Robustness Analysis of Total Project Cost and Schedule Delay and Overrun Indicators of Heavy Industrial Projects

被引:2
|
作者
Kermanshachi, Sharareh [1 ]
Pamidimukkala, Apurva [1 ]
机构
[1] Univ Texas Arlington, Dept Civil Engn, 425 Nedderman Hall,416 Yates St, Arlington, TX 76019 USA
关键词
Heavy industrial projects; Performance; Cost overruns; Schedule overruns; CONSTRUCTION PROJECTS;
D O I
10.1061/JLADAH.LADR-942
中图分类号
D9 [法律]; DF [法律];
学科分类号
0301 ;
摘要
Barriers such as cost overruns and schedule delays make it challenging to achieve successful project outcomes. Their early detection, however, allows mitigation strategies to be implemented before too much delay has occurred; therefore, the objective of this study was to identify the total project cost and schedule overrun indicators and evaluate their reliability for large-scale heavy industrial projects. To accomplish the study's goals, a structured survey was developed and disseminated to construction industry professionals to gain their input on the most important cost overrun indicators (COIs) and schedule overrun indicators (SOIs). The collected data were analyzed by applying various statistical tests, and a list of the significant COIs and SOIs was compiled utilizing all-possible regression. The extreme bound analysis (EBA) method was adopted to determine the robustness of the identified indicators. The results revealed the nine COIs are design phase contract type, change management approach, degree of internal stakeholders' alignment, delay in the delivery of long-term facility machinery, proportion of artisanal labor sourced locally, proportion of design completion before the budget approval of the project, preparing for startup deployment, agreement including delayed completion charges, and number of design organizations; two of these were fragile indicators. The results also demonstrated the nine influential indicators for total schedule overrun are implementation of front-end planning, efficacy of the change management process, project population density, average number of project management (PM) team participants in the procurement phase, prior designer and contractor partnership, delay in the delivery of long-term facility machinery, average size of PM team design phase, efficacy of designers group interaction, and number of subcontracting firms; six of these were robustly related to the model. The findings of this study can help construction project decision makers focus on the most reliable indicators and reduce the number of revisions required throughout the execution of a project.
引用
收藏
页数:10
相关论文
共 50 条
  • [1] Factors Affecting Schedule Delay, Cost Overrun, and Quality Level in Public Construction Projects
    Larsen, Jesper Kranker
    Shen, Geoffrey Qiping
    Lindhard, Soren Munch
    Brunoe, Thomas Ditlev
    [J]. JOURNAL OF MANAGEMENT IN ENGINEERING, 2016, 32 (01)
  • [2] Delay and Cost Overrun in Infrastructure Projects in Jordan
    Al-Hazim, Nabil
    Abu Salem, Zaydoun
    Ahmad, Hesham
    [J]. 7TH INTERNATIONAL CONFERENCE ON ENGINEERING, PROJECT, AND PRODUCTION MANAGEMENT, 2017, 182 : 18 - 24
  • [3] An analysis of causes of delay and cost overrun in construction of hydropower project
    Azam, Tamoor
    Jiang, Wang Song
    Malik, Sohail Ahmed
    Malik, Saqib Yaqoob
    Nilofar, Memoona
    Abbas, Zaheer
    Ullah, Ihsan
    [J]. JOURNAL OF PUBLIC AFFAIRS, 2022, 22 (03)
  • [4] Cost overrun and time delay of construction project in Indonesia
    Susanti, Riza
    [J]. 8TH ENGINEERING INTERNATIONAL CONFERENCE 2019, 2020, 1444
  • [5] Uncertainty Analysis of Key Schedule Performance Indicators in Design, Procurement, and Construction Phases of Heavy Industrial Projects
    Kermanshachi, Sharareh
    Pamidimukkala, Apurva
    [J]. JOURNAL OF LEGAL AFFAIRS AND DISPUTE RESOLUTION IN ENGINEERING AND CONSTRUCTION, 2023, 15 (01)
  • [6] Time Delay and Cost Overrun in Qatari Public Construction Projects
    Senouci, Ahmed
    Ismail, Alaa
    Eldin, Neil
    [J]. 5TH CREATIVE CONSTRUCTION CONFERENCE (CCC 2016), 2016, 164 : 368 - 375
  • [7] Delay factors of the schedule of strategic industrial projects
    Sweis, Rateb
    Moarefi, Alireza
    Hoseini-Amiri, Seyyed-Mahmoud
    Moarefi, Soad
    [J]. INTERNATIONAL JOURNAL OF BUILDING PATHOLOGY AND ADAPTATION, 2019, 37 (01) : 69 - 86
  • [8] Analysis of Cost Overrun and Schedule Delays of Infrastructure Projects in Low Income Economies: Case Studies in Ethiopia
    Melaku Belay, Solomon
    Tilahun, Seifu
    Yehualaw, Mitiku
    Matos, Jose
    Sousa, Helder
    Workneh, Endalew Temesgen
    [J]. ADVANCES IN CIVIL ENGINEERING, 2021, 2021
  • [9] Cost overrun factor analysis for hospital projects in Vietnam
    Soo-Yong Kim
    Kiet Nguyen Tuan
    Jae Do Lee
    Hai Pham
    Van Truong Luu
    [J]. KSCE Journal of Civil Engineering, 2018, 22 : 1 - 11
  • [10] Cost overrun factor analysis for hospital projects in Vietnam
    Kim, Soo-Yong
    Kiet Nguyen Tuan
    Lee, Jae Do
    Pham, Hai
    Van Truong Luu
    [J]. KSCE JOURNAL OF CIVIL ENGINEERING, 2018, 22 (01) : 1 - 11