Impacts of Change Orders on Cost and Schedule Performance and the Correlation with Project Size of DB Building Projects

被引:23
|
作者
Shrestha, Pramen P. [1 ]
Fathi, Medya [1 ]
机构
[1] Univ Nevada, Dept Civil & Environm Engn & Construct, Howard R Hughes Coll Engn, Las Vegas, NV 89154 USA
关键词
Design-build; Building projects; Change orders; Cost overrun; Schedule overrun; LABOR EFFICIENCY; MODEL;
D O I
10.1061/(ASCE)LA.1943-4170.0000311
中图分类号
D9 [法律]; DF [法律];
学科分类号
0301 ;
摘要
Few studies have been conducted to evaluate change orders in design-build (DB) projects, examining their impacts on cost and schedule performance, and their relationship with project size. This study analyzed cost, schedule, and change order data for 125 DB building projects to check whether the number of change orders for DB projects was higher than for design-bid-build (DBB) projects. All of the DB projects considered in this study had fixed their final guaranteed maximum price (GMP) before the design was 100% completed. One of the advantages of the DB delivery method is constructability, in which the designer can solicit feedback from construction personnel during the design phase; this can reduce the number of change orders. Results indicated that there were fewer change orders during DB building projects compared with DBB building projects. In addition, the percentage of projects that had cost overruns (21%) was significantly lower than that for projects that had cost underruns or were completed on budget (79%). In addition, the percentage of change orders in projects that had schedule overruns was not significantly higher than that in projects that had no schedule overruns; among other findings, the number of change orders increased as the size of the project increased (r=0.59).
引用
收藏
页数:9
相关论文
共 50 条
  • [1] Effect of Change Orders on Cost and Schedule Overruns of School Building Renovation Projects
    Shrestha, Pramen P.
    Zeleke, Haileab
    [J]. JOURNAL OF LEGAL AFFAIRS AND DISPUTE RESOLUTION IN ENGINEERING AND CONSTRUCTION, 2018, 10 (04)
  • [2] Cost Impacts of Change Orders due to Unforeseen Existing Conditions in Building Renovation Projects
    Kim, Joseph J.
    Miller, James A.
    Kim, Sunkuk
    [J]. JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT, 2020, 146 (08)
  • [3] Cost, Change Order, and Schedule Performance of Highway Projects
    Shrestha, Bandana
    Shrestha, Pramen P.
    Maharjan, Ruiko
    Gransberg, Douglas
    [J]. JOURNAL OF LEGAL AFFAIRS AND DISPUTE RESOLUTION IN ENGINEERING AND CONSTRUCTION, 2022, 14 (01)
  • [4] Effect of project complexity on cost and schedule performance in transportation projects
    Nguyen, Long D.
    Long Le-Hoai
    Tran, Dai Q.
    Dang, Chau N.
    Nguyen, Chau V.
    [J]. CONSTRUCTION MANAGEMENT AND ECONOMICS, 2019, 37 (07) : 384 - 399
  • [5] PREDICTING THE SCHEDULE AND COST PERFORMANCE IN PUBLIC SCHOOL BUILDING PROJECTS IN TAIWAN
    Juan, Yi-Kai
    Liou, Ling-Er
    [J]. JOURNAL OF CIVIL ENGINEERING AND MANAGEMENT, 2022, 28 (01) : 51 - 67
  • [6] Exploring the Impacts of Change Orders on Performance of Construction Projects in Saudi Arabia
    Alzara, Majed
    [J]. ADVANCES IN CIVIL ENGINEERING, 2022, 2022
  • [7] The impacts of change management practices on project change cost performance
    Zou, Yi
    Lee, Sang-Hoon
    [J]. CONSTRUCTION MANAGEMENT AND ECONOMICS, 2008, 26 (04) : 387 - 393
  • [8] Effects of Change Orders on Cost Growth, Schedule Growth, and Construction Intensity of Large Highway Projects
    Shrestha, Pramen P.
    Maharjan, Ruiko
    [J]. JOURNAL OF LEGAL AFFAIRS AND DISPUTE RESOLUTION IN ENGINEERING AND CONSTRUCTION, 2018, 10 (03)
  • [9] Design-Build for Transportation Projects: Cost and Schedule Change Performance Analysis
    El Asmar, Mounir
    Ramsey, David
    Gibson, G. Edward, Jr.
    Bearup, Wylie
    [J]. JOURNAL OF LEGAL AFFAIRS AND DISPUTE RESOLUTION IN ENGINEERING AND CONSTRUCTION, 2020, 12 (01)
  • [10] Cost performance of public infrastructure projects: the nemesis and nirvana of change-orders
    Love, Peter E. D.
    Irani, Zahir
    Smith, Jim
    Regan, Michael
    Liu, Junxiao
    [J]. PRODUCTION PLANNING & CONTROL, 2017, 28 (13) : 1081 - 1092