Project scheduling problem with stochastic resource-dependent activity duration

被引:2
|
作者
Zhong, Chunjie [1 ]
Yu, Ying [1 ,2 ]
Jia, YunLang [2 ]
机构
[1] Shanghai Univ, Sch Mechatron Engn & Automat, Shanghai, Peoples R China
[2] Nanjing Inst Technol, Sch Elect Power Engn, Nanjing, Peoples R China
关键词
two-point method; Monte Carlo simulation; genetic algorithm; RCPSP; ALGORITHM;
D O I
10.4028/www.scientific.net/AMM.483.607
中图分类号
TH [机械、仪表工业];
学科分类号
0802 ;
摘要
A resource-constrained project scheduling problem with stochastic resource-dependent activity durations is presented in this paper,and the two-point method is employed to simulate the uncertain property.Furthermore a genetic algorithm combined with this method is provided to solve the problem. Compared with the results from the genetic with Monte Carlo simulation, the proposed method is verified to be effective and more efficient.
引用
收藏
页码:607 / +
页数:2
相关论文
共 50 条
  • [1] Project scheduling problem with stochastic activity duration times
    Ke, Hua
    Liu, Baoding
    [J]. Proceedings of the Third International Conference on Information and Management Sciences, 2004, 3 : 284 - 289
  • [2] Project scheduling problem with stochastic activity duration times
    Ke, H
    Liu, BD
    [J]. APPLIED MATHEMATICS AND COMPUTATION, 2005, 168 (01) : 342 - 353
  • [3] Machine scheduling with deteriorating and resource-dependent maintenance activity
    Zhu, Hui
    Li, Min
    Zhou, Zhangjin
    [J]. COMPUTERS & INDUSTRIAL ENGINEERING, 2015, 88 : 479 - 486
  • [4] The Resource-constrained Project Scheduling Problem with Stochastic Activity Durations
    Creemers, S.
    [J]. 2014 IEEE INTERNATIONAL CONFERENCE ON INDUSTRIAL ENGINEERING AND ENGINEERING MANAGEMENT (IEEM), 2014, : 453 - 457
  • [5] Robust resource-constrained max-NPV project scheduling with stochastic activity duration
    Yangyang Liang
    Nanfang Cui
    Tian Wang
    Erik Demeulemeester
    [J]. OR Spectrum, 2019, 41 : 219 - 254
  • [6] Robust resource-constrained max-NPV project scheduling with stochastic activity duration
    Liang, Yangyang
    Cui, Nanfang
    Wang, Tian
    Demeulemeester, Erik
    [J]. OR SPECTRUM, 2019, 41 (01) : 219 - 254
  • [7] A purely proactive scheduling procedure for the resource-constrained project scheduling problem with stochastic activity durations
    Lamas, Patricio
    Demeulemeester, Erik
    [J]. JOURNAL OF SCHEDULING, 2016, 19 (04) : 409 - 428
  • [8] A purely proactive scheduling procedure for the resource-constrained project scheduling problem with stochastic activity durations
    Patricio Lamas
    Erik Demeulemeester
    [J]. Journal of Scheduling, 2016, 19 : 409 - 428
  • [9] Solving the project scheduling problem with dependent resource constraints
    Lin, Chun-Wei R.
    Lai, Yung Sheng
    Jeng, Shiou-Yun
    Hsiau, Hsian-Jong
    [J]. JOURNAL OF INDUSTRIAL AND PRODUCTION ENGINEERING, 2024,
  • [10] Project-Scheduling Problem With Random Time-Dependent Activity Duration Times
    Huang, Wei
    Ding, Lixin
    [J]. IEEE TRANSACTIONS ON ENGINEERING MANAGEMENT, 2011, 58 (02) : 377 - 387