Five-Year Performance of an ESE Lightning Protection System for a Large Scale PV Power Plant in Thailand

被引:1
|
作者
Kongnok, Rungphet [1 ]
Pummaitong, Thanakorn [1 ]
Plangklang, Boonyang [1 ]
机构
[1] Rajamangala Univ Technol Thanyaburi, Dept Elect Engn, Fac Engn, 39 Moo 1,Klong 6, Khlong Luang 12110, Pathum Thani, Thailand
来源
SYMMETRY-BASEL | 2021年 / 13卷 / 11期
关键词
Franklin lightning protection; ESE lightning protection; PV power plant; STROKE;
D O I
10.3390/sym13112106
中图分类号
O [数理科学和化学]; P [天文学、地球科学]; Q [生物科学]; N [自然科学总论];
学科分类号
07 ; 0710 ; 09 ;
摘要
This article presents a five-year performance review of an early streamer emission (ESE) air terminal lightning protection system for a large scale PV power plant in Thailand. The comparison effect of a Franklin lightning protection system and the ESE lightning protection system was analyzed for the PV power plant. The ESE lightning protection system was selected to be implemented in the PV power plant. The capacity of the PV power plant studied was 8 MWp on an area of 150,000 square meters in the Nong Ya Plong district, Phetchaburi province, Western Thailand. A Franklin lightning rod type was also designed to be implemented in this PV power plant. The Franklin lightning rod type comprised 122 pieces but the ESE lightning rod type consisted of only 11 pieces. The conceptual design of the Franklin rod type followed the standard of the Council of Engineers, Thailand, and the ESE lightning rod type followed the NFC17102 standard of France. The estimated cost of installation was a key comparison to select the lightning protection system; the total installation cost of the Franklin lightning rod type was USD 197,363.80 and the ESE lightning rod type was USD 44,338.06. The lightning system was applied to the lightning arrester in the power plant to provide good protection, in which the balance of the pole to the mounting position is required to optimize the system performance. The result of the simulation also showed that the shading effects of the Franklin rod type were greater than the ESE rod type. The installation cost of the Franklin lightning rod type was 4.45 times more expensive than the ESE lightning rod type. Therefore, the ESE lightning protection system was selected to be implemented in the PV power plant. From the recorded data of the five-year performance of the ESE lightning protection system (2016-2020), there were three occurrences of a lightning strike on the PV power plant. The ESE lightning protection system effectively protected and prevented the lightning strike to the PV power plant. This study can help and support with the selection of a lightning system for the protection of large scale PV power plants in the future.
引用
收藏
页数:13
相关论文
共 50 条
  • [1] An Investigation into the Influence of Large Scale PV Power Plant on the Distribution Power System Protection Performance
    Bejmert, Daniel
    Sidhu, Tarlochan S.
    PROCEEDINGS OF THE 13TH INTERNATIONAL SCIENTIFIC CONFERENCE ELECTRIC POWER ENGINEERING 2012, VOLS 1 AND 2, 2012, : 767 - 771
  • [2] Methods of Lightning Protection for the PV Power Plant
    Tan, Pi Hua
    Gan, Chin Kim
    2013 IEEE STUDENT CONFERENCE ON RESEARCH AND DEVELOPMENT (SCORED 2013), 2013, : 221 - 226
  • [3] Fault Transient Analysis and Protection Performance Evaluation within a Large-scale PV Power Plant
    Wen, Jinghua
    Luo, Meiling
    Gu, Chenjie
    Wei, Hongsheng
    Liu, Bohan
    2016 3RD INTERNATIONAL CONFERENCE ON MECHANICS AND MECHATRONICS RESEARCH (ICMMR 2016), 2016, 77
  • [4] Power Fluctuation Suppression System for Large Scale PV
    Noro, Yasuhiro
    Naoi, Shinya
    Toba, Koji
    Kimura, Misao
    Minegishi, Toshiaki
    Shimizu, Masanao
    Aoki, Shinichi
    Okuda, Yasuo
    2012 IEEE PES TRANSMISSION AND DISTRIBUTION CONFERENCE AND EXPOSITION (T&D), 2012,
  • [5] Performance results and analysis of large scale PV system
    So, Jung Hun
    Jung, Young Seok
    Yu, Byung Gyu
    Hwang, Hye Mi
    Yu, Gwon Jong
    Choi, Ju Yeop
    CONFERENCE RECORD OF THE 2006 IEEE 4TH WORLD CONFERENCE ON PHOTOVOLTAIC ENERGY CONVERSION, VOLS 1 AND 2, 2006, : 2375 - +
  • [6] Condition Monitoring of a Large-scale PV Power Plant in Australia
    Dhoke, Amit
    Sharma, Rahul
    Saha, Tapan K.
    2016 IEEE POWER AND ENERGY SOCIETY GENERAL MEETING (PESGM), 2016,
  • [7] Lightning protection of high-performance photovoltaic power plants: Issues of parts to be covered by the lightning protection system
    Tóth Z.
    Kiss I.
    Németh B.
    Berta I.
    Periodica polytechnica Electrical engineering and computer science, 2021, 65 (01): : 20 - 28
  • [8] Complete PV Power Plant Certification: New Standards for Quality Assurance of Large Scale PV Power Plants
    Farnung, Boris
    Bostock, Peter
    Brueckner, Jonas
    Kiefer, Klaus
    2014 IEEE 40TH PHOTOVOLTAIC SPECIALIST CONFERENCE (PVSC), 2014, : 1917 - 1920
  • [9] Five-Year Outcomes of a Melanoma Screening Initiative in a Large Health Care System
    Matsumoto, Martha
    Wack, Sarah
    Weinstock, Martin A.
    Geller, Alan
    Wang, Hong
    Solano, Francis X.
    Kirkwood, John M.
    Ferris, Laura K.
    JAMA DERMATOLOGY, 2022, 158 (05) : 504 - 512
  • [10] Study on Lightning Protection Design for Automatic Instrument System of Nuclear Power Plant
    Liu, Lu
    Ma, Sai
    Xiao, Zhou
    2019 CHINESE AUTOMATION CONGRESS (CAC2019), 2019, : 5126 - 5131