A risk identification procedure for construction contracts - a case study of power station projects in Egypt

被引:22
|
作者
Hassanein, Amr A. G. [1 ]
Afify, Hala M. F. [1 ]
机构
[1] Amer Univ Cairo, Cairo, Egypt
关键词
risk management; risk identification; Egypt; construction contracts; risk checklist;
D O I
10.1080/10286600600910104
中图分类号
TU [建筑科学];
学科分类号
0813 ;
摘要
The process of risk management is generally divided into three phases: risk identification, risk analysis and risk response. From these three phases, the concept of risk identification appears to be the most known and practiced. The development of a more formalized, yet easy to use risk identification method is of extreme importance. This research focuses on risk identification as it relates to the Egyptian business environment including its procurement laws and regulations. Egypt is a developing country where the business environment emphasizes certain risks while diminishing others when compared with other countries. This study tackles risk identification by investigating the most significant risks related to construction contracts for two power station projects in Egypt. These had typical characteristics such as large scale, fast track projects where a multi-package contracting plan was utilized. Ultimately, a checklist of risk categories was developed to aid contractors in their risk identification effort. The compilation of this checklist identified seven risk categories: (1) owner's obligations; (2) interface with other contractors; (3) liability risks; (4) financial risks; (5) risks related to changes; (6) technical risks; and (7) consortium risks.
引用
收藏
页码:3 / 14
页数:12
相关论文
共 50 条
  • [1] Risk management practices of contractors: a case study of power station projects in Egypt
    Hassanein, Amr
    Afify, Halaa
    [J]. JOURNAL OF FINANCIAL MANAGEMENT OF PROPERTY AND CONSTRUCTION, 2007, 12 (03) : 165 - +
  • [2] Risk Identification of Building Construction Projects in Egypt
    Yousri, Elhosin
    Sayed, Ahmed El Badawy
    Farag, Moataz A. M.
    Abdelalim, Ahmed Mohammed
    [J]. BUILDINGS, 2023, 13 (04)
  • [3] Risk Identification in Cogeneration (Combined Heat and Power) Projects: A Polish Case Study
    Rzempala, Joanna
    Borkowski, Daniel
    Rzempala, Artur Piotr
    [J]. ENERGIES, 2022, 15 (01)
  • [4] THE PROBLEM OF RISK IN INFRASTRUCTURAL PROJECTS AND INTERNATIONAL CONSTRUCTION CONTRACTS
    Rodriguez Fernandez, Maximiliano
    [J]. REVISTA E-MERCATORIA, 2007, 6 (01)
  • [5] Increasing VFM in PPP power station projects - Case study: Rudeshur gas turbine power station
    Sobhiyah, M. H.
    Bemanian, M. R.
    Kashtiban, Y. Kh.
    [J]. INTERNATIONAL JOURNAL OF PROJECT MANAGEMENT, 2009, 27 (05) : 512 - 521
  • [6] A Preliminary Study of the Subcontractor's Risk Identification for the construction projects
    Zaini, Afzan Ahmad
    Endut, Intan Rohani
    Shehu, Zayyana
    [J]. IEEE SYMPOSIUM ON BUSINESS, ENGINEERING AND INDUSTRIAL APPLICATIONS (ISBEIA 2012), 2012, : 878 - 883
  • [7] Economic and Time Risk Factors Influencing the Construction Projects: A Case Study of Lebanese Construction Projects
    Ahmad, Omar
    Nouban, Fatemeh
    [J]. JORDAN JOURNAL OF CIVIL ENGINEERING, 2023, 17 (03) : 399 - 407
  • [8] A risk management model for large projects in the construction phase in Egypt
    Habib, Mohamed Mostafa
    Eldawla, Marwa Ahmed Kamer
    Zaki, Mahmoud Ahmed
    [J]. JOURNAL OF PROJECT MANAGEMENT, 2022, : 25 - 36
  • [9] A risk management model for large projects in the construction phase in Egypt
    Habib, Mohamed Mostafa
    Eldawla, Marwa Ahmed Kamer
    Zaki, Mahmoud Ahmed
    [J]. JOURNAL OF PROJECT MANAGEMENT, 2023, 8 (01) : 25 - 36
  • [10] Development of Risk Identification and Risk Analysis in Construction Projects
    Shen, JianHong
    Cao, XiuFeng
    [J]. PROCEEDINGS OF THE 16TH INTERNATIONAL SYMPOSIUM ON ADVANCEMENT OF CONSTRUCTION MANAGEMENT AND REAL ESTATE (CRIOCM2011), 2011, : 412 - 415