MIP models for resource-constrained project scheduling with flexible resource profiles

被引:81
|
作者
Naber, Anulark [1 ]
Kolisch, Rainer [1 ]
机构
[1] Tech Univ Munich, TUM Sch Management, D-80333 Munich, Germany
关键词
Project scheduling; Flexible profiles; Principal resources; Dependent resources; Discrete-time models; TRADE-OFF PROBLEM; LIMITED RESOURCES; BOUND APPROACH; NETWORKS; BRANCH; ALGORITHM; SEARCH;
D O I
10.1016/j.ejor.2014.05.036
中图分类号
C93 [管理学];
学科分类号
12 ; 1201 ; 1202 ; 120202 ;
摘要
This paper addresses the resource-constrained project scheduling problem with flexible resource profiles (FRCPSP). Such a problem often arises in many real-world applications, in which the resource usage of an activity is not merely constant, but can be adjusted from period to period. The FRCPSP is, therefore, to simultaneously determine the start time, the resource profile, and the duration of each activity in order to minimize the makespan, subject to precedence relationships, limited availability of multiple resources, and restrictions on resource profiles. We propose four discrete-time model formulations and compare their model efficiency in terms of solution quality and computational times. Both preprocessing and priority-based heuristic methods are also applied to compute both upper and lower bounds of the makespan. Our comparative results show significant dominance of one of the models, the so-called "variable-intensity-based" model, in both solution quality and runtimes. (C) 2014 Elsevier B.V. All rights reserved.
引用
收藏
页码:335 / 348
页数:14
相关论文
共 50 条
  • [1] A hybrid metaheuristic for resource-constrained project scheduling with, flexible resource profiles
    Tritschler, Martin
    Naber, Anulark
    Kolisch, Rainer
    EUROPEAN JOURNAL OF OPERATIONAL RESEARCH, 2017, 262 (01) : 262 - 273
  • [2] Resource-constrained project scheduling with flexible resource profiles in continuous time
    Naber, Anulark
    COMPUTERS & OPERATIONS RESEARCH, 2017, 84 : 33 - 45
  • [3] Flexible resource-constrained resource leveling project scheduling problem
    Yu, Xiao-Guang
    Zhan, De-Chen
    Nie, Lan-Shun
    Chu, Dian-Hui
    Xu, Xiao-Fei
    Jisuanji Jicheng Zhizao Xitong/Computer Integrated Manufacturing Systems, CIMS, 2010, 16 (09): : 1967 - 1976
  • [4] Flexible Scheduling Approach for Resource-Constrained Project Scheduling Problems
    Liu, Shixin
    Tukel, Oya I.
    Rom, W.
    2008 7TH WORLD CONGRESS ON INTELLIGENT CONTROL AND AUTOMATION, VOLS 1-23, 2008, : 3522 - +
  • [5] Multimode resource-constrained project scheduling in flexible projects
    Kosztyan, Zsolt T.
    Szalkai, Istvan
    JOURNAL OF GLOBAL OPTIMIZATION, 2020, 76 (01) : 211 - 241
  • [6] A Flexible Heuristic Algorithm for Resource-Constrained Project Scheduling
    Seda, Milos
    Matousek, Radomil
    Osmera, Pavel
    Pivonka, Petr
    Sandera, Cenek
    WCECS 2009: WORLD CONGRESS ON ENGINEERING AND COMPUTER SCIENCE, VOLS I AND II, 2009, : 730 - +
  • [7] Multimode resource-constrained project scheduling in flexible projects
    Zsolt T. Kosztyán
    István Szalkai
    Journal of Global Optimization, 2020, 76 : 211 - 241
  • [8] Scheduling resource-constrained projects with a flexible project structure
    Kellenbrink, Carolin
    Helber, Stefan
    EUROPEAN JOURNAL OF OPERATIONAL RESEARCH, 2015, 246 (02) : 379 - 391
  • [9] Resource-Constrained Project Scheduling Problem with Flexible Work Profiles: A Genetic Algorithm Approach
    Ranjbar, M.
    Kianfar, F.
    SCIENTIA IRANICA TRANSACTION E-INDUSTRIAL ENGINEERING, 2010, 17 (01): : 25 - 35
  • [10] Multi-Objective Multi-Skill Resource-Constrained Project Scheduling Considering Flexible Resource Profiles
    Luo, Xu
    Guo, Shunsheng
    Du, Baigang
    Luo, Xinhao
    Guo, Jun
    APPLIED SCIENCES-BASEL, 2024, 14 (05):