Numerical Analysis on Large-Section Pipe Jacking within Close Distance in Soft Soil

被引:0
|
作者
Xie, Xiaoli [1 ]
Ye, Bin [1 ]
机构
[1] Tongji Univ, Dept Geotech Engn, Shanghai, Peoples R China
关键词
TECHNOLOGY;
D O I
暂无
中图分类号
TU [建筑科学];
学科分类号
0813 ;
摘要
Three parallel large-section tunnels within close proximity were constructed by pipe jacking to build the Jing'ansi station of Shanghai Metro Line 14. The three tunnels include Tunnel A, Tunnel B, which is on the left of Tunnel A, and Tunnel C, which is on the top of Tunnel A. Cross-section size of the three tunnels is 9.90 x 8.70 m, 9.90 x 8.70 m, and 9.50 x 4.88 m, respectively. Because such large-section pipe jacking in soft soil is rarely reported, a three-dimensional numerical model was developed in this study to simulate the entire construction process of pipe jacking to provide guidance for the engineers. Numerical simulation results demonstrated that the construction of the current tunnel obviously affected the internal force of the previously constructed tunnels. The deformation of the ground surface and the lateral displacement of the neighboring pile groups increased gradually in the process of constructing Tunnels A and B but increased slightly in the process of constructing Tunnel C.
引用
收藏
页码:156 / 165
页数:10
相关论文
共 50 条
  • [1] Model tests on large-section and shallow soil rectangular pipe jacking
    Pan, Yu-Qing
    Zhen, Liang
    Jiang, Hai-Li
    Li, Xiao-Jun
    Yantu Gongcheng Xuebao/Chinese Journal of Geotechnical Engineering, 2022, 44 : 125 - 129
  • [2] Experimental Study on the Complex Contact Frictional Property of an Ultralong Distance Large-Section Concrete Pipe Jacking and Prediction of Pipe String Stuck
    He, Ziyong
    Chen, Jiangong
    ADVANCES IN MATERIALS SCIENCE AND ENGINEERING, 2019, 2019
  • [3] Structural response of existed metro tunnels to adjacent large-section pipe jacking construction
    Liu, Bo
    Zhang, Dingwen
    Fang, Lei
    PROCEEDINGS OF THE INTERNATIONAL SCIENTIFIC CONFERENCE TRANSPORTATION GEOTECHNICS AND GEOECOLOGY (TGG-2017), 2017, 189 : 11 - 17
  • [4] Formulation optimization and performance analysis of the thixotropic slurry for large-section rectangular pipe jacking in anhydrous sand
    Liu, Shuo
    Zhang, Bin
    Zhang, Xue
    Fan, Dongsheng
    Wang, Hanxun
    Yu, Ming
    CONSTRUCTION AND BUILDING MATERIALS, 2022, 357
  • [5] Temporal variation laws of longitudinal stress of pipe jacking with large-section steel structure
    Liu, Xian
    Jiao, Bo-Chang
    Pan, Wei-Qiang
    Huang, Ai-Jun
    Yantu Gongcheng Xuebao/Chinese Journal of Geotechnical Engineering, 2022, 44 (10): : 1810 - 1816
  • [6] Analytical solutions for surface deformation induced by jacking large-section pipe curtain box culvert
    Zhang, Kunyong
    Li, Danyang
    Zhang, Meng
    Shen, Xiaorui
    Yantu Gongcheng Xuebao/Chinese Journal of Geotechnical Engineering, 47 (01): : 184 - 191
  • [7] Soil Disturbance Analysis and Settlement Control of Rectangular Pipe Jacking with Super Large Section
    Jiang, Liutao
    Li, Hongbo
    Journal of Railway Engineering Society, 2023, 40 (03) : 64 - 70
  • [8] Ground Settlement Law, Jacking Force Prediction, and Control Countermeasures for Large-Section Rectangular Pipe Jacking of National Highway Underpass
    Qian, Deyu
    Jiao, Hexi
    Li, Zexiang
    Zhu, Yingli
    Liu, Jiale
    Chen, Zhenglong
    Gao, Xing
    Liu, Hongwang
    Tao, Baihong
    Xu, Zixiang
    SUSTAINABILITY, 2023, 15 (17)
  • [9] Application and analysis of forepoling and large-section box culvert jacking for underpass highway construction
    Zhengzhou Supervise Bureau of Highway, Zhengzhou 450015, China
    不详
    Tumu Gongcheng Xuebao, 2008, 4 (106-111):
  • [10] Analysis of construction monitoring of large-section box culvert jacking process underpass expressway
    State Key Laboratory of Geomechanics and Geotechnical Engineering, Institute of Rock and Soil Mechanics, Chinese Academy of Sciences, Wuhan, Hubei 430071, China
    不详
    不详
    Yanshilixue Yu Gongcheng Xuebao, 2009, 9 (1790-1797):