METHODOLOGY FOR ENHANCING RELIABILITY OF PREDICTIVE PROJECT SCHEDULES IN CONSTRUCTION

被引:17
|
作者
Jaskowski, Piotr [1 ]
机构
[1] Lublin Univ Technol, Fac Civil Engn & Architecture, PL-20816 Lublin, Poland
关键词
project programme reliability; construction project scheduling; construction and maintenance of built facilities; robustness; duration risk analysis and assessment; time buffer allocation; MANAGEMENT; RISK; STRATEGIES; STABILITY; MODEL;
D O I
10.17531/ein.2015.3.20
中图分类号
T [工业技术];
学科分类号
08 ;
摘要
Construction projects consist in providing new built facilities as well as in maintaining the existing building stock. Reliability engineering in construction encompasses all stages of the structure's life cycle from the earliest concept of the project to decommissioning. The project planning and design stages are aimed at selecting or creating technical and organisational solutions to assure that the built facility meets the sponsor's and the user's requirements; these requirements regulate also the construction process. The result of planning the construction process should be a reliable schedule - immune to disruptive effects of random occurrences, so assuring high probability of the actual processes meeting their predefined deadlines. A practical method of scheduling construction projects should enable the planner to generate schedules resistant to random occurrences, making them reliable so that the users can meet deadlines. The paper presents a proactive methodology for generating construction schedules of enhanced reliability. The methodology covers two fundamental stages. The first stage is a construction duration risk assessment based on a multi-attribute evaluation of operating conditions. The second stage is the allocation of time buffers. An original methodology supporting decisions at each stage is put forward, namely a methodology for evaluating process duration risk level, defining significance of operating conditions, estimating dispersion of process durations, and defining criticality of processes in the schedule. The author proposes a set of measures of schedule robustness to serve as surrogate criteria in the schedule instability cost minimization problem and buffer sizing. The proposed way of allowing for risk and uncertainty in creating reliable schedules is argued to be efficient in protecting the project completion date, as well as stage or even process start dates, against disruptions.
引用
收藏
页码:470 / 479
页数:10
相关论文
共 50 条
  • [1] The construction of stable project baseline schedules
    Herroelen, W
    Leus, R
    [J]. EUROPEAN JOURNAL OF OPERATIONAL RESEARCH, 2004, 156 (03) : 550 - 565
  • [2] Crashing Construction Project Schedules by Relocating Resources
    Tomczak, Michal
    Jaskowski, Piotr
    [J]. IEEE ACCESS, 2020, 8 : 224522 - 224531
  • [3] Construction and application of robustness indicator for project schedules
    Hu, Zhentao
    Cui, Nanfang
    Leng, Kaijun
    Bi, Ya
    [J]. Xitong Gongcheng Lilun yu Shijian/System Engineering Theory and Practice, 2024, 44 (05): : 1669 - 1679
  • [4] A study on methodology for enhancing reliability of datapath
    Yang, SW
    Kim, MJ
    Park, JH
    Chang, H
    [J]. COMPUTATIONAL SCIENCE AND ITS APPLICATIONS - ICCSA 2004, PT 1, 2004, 3043 : 73 - 80
  • [5] A tabu search procedure for developing robust predictive project schedules
    Lambrechts, Olivier
    Demeulemeester, Erik
    Herroelen, Willy
    [J]. INTERNATIONAL JOURNAL OF PRODUCTION ECONOMICS, 2008, 111 (02) : 493 - 508
  • [6] Financing and reliability analysis for schedules in the project calendar planning problem
    E. A. Kazakovtseva
    V. V. Servakh
    [J]. Automation and Remote Control, 2014, 75 : 1231 - 1240
  • [7] Financing and reliability analysis for schedules in the project calendar planning problem
    Kazakovtseva, E. A.
    Servakh, V. V.
    [J]. AUTOMATION AND REMOTE CONTROL, 2014, 75 (07) : 1231 - 1240
  • [8] Reliability enhancement methodology and modelling - the REMM project
    Marshall, J
    Walls, L
    Jones, J
    [J]. AERONAUTICAL JOURNAL, 2002, 106 (1058): : 195 - 201
  • [9] Reliability by Construction using Design by Contract Methodology
    Murthy, P. V. R.
    [J]. PROCEEDINGS OF THE 9TH INDIA SOFTWARE ENGINEERING CONFERENCE, 2016, : 201 - 202
  • [10] A quantitative risk assessment methodology for construction project
    Gupta, Vishal Kumar
    Thakkar, Jitesh J.
    [J]. SADHANA-ACADEMY PROCEEDINGS IN ENGINEERING SCIENCES, 2018, 43 (07):