A weighted assembly precedence graph for assembly sequence planning

被引:32
|
作者
Wang, Yong [1 ]
Tian, De [1 ]
机构
[1] North China Elect Power Univ, Renewable Energy Sch, Beijing 102206, Peoples R China
关键词
Assembly sequence planning; Weighted assembly precedence graph; Fuzzy analytical hierarchy process; Minimum spanning tree-based algorithm; HIERARCHICAL APPROACH; ALGORITHM; OPTIMIZATION; GENERATION; INTEGRATION; DESIGN;
D O I
10.1007/s00170-015-7565-5
中图分类号
TP [自动化技术、计算机技术];
学科分类号
0812 ;
摘要
Assembly sequence planning is one of the well-known combinatorial optimization problems in manufacturing. An assembly is often represented as an assembly relation graph or precedence graph. The traditional methods are used to generate a large number of feasible assembly sequences and then find the optimal sequence through evaluation. A lot of computation resources are needed. To reduce the complexity of assembly sequence planning, the assembly is converted into a weighted assembly precedence graph considering multiple assembly constraints, i.e., the qualitative and quantitative constraints. The vertices in the weighted precedence graph are the parts or components. The qualitative constraints including the topological and geometrical assembly constraints guarantee to derive the feasible assembly sequences. Some process constraints are also taken as the qualitative constraints. They are represented as the directed edges in the weighted assembly precedence graph. The other assembly constraints, such as the stable support, connector strength, changes of assembly directions, and tools and so forth, are quantified as indices to compute the cost of assembly relations with the fuzzy analytical hierarchy process. The costs are taken as the heuristic information to find the optimal or near-optimal assembly sequences. With the weighted assembly precedence graph, the search space of the optimal assembly sequence will be reduced. We design a minimum spanning tree-based algorithm to detect the optimal assembly sequence based on the weighted assembly precedence graph. The optimal assembly sequences are found in O(n (3)) computation time, where n is the number of the discrete parts.
引用
收藏
页码:99 / 115
页数:17
相关论文
共 50 条
  • [31] An enhanced graph and artificial intelligence-based approach for assembly sequence planning
    Hsu, Y. Y.
    Chen, W. C.
    Tai, P. H.
    Tsai, M. D.
    Proceedings of the 35th International MATADOR Conference: FORMERLY THE INTERNATIONAL MACHINE TOOL DESIGN AND RESEARCH CONFERENCE, 2007, : 49 - 52
  • [32] A behavioral scene graph for rule enforcement in interactive virtual assembly sequence planning
    Banerjee, A
    Banerjee, P
    COMPUTERS IN INDUSTRY, 2000, 42 (2-3) : 147 - 157
  • [33] Generation and application of precedence information for the planning of assembly and disassembly procedures
    Aguinaga, Iker
    Borro, Diego
    Matey, Luis M.
    2007 5TH IEEE INTERNATIONAL CONFERENCE ON INDUSTRIAL INFORMATICS, VOLS 1-3, 2007, : 219 - +
  • [34] AUTOMATIC PRECEDENCE CONSTRAINT GENERATION FOR ASSEMBLY SEQUENCE PLANNING USING A THREE-DIMENSIONAL SOLID MODEL
    Alfadhlani
    Samadhi, T. M. A. Ari
    Ma'ruf, Anas
    Toha, Isa Setiasyah
    INTERNATIONAL JOURNAL OF TECHNOLOGY, 2019, 10 (02) : 339 - 350
  • [35] A Sub-assembly Identification Algorithm for Assembly Sequence Planning
    Cao, Yan
    Kou, Xiaoxi
    Cao, Sen
    PROCEEDINGS OF THE 2015 INTERNATIONAL INDUSTRIAL INFORMATICS AND COMPUTER ENGINEERING CONFERENCE, 2015, : 555 - 558
  • [36] Assembly sequences, assembly constraints, precedence graphs
    Henrioud, JM
    Relange, L
    Perrard, C
    PROCEEDINGS OF THE 2003 IEEE INTERNATIONAL SYMPOSIUM ON ASSEMBLY AND TASK PLANNING (ISATP2003), 2003, : 90 - 95
  • [37] Assembly sequence planning optimization for aircraft assembly based on GA
    Li, Yuan
    Zhang, Kai-Fu
    Wang, Ting
    Yang, Hai-Cheng
    Jisuanji Jicheng Zhizao Xitong/Computer Integrated Manufacturing Systems, CIMS, 2006, 12 (02): : 188 - 191
  • [38] An interference discrimination method for assembly sequence planning and assembly simulation
    Zhang, Wenlei
    Ma, Mingxu
    Li, Haiyan
    Yu, Jiapeng
    Zhang, Zhenwei
    ASSEMBLY AUTOMATION, 2020, 40 (04) : 541 - 552
  • [39] APPLICATION OF SYSTEM LEARNING TO PRECEDENCE GRAPH GENERATION FOR ASSEMBLY LINE BALANCING
    Antani, Kavit R.
    Pearce, Bryan
    Mears, Laine
    Renu, Rahul
    Kurz, Mary E.
    Schulte, Joerg
    PROCEEDINGS OF THE ASME 9TH INTERNATIONAL MANUFACTURING SCIENCE AND ENGINEERING CONFERENCE, 2014, VOL 1, 2014,
  • [40] A hierarchical approach to assembly sequence planning
    Niu, X
    Ding, H
    Xiong, Y
    ICMA 2002 INTERNATIONAL CONFERENCE ON MANUFACTURING AUTOMATION, 2002, : 321 - 328