized Precedence Relations
    Su, Zhi-Xiong
    Wei, Han-Ying
    Zou, Xin
    Qi, Jian-Xun
    JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT, 2019, 145 (03)