Research on Surface Settlement of Subway Station Construction Using Pile-Beam-Arch Approach

被引:3
|
作者
Xu, Yushan [1 ]
Tang, Bo [1 ]
Duan, Yanwei [1 ]
机构
[1] JiNan Geotech Engn Co, Jinan, Peoples R China
关键词
Pile-Beam-Arch Approach; Midas-GTS; Surface Settlement and Crustal stress;
D O I
10.1088/1755-1315/455/1/012167
中图分类号
TU [建筑科学];
学科分类号
0813 ;
摘要
The pile-beam-arch (PBA) approach is illustrated as a creative construction method in shallow-buried tunneling excavation of subway construction. Attentions have been paid to this method due to its unique advantages of construction technology. Subway station construction by using PBA approach will make disturbance to the ground surface. Research on surface deformation caused by PBA approach is of great significance to the surrounding environment and its structure. The example of subway construction in Beijing is presented as the research background, a three-dimensional model is established by using the Midas-GTS finite element numerical simulation software to simulate the practical excavation support conditions, and to analyze the surface settlement, the initial support structure settlement and crustal stress caused by PBA construction method.
引用
收藏
页数:7
相关论文
共 50 条
  • [1] Surface settlement of subway station construction using pile-beam-arch approach
    Yu, Lin
    Zhang, Dingli
    Fang, Qian
    Cao, Liqiang
    Xu, Tong
    Li, Qianqian
    TUNNELLING AND UNDERGROUND SPACE TECHNOLOGY, 2019, 90 : 340 - 356
  • [2] Ground surface settlement response to subway station construction activities using pile-beam-arch method
    Guo, Xiangyu
    Wang, Zhengzheng
    Geng, Ping
    Chen, Changjian
    Zhang, Jing
    TUNNELLING AND UNDERGROUND SPACE TECHNOLOGY, 2021, 108
  • [3] The Surface Settlement Law of Precipitation in Pile-Beam-Arch Station Adjacent to Pile Foundation
    Yunsi Liu
    Yueyuan Huang
    KSCE Journal of Civil Engineering, 2023, 27 : 1441 - 1457
  • [4] The Surface Settlement Law of Precipitation in Pile-Beam-Arch Station Adjacent to Pile Foundation
    Liu, Yunsi
    Huang, Yueyuan
    KSCE JOURNAL OF CIVIL ENGINEERING, 2023, 27 (04) : 1441 - 1457
  • [5] Analysis of stratum deformation and pile foundation response during subway station built by pile-beam-arch construction method
    School of Civil Engineering and Architecture, Beijing Jiaotong University, Beijing 100044, China
    不详
    Beijing Jiaotong Daxue Xuebao, 2008, 3 (30-36): : 30 - 36
  • [6] Numerical analysis on the mechanical performance of supporting structures and ground settlement characteristics in construction process of subway station built by Pile-Beam-Arch method
    Xinrong Liu
    Yongquan Liu
    Zhongping Yang
    Chunmei He
    KSCE Journal of Civil Engineering, 2017, 21 : 1690 - 1705
  • [7] Numerical analysis on the mechanical performance of supporting structures and ground settlement characteristics in construction process of subway station built by Pile-Beam-Arch method
    Liu, Xinrong
    Liu, Yongquan
    Yang, Zhongping
    He, Chunmei
    KSCE JOURNAL OF CIVIL ENGINEERING, 2017, 21 (05) : 1690 - 1705
  • [8] The Influence of Pile-Beam-Arch Construction on the Stratum and Station Support Structure
    Liu, Nan
    Tong, Xiao
    Chang, Longfei
    Lv, Yong
    GEOFLUIDS, 2023, 2023
  • [9] Challenges and countermeasures for using pile-beam-arch approach to enlarge large-diameter shield tunnel to subway station
    Xu, Xuezhao
    Li, Zhaoping
    Fang, Qian
    Zheng, Hao
    TUNNELLING AND UNDERGROUND SPACE TECHNOLOGY, 2020, 98
  • [10] Analysis on the Response of Ground Surface Settlement for a Metro Station during Construction Using the Pile-Beam-Arch (PBA) Method Subjected to Pore Pressure
    Xu, Fei
    Li, Li-Ping
    Zhang, Qian-Qing
    Wang, Zhe-Chao
    He, Peng
    GEO-CHINA 2016: EMERGING TECHNOLOGIES IN TUNNEL ENGINEERING, MODELING, DESIGN, CONSTRUCTION, REPAIR, AND REHABILITATION, 2016, (260): : 243 - 250