Improving the Accuracy of Project Schedules

被引:5
|
作者
Lorko, Matej [1 ,2 ]
Servatka, Maros [1 ,2 ]
Zhang, Le [1 ]
机构
[1] Macquarie Business Sch, MGSM Expt Econ Lab, Sydney, NSW, Australia
[2] Univ Econ Bratislava, Fac Natl Econ, Bratislava, Slovakia
关键词
project management; project planning; duration estimation; historical information; project specification; PUBLIC-WORKS PROJECTS; SOFTWARE-DEVELOPMENT; FORECASTS; JUDGMENT; PEOPLE; TIME; BIAS;
D O I
10.1111/poms.13299
中图分类号
T [工业技术];
学科分类号
08 ;
摘要
How to avoid project failures driven by overoptimistic schedules? Managers often attempt to mitigate the duration underestimation and improve the accuracy of project schedules by providing their planners with excessively detailed project specifications. While this traditional approach may be intuitive, solely providing more detailed information has proven to have a limited effect on eliminating behavioral biases. We experimentally test the effectiveness of providing detailed specification and compare it to an alternative intervention of providing historical information about the average duration of similar projects in the past. We find that both interventions mitigate the underestimation bias. However, since providing detailed project specification results in high variance of estimation errors due to sizable over- and underestimates, only the provision of historical information leads to more accurate project duration estimates. We also test whether it is more effective to anchor planners by providing historical information simultaneously with the project specification or to provide the historical information only after beliefs regarding the project duration are formed, in which case planners can regress their initial estimates toward the historical average. We find that the timing of disclosing information does not play a role as the estimation bias is mitigated and the accuracy is improved in both conditions. Finally, we observe that the subjective confidence in the accuracy of duration estimates does not vary across the interventions, suggesting that the confidence is neither a function of the amount nor the detail of available information.
引用
收藏
页码:1633 / 1646
页数:14
相关论文
共 50 条
  • [1] Improving the Accuracy of Project Cost with BIM
    Xiao, Xin-hua
    Deng, Yan-bo
    3RD INTERNATIONAL CONFERENCE ON CIVIL ENGINEERING, ARCHITECTURE AND SUSTAINABLE INFRASTRUCTURE, ICCEASI 2015, 2015, : 266 - 270
  • [2] THE METHOD FOR IMPROVING STABILITY OF CONSTRUCTION PROJECT SCHEDULES THROUGH BUFFER ALLOCATION
    Jaskowski, Piotr
    Biruk, Slawomir
    TECHNOLOGICAL AND ECONOMIC DEVELOPMENT OF ECONOMY, 2011, 17 (03) : 429 - 444
  • [3] Dilbert Moments: Exploring the Factors Impacting Upon the Accuracy of Project Managers' Baseline Schedules
    Prater, James
    Kirytopoulos, Konstantinos
    Ma, Tony
    INTERNATIONAL JOURNAL OF INFORMATION TECHNOLOGY PROJECT MANAGEMENT, 2019, 10 (02) : 29 - 40
  • [4] Project organizations and schedules
    1600, Publ by Plenum Publ Corp, New York, NY, USA
  • [5] Improving Accuracy of Medication Reconciliation for Hospitalized Children: A Quality Project
    Gunkelman, Samantha M.
    Jamerino-Thrush, Jennifer
    Genet, Katherine
    Blackford, Martha
    Jones, Kerwyn
    Bigham, Michael T.
    HOSPITAL PEDIATRICS, 2024, 14 (04) : 300 - 307
  • [6] Improving Pleural Fluid pH Accuracy: A Quality Improvement Project
    Bowmaster, S.
    Merrill, A.
    Gross, T. J.
    AMERICAN JOURNAL OF RESPIRATORY AND CRITICAL CARE MEDICINE, 2024, 209
  • [7] Things that disrupt project schedules
    IEEE Eng Manage Rev, 4 (13-14):
  • [8] Quantifying buffers for project schedules
    Hoel, Kjersti
    Taylor, Sam G.
    Production and Inventory Management Journal, 40 (02): : 43 - 47
  • [9] Emerge of scaling in project schedules
    Vazquez, Alexei
    EUROPEAN PHYSICAL JOURNAL B, 2024, 97 (04):
  • [10] Improving operating room schedules
    Li, Fei
    Gupta, Diwakar
    Potthoff, Sandra
    HEALTH CARE MANAGEMENT SCIENCE, 2016, 19 (03) : 261 - 278