Crashing Construction Project Schedules by Relocating Resources

被引:6
|
作者
Tomczak, Michal [1 ]
Jaskowski, Piotr [1 ]
机构
[1] Lublin Univ Technol, Fac Civil Engn & Architecture, PL-20618 Lublin, Poland
来源
IEEE ACCESS | 2020年 / 8卷
关键词
Schedules; Task analysis; Solid modeling; Optimal scheduling; Acceleration; Computer crashes; Scheduling; Construction project management; construction project scheduling; resource allocation; resource-constrained project scheduling problem; schedule optimization; LINE-OF-BALANCE; REPETITIVE PROJECTS; MODEL; OPTIMIZATION; UNCERTAINTY; REDUCTION;
D O I
10.1109/ACCESS.2020.3044645
中图分类号
TP [自动化技术、计算机技术];
学科分类号
0812 ;
摘要
A variety of schedule compression techniques are used to get delayed construction projects "back on tracks". This paper presents a new optimization approach to schedule crashing by relocating some of the workers from non-critical to critical processes (changing composition of crews using the initial pool of workers) and employing additional resources. The authors describe their idea in the form of a mixed-integer linear problem. A numerical example illustrates the merits of the proposed approach. The method may become a practical support in construction scheduling decisions.
引用
收藏
页码:224522 / 224531
页数:10
相关论文
共 50 条
  • [31] A Probabilistic-Based Method to Determine Optimum Size of Project Buffer in Construction Schedules
    Poshdar, M.
    Gonzalez, V. A.
    Raftery, G. M.
    Orozco, F.
    Romeo, J. S.
    Forcael, E.
    [J]. JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT, 2016, 142 (10)
  • [32] Taiwan - Tuntex considers relocating cracker project to Australia
    不详
    [J]. CHEMICAL WEEK, 1999, 161 (33) : 26 - 26
  • [33] Improving the Accuracy of Project Schedules
    Lorko, Matej
    Servatka, Maros
    Zhang, Le
    [J]. PRODUCTION AND OPERATIONS MANAGEMENT, 2021, 30 (06) : 1633 - 1646
  • [34] Emerge of scaling in project schedules
    Vazquez, Alexei
    [J]. EUROPEAN PHYSICAL JOURNAL B, 2024, 97 (04):
  • [35] Construction project risk management in Singapore: Resources, effectiveness, impact, and understanding
    Xianbo Zhao
    Bon-Gang Hwang
    Weisheng Phng
    [J]. KSCE Journal of Civil Engineering, 2014, 18 : 27 - 36
  • [36] Effect of human resources management and advances to improve construction project performance
    Muntu, D.
    Setyawati, R.
    Riantini, L. S.
    Ichsan, M.
    [J]. PHYSICS AND CHEMISTRY OF THE EARTH, 2021, 122
  • [37] An unsupervised cross project model for crashing fault residence identification
    Liu, Xiao
    Xu, Zhou
    Yang, Dan
    Yan, Meng
    Zhang, Weihan
    Zhao, Haohan
    Xue, Lei
    Fan, Ming
    [J]. IET SOFTWARE, 2022, 16 (06) : 630 - 646
  • [38] Fuzzy activity times in critical path and project crashing problems
    Liu, ST
    [J]. CYBERNETICS AND SYSTEMS, 2003, 34 (02) : 161 - 172
  • [39] The Optimization of Construction Period and Resources of Project based on Traverse Network Chart
    Li, Yueqin
    Cai, Hong
    [J]. 2011 INTERNATIONAL CONFERENCE ON ECONOMIC, EDUCATION AND MANAGEMENT (ICEEM2011), VOL III, 2011, : 637 - 641
  • [40] Identifying and Analysing the Root Causes of Quality Non-Conformance in Construction Project Baseline Schedules
    Srinath P.
    Varghese K.
    [J]. Journal of The Institution of Engineers (India): Series A, 2023, 104 (02) : 397 - 416