Preferences of Construction Managers Regarding the Quality and Optimization Criteria of Project Schedules

被引:6
|
作者
Tomczak, Michal [1 ]
Jaskowski, Piotr [1 ]
机构
[1] Lublin Univ Technol, Fac Civil Engn & Architecture, 40 Nadbystrzycka St, PL-20618 Lublin, Poland
关键词
construction scheduling; construction project management; factor analysis; multiple objective; schedule criteria; survey research;
D O I
10.3390/su13020544
中图分类号
X [环境科学、安全科学];
学科分类号
08 ; 0830 ;
摘要
In the literature on the scheduling of construction projects it is difficult to find a justification for adopting the criteria for evaluating work schedules based explicitly on the preferences of those who develop them. This article tries to fill this gap and provide information on the preferences of construction site managers for sustainable scheduling and organization of construction projects. The publication focuses on the views and needs of construction site engineering staff regarding methods of work organization, the need to reduce downtimes in the work of crews, the deadline for project realization and the selection of crews for tasks. This information was obtained on the basis of surveys conducted among managerial staff of various levels (74 people). The authors hope that the information provided in this publication will allow the creation of more reliable tools to support construction managers better adapted to their preferences and needs, and therefore more likely to be applied in practice.
引用
收藏
页码:1 / 24
页数:22
相关论文
共 50 条
  • [1] Software project managers' risk preferences
    Lauer, TW
    [J]. JOURNAL OF INFORMATION TECHNOLOGY, 1996, 11 (04) : 287 - 295
  • [2] Approaches to construction project managers
    Radujkovic, Mladen
    Vukomanovic, Mladen
    Bezak, Stjepan
    [J]. GRADEVINAR, 2010, 62 (07): : 621 - 631
  • [3] Construction Project Quality Cost Optimization Design
    Zhang, Wei-Hua
    Zhang, Jian-Hua
    Zhou, Xiao-Yan
    [J]. EBM 2010: INTERNATIONAL CONFERENCE ON ENGINEERING AND BUSINESS MANAGEMENT, VOLS 1-8, 2010, : 2054 - 2057
  • [4] The Influence of Message Framing on Project Managers' Behavioral Intentions Regarding Construction Waste Reduction
    Yao, Lianying
    Liang, Yulu
    Li, Xiangyu
    Wang, Zhimin
    Jiang, Shuli
    Yan, Cheng
    [J]. BUILDINGS, 2022, 12 (08)
  • [5] The construction of stable project baseline schedules
    Herroelen, W
    Leus, R
    [J]. EUROPEAN JOURNAL OF OPERATIONAL RESEARCH, 2004, 156 (03) : 550 - 565
  • [6] Quality assessment of construction schedules
    Marcinkowski, Roman
    [J]. Komunikacie, 2003, 5 (01): : 76 - 83
  • [7] Crashing Construction Project Schedules by Relocating Resources
    Tomczak, Michal
    Jaskowski, Piotr
    [J]. IEEE ACCESS, 2020, 8 : 224522 - 224531
  • [8] Construction and application of robustness indicator for project schedules
    Hu, Zhentao
    Cui, Nanfang
    Leng, Kaijun
    Bi, Ya
    [J]. Xitong Gongcheng Lilun yu Shijian/System Engineering Theory and Practice, 2024, 44 (05): : 1669 - 1679
  • [9] Effects of construction project managers' goal orientation on project performance
    Zhang, Qi
    Hao, Shengyue
    Guo, Jienan
    Tang, Boju
    [J]. SOCIAL BEHAVIOR AND PERSONALITY, 2022, 50 (06):
  • [10] Integrated management and optimization of construction project schedule, cost and quality
    Zhan Xiaran
    [J]. 2018 INTERNATIONAL WORKSHOP ON ADVANCES IN SOCIAL SCIENCES (IWASS 2018), 2019, : 622 - 625