Impacts of Change Orders on Cost and Schedule Performance and the Correlation with Project Size of DB Building Projects

被引:23
|
作者
Shrestha, Pramen P. [1 ]
Fathi, Medya [1 ]
机构
[1] Univ Nevada, Dept Civil & Environm Engn & Construct, Howard R Hughes Coll Engn, Las Vegas, NV 89154 USA
关键词
Design-build; Building projects; Change orders; Cost overrun; Schedule overrun; LABOR EFFICIENCY; MODEL;
D O I
10.1061/(ASCE)LA.1943-4170.0000311
中图分类号
D9 [法律]; DF [法律];
学科分类号
0301 ;
摘要
Few studies have been conducted to evaluate change orders in design-build (DB) projects, examining their impacts on cost and schedule performance, and their relationship with project size. This study analyzed cost, schedule, and change order data for 125 DB building projects to check whether the number of change orders for DB projects was higher than for design-bid-build (DBB) projects. All of the DB projects considered in this study had fixed their final guaranteed maximum price (GMP) before the design was 100% completed. One of the advantages of the DB delivery method is constructability, in which the designer can solicit feedback from construction personnel during the design phase; this can reduce the number of change orders. Results indicated that there were fewer change orders during DB building projects compared with DBB building projects. In addition, the percentage of projects that had cost overruns (21%) was significantly lower than that for projects that had cost underruns or were completed on budget (79%). In addition, the percentage of change orders in projects that had schedule overruns was not significantly higher than that in projects that had no schedule overruns; among other findings, the number of change orders increased as the size of the project increased (r=0.59).
引用
收藏
页数:9
相关论文
共 50 条
  • [41] Predicting Cost and Schedule Performance of Green Building Projects Based on Preproject Planning Efforts Using Multiple Linear Regression Analysis
    Khun-Anod, Kritsada
    Limsawasd, Charinee
    Athigakunagorn, Nathee
    [J]. Journal of Architectural Engineering, 2023, 29 (03):
  • [42] Work rate modeling of building construction projects using system dynamic to optimize project cost and time performance
    Rachmawati, Farida
    Mudjahidin, Mudjahidin
    Widowati, Elok Dewi
    [J]. INTERNATIONAL JOURNAL OF CONSTRUCTION MANAGEMENT, 2024, 24 (02) : 213 - 225
  • [43] An Empirical Investigation of Key Pre-project Planning Practices Affecting the Cost Performance of Green Building Projects
    Son, H.
    Lee, S.
    Kim, C.
    [J]. DEFINING THE FUTURE OF SUSTAINABILITY AND RESILIENCE IN DESIGN, ENGINEERING AND CONSTRUCTION, 2015, 118 : 37 - 41
  • [44] Cost and Schedule Performance Analysis of Transportation Public-Private Partnership Projects
    Ramsey, David
    El Asmar, Mounir
    [J]. JOURNAL OF LEGAL AFFAIRS AND DISPUTE RESOLUTION IN ENGINEERING AND CONSTRUCTION, 2020, 12 (01)
  • [45] Understanding the Key Risks Affecting Cost and Schedule Performance of Modular Construction Projects
    Abdul Nabi, Mohamad
    El-adaway, Islam H.
    [J]. JOURNAL OF MANAGEMENT IN ENGINEERING, 2021, 37 (04)
  • [46] Explanation of Change Study Update to Examine the Cost, Schedule, and Technical Changes to NASA Projects
    Bitten, Robert
    Shinn, Stephen
    Emmons, Debra
    Scolese, Christopher J.
    [J]. 2018 IEEE AEROSPACE CONFERENCE, 2018,
  • [47] Factors Influencing Facilities Management Cost Performance in Building Projects
    Islam, Rashidul
    Nazifa, Tasnia Hassan
    Mohamed, Sarajul Fikri
    [J]. JOURNAL OF PERFORMANCE OF CONSTRUCTED FACILITIES, 2019, 33 (03)
  • [48] Model for Quantifying the Impact of Change Orders on Project Cost for US Roadwork Construction
    Serag, Engy
    Oloufa, Amr
    Malone, Linda
    Radwan, Essam
    [J]. JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT-ASCE, 2010, 136 (09): : 1015 - 1027
  • [49] Robustness Analysis of Total Project Cost and Schedule Delay and Overrun Indicators of Heavy Industrial Projects
    Kermanshachi, Sharareh
    Pamidimukkala, Apurva
    [J]. JOURNAL OF LEGAL AFFAIRS AND DISPUTE RESOLUTION IN ENGINEERING AND CONSTRUCTION, 2023, 15 (02)
  • [50] Estimating the impacts of climate change and urbanization on building performance
    Crawley, Drury B.
    [J]. BUILDING SIMULATION 2007, VOLS 1-3, PROCEEDINGS, 2007, : 1115 - 1122