A competitive heuristic solution technique for Resource-Constrained Project Scheduling

被引:111
|
作者
Tormos, P [1 ]
Lova, A [1 ]
机构
[1] Univ Politecn Valencia, Dept Stat & Operat Res, Valencia 46022, Spain
关键词
project management; resource-constrained project scheduling; random sampling; backward-forward;
D O I
10.1023/A:1010997814183
中图分类号
C93 [管理学]; O22 [运筹学];
学科分类号
070105 ; 12 ; 1201 ; 1202 ; 120202 ;
摘要
In this work a new heuristic solution technique for the Resource-Constrained Project Scheduling Problem (RCPSP) is proposed. This technique is a hybrid multi-pass method that combines random sampling procedures with a backward-forward method. The impact of each component of the algorithm is evaluated through a step-wise computational analysis which in addition permits the value of their parameters to be specified. Furthermore, the performance of the new technique is evaluated against the best currently available heuristics using a well known set of instances. The results obtained point out that the new technique greatly outperforms both the heuristics and metaheuristics currently available for the RCPSP being thus competitive with the best heuristic solution techniques for this problem.
引用
收藏
页码:65 / 81
页数:17
相关论文
共 50 条
  • [1] A Competitive Heuristic Solution Technique for Resource-Constrained Project Scheduling
    Pilar Tormos
    Antonio Lova
    Annals of Operations Research, 2001, 102 : 65 - 81
  • [2] A NEW HEURISTIC SOLUTION METHOD IN RESOURCE-CONSTRAINED PROJECT SCHEDULING
    BELL, CE
    HAN, J
    NAVAL RESEARCH LOGISTICS, 1991, 38 (03) : 315 - 331
  • [3] Fuzzy resource-constrained project scheduling with multiple routes: A heuristic solution
    Birjandi, Alireza
    Mousavi, S. Meysam
    AUTOMATION IN CONSTRUCTION, 2019, 100 : 84 - 102
  • [4] A Flexible Heuristic Algorithm for Resource-Constrained Project Scheduling
    Seda, Milos
    Matousek, Radomil
    Osmera, Pavel
    Pivonka, Petr
    Sandera, Cenek
    WCECS 2009: WORLD CONGRESS ON ENGINEERING AND COMPUTER SCIENCE, VOLS I AND II, 2009, : 730 - +
  • [5] A heuristic approach to fuzzy resource-constrained project scheduling
    Yeh, CH
    Pan, HQ
    Willis, RJ
    COMPUTATIONAL INTELLIGENCE FOR MODELLING, CONTROL & AUTOMATION - EVOLUTIONARY COMPUTATION & FUZZY LOGIC FOR INTELLIGENT CONTROL, KNOWLEDGE ACQUISITION & INFORMATION RETRIEVAL, 1999, 55 : 423 - 428
  • [6] Comparison of Heuristic Priority Rules in the Solution of the Resource-Constrained Project Scheduling Problem
    Turkakin, Osman Hurol
    Arditi, David
    Manisali, Ekrem
    SUSTAINABILITY, 2021, 13 (17)
  • [7] AN ITERATIVE SCHEDULING TECHNIQUE FOR RESOURCE-CONSTRAINED PROJECT SCHEDULING
    LI, KY
    WILLIS, RJ
    EUROPEAN JOURNAL OF OPERATIONAL RESEARCH, 1992, 56 (03) : 370 - 379
  • [8] A competitive genetic algorithm for resource-constrained project scheduling
    Hartmann, S
    NAVAL RESEARCH LOGISTICS, 1998, 45 (07) : 733 - 750
  • [9] HEURISTIC PERFORMANCE AND NETWORK RESOURCE CHARACTERISTICS IN RESOURCE-CONSTRAINED PROJECT SCHEDULING
    ULUSOY, G
    OZDAMAR, L
    JOURNAL OF THE OPERATIONAL RESEARCH SOCIETY, 1989, 40 (12) : 1145 - 1152
  • [10] Heuristic algorithm for flexible resource-constrained project scheduling problem
    Jia, Yan
    Wang, Zhimin
    Zhang, Yuegang
    Jisuanji Jicheng Zhizao Xitong/Computer Integrated Manufacturing Systems, CIMS, 2015, 21 (07): : 1846 - 1855