Crashing Construction Project Schedules by Relocating Resources

被引:6
|
作者
Tomczak, Michal [1 ]
Jaskowski, Piotr [1 ]
机构
[1] Lublin Univ Technol, Fac Civil Engn & Architecture, PL-20618 Lublin, Poland
来源
IEEE ACCESS | 2020年 / 8卷
关键词
Schedules; Task analysis; Solid modeling; Optimal scheduling; Acceleration; Computer crashes; Scheduling; Construction project management; construction project scheduling; resource allocation; resource-constrained project scheduling problem; schedule optimization; LINE-OF-BALANCE; REPETITIVE PROJECTS; MODEL; OPTIMIZATION; UNCERTAINTY; REDUCTION;
D O I
10.1109/ACCESS.2020.3044645
中图分类号
TP [自动化技术、计算机技术];
学科分类号
0812 ;
摘要
A variety of schedule compression techniques are used to get delayed construction projects "back on tracks". This paper presents a new optimization approach to schedule crashing by relocating some of the workers from non-critical to critical processes (changing composition of crews using the initial pool of workers) and employing additional resources. The authors describe their idea in the form of a mixed-integer linear problem. A numerical example illustrates the merits of the proposed approach. The method may become a practical support in construction scheduling decisions.
引用
收藏
页码:224522 / 224531
页数:10
相关论文
共 50 条
  • [1] Selection of the Optimal Actions for Crashing Processes Duration to Increase the Robustness of Construction Schedules
    Biruk, Slawomir
    Jaskowski, Piotr
    [J]. APPLIED SCIENCES-BASEL, 2020, 10 (22): : 1 - 14
  • [2] The construction of stable project baseline schedules
    Herroelen, W
    Leus, R
    [J]. EUROPEAN JOURNAL OF OPERATIONAL RESEARCH, 2004, 156 (03) : 550 - 565
  • [3] Construction project planning using integration of crashing and concurrency techniques
    Hady, Haider Najy
    AL-Kindi, Luma Adnan
    Mahmoud, Mahmoud A.
    [J]. 4TH INTERNATIONAL CONFERENCE ON BUILDINGS, CONSTRUCTION AND ENVIRONMENTAL ENGINEERING, 2020, 737
  • [4] Construction and application of robustness indicator for project schedules
    Hu, Zhentao
    Cui, Nanfang
    Leng, Kaijun
    Bi, Ya
    [J]. Xitong Gongcheng Lilun yu Shijian/System Engineering Theory and Practice, 2024, 44 (05): : 1669 - 1679
  • [5] WORKSTATION SOFTWARE MANAGES PROJECT SCHEDULES, COSTS, AND RESOURCES
    MASSEY, A
    [J]. ELECTRONIC DESIGN, 1984, 32 (21) : 185 - &
  • [6] METHODOLOGY FOR ENHANCING RELIABILITY OF PREDICTIVE PROJECT SCHEDULES IN CONSTRUCTION
    Jaskowski, Piotr
    [J]. EKSPLOATACJA I NIEZAWODNOSC-MAINTENANCE AND RELIABILITY, 2015, 17 (03): : 470 - 479
  • [7] Optimization of Project Schedule Crashing
    Shrestha, Kabindra K.
    Shrestha, Pramen P.
    [J]. CONSTRUCTION RESEARCH CONGRESS 2016: OLD AND NEW CONSTRUCTION TECHNOLOGIES CONVERGE IN HISTORIC SAN JUAN, 2016, : 708 - 717
  • [8] RESOURCE CONSTRAINED PROJECT CRASHING
    DECKRO, RF
    HEBERT, JE
    [J]. OMEGA-INTERNATIONAL JOURNAL OF MANAGEMENT SCIENCE, 1989, 17 (01): : 69 - 79
  • [9] Impact of project construction on land and water resources
    Dang, JQ
    Zhang, XH
    Feng, W
    [J]. JOURNAL OF EXPERIMENTAL BOTANY, 2003, 54 : 54 - 54
  • [10] Preferences of Construction Managers Regarding the Quality and Optimization Criteria of Project Schedules
    Tomczak, Michal
    Jaskowski, Piotr
    [J]. SUSTAINABILITY, 2021, 13 (02) : 1 - 24