Prediction of Cost Overrun Risk in Construction Projects

被引:12
|
作者
Plebankiewicz, Edyta [1 ]
Wieczorek, Damian [1 ]
机构
[1] Cracow Univ Technol, Fac Civil Engn, Div Management Civil Engn, PL-31155 Krakow, Poland
关键词
cost overrun; construction project; fuzzy sets; fuzzy inference model of Mamdani; INFRASTRUCTURE PROJECTS; ESTIMATION MODEL; INDUSTRY;
D O I
10.3390/su12229341
中图分类号
X [环境科学、安全科学];
学科分类号
08 ; 0830 ;
摘要
The paper proposes a cost overrun risks prediction model, the structure of which is based on the fuzzy inference model of Mamdani. The model consists of numerous inputs and one output (MISO, multi-input-single-output), based on processes running consecutively in three blocks (the fuzzy block, the interference block, and the block of sharpening the representative output value). The input variables of the model include the share of element costs in the building costs (SE), predicted changes in the number of works (WC), and expected changes in the unit price (PC). The developed rule base makes it possible to determine the risk of cost overruns in the following categories: "very low", "quite low", "average", "quite high", and "very high". Twenty-seven rules were assumed in the interference block. The operation of the model was illustrated by the example of selected elements of a road object and was validated by checking the correctness of the assumptions made at the design stage of the inference block rule base. It has been proven that with the increase of the share of element costs in the building costs (SE), predicted changes in the number of works (WC), and expected changes in the unit price (PC), the value of the risk exceeding the costs of a given element of the construction project (R) increases naturally and smoothly. It was emphasized in the conclusions that the cost overrun risks prediction model is intended for general contractors who subcontract many stages of works to their subcontractors in accordance with the agreed division into work elements.
引用
收藏
页码:1 / 15
页数:15
相关论文
共 50 条
  • [21] Machine learning-aided time and cost overrun prediction in construction projects: application of artificial neural network
    Al mnaseer R.
    Al-Smadi S.
    Al-Bdour H.
    Asian Journal of Civil Engineering, 2023, 24 (7) : 2583 - 2593
  • [22] Critical Factors Influencing Cost Overrun in Construction Projects: A Fuzzy Synthetic Evaluation
    Xie, Wenwen
    Deng, Binchao
    Yin, Yilin
    Lv, Xindong
    Deng, Zhenhua
    BUILDINGS, 2022, 12 (11)
  • [23] Assessment of cost overrun factors in construction projects in Nigeria using fuzzy logic
    Jude Iloabuchi Obianyo
    Okey Enangha Okey
    George Uwadiegwu Alaneme
    Innovative Infrastructure Solutions, 2022, 7
  • [24] Identifying The Effective Factors for Cost Overrun and Time Delay in Water Construction Projects
    Matin, Danial Mirzai
    ENGINEERING TECHNOLOGY & APPLIED SCIENCE RESEARCH, 2016, 6 (04) : 1062 - 1066
  • [25] Evaluation of Cost Overrun in Construction Projects during COVID-19 Pandemic
    Adepu, Nikhitha
    Kermanshachi, Sharareh
    Pamidimukkala, Apurva
    Loganathan, Karthikeyan
    JOURNAL OF LEGAL AFFAIRS AND DISPUTE RESOLUTION IN ENGINEERING AND CONSTRUCTION, 2024, 16 (01)
  • [26] Assessment of cost overrun factors in construction projects in Nigeria using fuzzy logic
    Obianyo, Jude Iloabuchi
    Okey, Okey Enangha
    Alaneme, George Uwadiegwu
    INNOVATIVE INFRASTRUCTURE SOLUTIONS, 2022, 7 (05)
  • [27] Application of knowledge discovery in database (KDD) techniques in cost overrun of construction projects
    Ghazal, Mai Monir
    Hammad, Ahmed
    INTERNATIONAL JOURNAL OF CONSTRUCTION MANAGEMENT, 2022, 22 (09) : 1632 - 1646
  • [28] A review of artificial intelligence based risk assessment methods for capturing complexity-risk interdependencies Cost overrun in construction projects
    Afzal, Farman
    Shao Yunfei
    Nazir, Mubasher
    Bhatti, Saad Mahmood
    INTERNATIONAL JOURNAL OF MANAGING PROJECTS IN BUSINESS, 2021, 14 (02) : 300 - 328
  • [29] Factors Affecting Schedule Delay, Cost Overrun, and Quality Level in Public Construction Projects
    Larsen, Jesper Kranker
    Shen, Geoffrey Qiping
    Lindhard, Soren Munch
    Brunoe, Thomas Ditlev
    JOURNAL OF MANAGEMENT IN ENGINEERING, 2016, 32 (01)
  • [30] Financial Mismanagement: A Leading Cause of Time and Cost Overrun in Mega Construction Projects in Pakistan
    Shaikh, Fazal Ali
    ENGINEERING TECHNOLOGY & APPLIED SCIENCE RESEARCH, 2020, 10 (01) : 5247 - 5250