IP Start-up Control for 300MW Turbine Unit with Bypass System

被引:1
|
作者
Wang, Weibing [1 ]
Wang, Xudong [2 ]
Liu, Dongju [1 ]
机构
[1] Harbin Univ Sci & Technol, Coll Comp Sci & Technol, Harbin 150080, Peoples R China
[2] Harbin Univ Sci & Technol, Coll Elect & Elect Engn, Harbin 150080, Peoples R China
关键词
300MW Turbine Unit; IP Start-up; Bypass Control;
D O I
10.1016/j.proeng.2011.08.1115
中图分类号
TE [石油、天然气工业]; TK [能源与动力工程];
学科分类号
0807 ; 0820 ;
摘要
Based on the analysis of characters of 300MW unit IP start-up, an approach with bypass system about turbine control has been explored in this paper. Control model for IP start-up is given. The pre-warm control of IP start-up and the start-up mode switching are discussed in detail. Control logic for main valve, valve exchanging and bypass system are properly designed. The opening curve of IP regulation valve is given. The schedule is successfully applied in the IP start-up of #8 turbine system, Shalingzi power plant, China. The actually operation results shows that the control logic is right and reasonable. It's available for the system requirements. (C) 2010 Published by Elsevier Ltd. Selection and/or peer-review under responsibility of Society for Automobile, Power and Energy Engineering
引用
收藏
页数:6
相关论文
共 50 条
  • [31] A multi agent system for monitoring industrial gas turbine start-up sequences
    Mangina, EE
    McArthur, SDJ
    McDonald, JR
    Moyes, A
    PICA 2001: 22ND IEEE POWER ENGINEERING SOCIETY INTERNATIONAL CONFERENCE ON POWER INDUSTRY COMPUTER APPLICATIONS, 2001, : 138 - 140
  • [32] Start-up system design for small scale autonomous DFIG wind turbine
    Ghodbane-Cherif, Meriem
    Skander-Mustapha, Sondes
    Slama-Belkhodja, Ilhem
    WIND ENGINEERING, 2021, 45 (04) : 753 - 768
  • [33] Realize the feedback control based on incremental observer in 300MW unit adopting EDPF-NT distributed control system
    Han Zhong-xu
    Zhou Chuan-xin
    Wang Zhong-sheng
    Luo Zhan-qiang
    Pan Gang
    Qiu Zhong-chang
    ICIEA 2007: 2ND IEEE CONFERENCE ON INDUSTRIAL ELECTRONICS AND APPLICATIONS, VOLS 1-4, PROCEEDINGS, 2007, : 1009 - +
  • [34] The Start-up Characteristics of Pump as Turbine System During Different Valve Openings
    Li, Jinfu
    Zhang, Yuliang
    Deng, Qianfa
    Kung Cheng Je Wu Li Hsueh Pao/Journal of Engineering Thermophysics, 2023, 44 (12): : 3292 - 3304
  • [35] Research on the start-up of the +300kvar ASVG
    Tsinghua Univ, Beijing, China
    Qinghua Daxue Xuebao, 7 (44-47):
  • [36] A multi agent system for monitoring industrial gas turbine start-up sequences
    Mangina, EE
    McArthur, SDJ
    McDonald, JR
    Moyes, A
    IEEE TRANSACTIONS ON POWER SYSTEMS, 2001, 16 (03) : 396 - 401
  • [37] Integrated nonlinear model of 300MW power unit for system dynamic performance studies
    Liu, CL
    Liang, WP
    Ma, JY
    Ma, GF
    PROCEEDINGS OF THE 2004 INTERNATIONAL CONFERENCE ON MACHINE LEARNING AND CYBERNETICS, VOLS 1-7, 2004, : 361 - 366
  • [38] Research on the start-up of the +300kvar ASVG
    Zhang, Li
    Chen, Jianye
    Wang, Zhonghong
    Han, Yingduo
    Qinghua Daxue Xuebao/Journal of Tsinghua University, 37 (07): : 44 - 47
  • [39] Nonlinear boiler model of 300MW power unit for system dynamic performance studies
    Liu, CL
    Liu, JZ
    Niu, YG
    Liang, WP
    ISIE 2001: IEEE INTERNATIONAL SYMPOSIUM ON INDUSTRIAL ELECTRONICS PROCEEDINGS, VOLS I-III, 2001, : 1296 - 1300
  • [40] Vail versus Morgan: Control of the start-up bell system
    Bellaver, RF
    IEEE TECHNOLOGY AND SOCIETY MAGAZINE, 2002, 21 (02) : 31 - 35