Lessons Learned in Risk Management on NCSX

被引:0
|
作者
Neilson, G. H. [1 ]
Gruber, C. O.
Harris, J. H. [2 ]
Rej, D. J. [1 ]
Simmons, R. T. [1 ]
Strykowsky, R. L. [1 ]
机构
[1] Princeton Plasma Phys Lab, POB 451,MS 38, Princeton, NJ 08543 USA
[2] Oak Ridge Natl Lab, Oak Ridge, TN 37831 USA
关键词
stellarator; NCSX; risk; management; MAGNETIC-FIELD; DESIGN; CONSTRUCTION; PHYSICS;
D O I
暂无
中图分类号
TM [电工技术]; TN [电子技术、通信技术];
学科分类号
0808 ; 0809 ;
摘要
The National Compact Stellarator Experiment (NCSX) was designed to test physics principles of an innovative stellarator design developed by the Princeton Plasma Physics Laboratory and Oak Ridge National Laboratory. Construction of some of the major components and sub-assemblies was completed, but the estimated cost and schedule for completing the project grew as the technical requirements and risks became better understood, leading to its cancellation in 2008. The project's risks stemmed from its technical challenges, primarily the complex component geometries and tight tolerances that were required. The initial baseline, established in 2004, was supported by a risk management plan and risk-based contingencies, both of which proved to be inadequate. Technical successes were achieved in the construction of challenging components and sub-assemblies, but cost and schedule growth was experienced. As part of an effort to improve project performance, a new risk management program was devised and implemented in 2007-08. It led to a better understanding of project risks, a sounder basis for contingency estimates, and improved management tools. Although the risks ultimately were unacceptable to the sponsor, valuable lessons in risk management were learned through the experiences with the NCSX project.
引用
收藏
页码:136 / +
页数:2
相关论文
共 50 条
  • [31] MANAGEMENT CONSULTING AND TEACHING: LESSONS LEARNED
    Dyrud, Marilyn A.
    BUSINESS AND PROFESSIONAL COMMUNICATION QUARTERLY, 2009, 72 (03) : 328 - 329
  • [32] The management of hepatobiliary cystadenomas: lessons learned
    Martel, Guillaume
    Alsharif, Jamal
    Aubin, Jean-Michel
    Marginean, Celia
    Mimeault, Richard
    Fairfull-Smith, Robert J.
    Mohammad, Waleed M.
    Balaa, Fady K.
    HPB, 2013, 15 (08) : 617 - 622
  • [33] Smart Rail Management and Lessons Learned
    Guijt, Dirk
    Culver, Frank
    AUTOMATED PEOPLE MOVERS AND AUTOMATED TRANSIT SYSTEMS 2016: INNOVATION IN A RAPIDLY URBANIZING WORLD, 2016, : 206 - 213
  • [34] Case Management of Dengue: Lessons Learned
    Kalayanarooj, Siripen
    Rothman, Alan L.
    Srikiatkhachorn, Anon
    JOURNAL OF INFECTIOUS DISEASES, 2017, 215 : S79 - S88
  • [35] MANAGEMENT OF RESEARCH PROJECTS - LESSONS LEARNED
    Betta, Jan
    Jastrzebska, Joanna
    CBU INTERNATIONAL CONFERENCE PROCEEDINGS 2017: INNOVATIONS IN SCIENCE AND EDUCATION, 2017, 5 : 39 - 44
  • [36] LESSONS LEARNED - THE LIMITS OF RISK ANALYSIS
    BELL, TE
    IEEE SPECTRUM, 1989, 26 (06) : 51 - 51
  • [37] Lessons learned and lessons not learned
    Bursky, D
    ELECTRONIC DESIGN, 2001, 49 (12) : 22 - 22
  • [38] Lessons Learned from the Financial Crisis for Risk Management: Contrasting Developments in Insurance and Banking
    Lehmann, Axel P.
    Hofmann, Daniel M.
    GENEVA PAPERS ON RISK AND INSURANCE-ISSUES AND PRACTICE, 2010, 35 (01): : 63 - 78
  • [39] Cassini Risk Management during mission operations and data analysis - Application & lessons learned
    Witkowski, MM
    2003 IEEE AEROSPACE CONFERENCE PROCEEDINGS, VOLS 1-8, 2003, : 799 - 806
  • [40] Lessons learned from the preparation of the flood risk management plans on the Seine basin and perspectives
    Dupray, Sebastien
    Lavallart, Caroline
    SaIles, Elodie
    Vignasse, Isabelle
    3RD EUROPEAN CONFERENCE ON FLOOD RISK MANAGEMENT (FLOODRISK 2016), 2016, 7