IP Start-up Control for 300MW Turbine Unit with Bypass System

被引:1
|
作者
Wang, Weibing [1 ]
Wang, Xudong [2 ]
Liu, Dongju [1 ]
机构
[1] Harbin Univ Sci & Technol, Coll Comp Sci & Technol, Harbin 150080, Peoples R China
[2] Harbin Univ Sci & Technol, Coll Elect & Elect Engn, Harbin 150080, Peoples R China
关键词
300MW Turbine Unit; IP Start-up; Bypass Control;
D O I
10.1016/j.proeng.2011.08.1115
中图分类号
TE [石油、天然气工业]; TK [能源与动力工程];
学科分类号
0807 ; 0820 ;
摘要
Based on the analysis of characters of 300MW unit IP start-up, an approach with bypass system about turbine control has been explored in this paper. Control model for IP start-up is given. The pre-warm control of IP start-up and the start-up mode switching are discussed in detail. Control logic for main valve, valve exchanging and bypass system are properly designed. The opening curve of IP regulation valve is given. The schedule is successfully applied in the IP start-up of #8 turbine system, Shalingzi power plant, China. The actually operation results shows that the control logic is right and reasonable. It's available for the system requirements. (C) 2010 Published by Elsevier Ltd. Selection and/or peer-review under responsibility of Society for Automobile, Power and Energy Engineering
引用
收藏
页数:6
相关论文
共 50 条
  • [1] Reconstruction of the gland sealing system of a 300MW steam turbine unit
    Xie, DM
    Liu, GL
    Wang, JM
    Yang, J
    [J]. ENERGY CONVERSION AND APPLICATION, VOL I AND II, 2001, : 862 - 866
  • [2] The optimization of the start-up scheduling for a 320 MW steam turbine
    Ji, Dong-Mei
    Sun, Jia-Qi
    Dui, Yue
    Ren, Jian-Xing
    [J]. ENERGY, 2017, 125 : 345 - 355
  • [3] FEATURES OF KHTGZ K-300-240 TURBINE START UP ACCORDING TO STANDARD START UP PROCEDURE FOR A 300 MW 2-BOILER UNIT
    CHERNETSKII, NS
    POLYAKOV, VS
    FOLIN, YA
    POLYAKOV, VA
    GALATSAN, VN
    [J]. THERMAL ENGINEERING, 1970, 17 (02) : 16 - +
  • [4] Improving the power unit operation flexibility by the turbine start-up optimization
    Nowak, Grzegorz
    Rusin, Andrzej
    Lukowicz, Henryk
    Tomala, Martyna
    [J]. ENERGY, 2020, 198
  • [5] START-UP PHASE OF THTR 300
    GUTSCH, U
    LEITHNER, D
    BRANDES, S
    OPPENHEI.CL
    [J]. ATOMWIRTSCHAFT-ATOMTECHNIK, 1974, 19 (04): : 176 - 178
  • [6] EXPERIENCE IN DDC TURBINE START-UP
    HOWARD, JR
    [J]. ISA JOURNAL, 1966, 13 (07): : 61 - &
  • [7] Assessing the flaws in welded seam of header of a 300MW steam turbine generator unit
    Song, Li
    Yang, Shuicheng
    Wei, Fengtao
    [J]. ENGINEERING PLASTICITY AND ITS APPLICATIONS FROM NANOSCALE TO MACROSCALE, PTS 1 AND 2, 2007, 340-341 : 1431 - +
  • [8] Flow Parameter Changes in Steam Turbine 10 MW during Start-Up and Heating
    Hoznedl, Michal
    Tajc, Ladislav
    [J]. 36TH MEETING OF DEPARTMENTS OF FLUID MECHANICS AND THERMODYNAMICS, 2017, 1889
  • [9] Experimental Investigation of a 10 MW Prototype Kaplan Turbine during Start-Up Operation
    Dehkharqani, Arash Soltani
    Engstrom, Fredrik
    Aidanpaa, Jan-Olov
    Cervantes, Michel J.
    [J]. ENERGIES, 2019, 12 (23)
  • [10] Assessment of 300MW Turbine Generator Stator Insulation
    Wang, Lijun
    Zhang, Yizhong
    Jin, Wenjing
    Shi, Jingzhe
    Zhou, Song
    Li, Qiang
    Liu, Song
    [J]. PROCEEDINGS OF 2014 INTERNATIONAL SYMPOSIUM ON ELECTRICAL INSULATING MATERIALS (ISEIM 2014), 2014, : 500 - 502