Ground Settlement Law, Jacking Force Prediction, and Control Countermeasures for Large-Section Rectangular Pipe Jacking of National Highway Underpass

被引:2
|
作者
Qian, Deyu [1 ]
Jiao, Hexi [1 ]
Li, Zexiang [1 ,2 ]
Zhu, Yingli [1 ]
Liu, Jiale [1 ]
Chen, Zhenglong [1 ]
Gao, Xing [1 ]
Liu, Hongwang [1 ]
Tao, Baihong [1 ]
Xu, Zixiang [1 ]
机构
[1] China Univ Min & Technol, Sch Mines, Xuzhou 221116, Peoples R China
[2] Wuhan Metro Operat Ltd Co, Wuhan 430035, Peoples R China
关键词
subway entrance; rectangular pipe jacking; jacking force; slurry sleeve; grouting pressure; earth chamber pressure; ground settlement; control countermeasures; CONSTRUCTION;
D O I
10.3390/su151712888
中图分类号
X [环境科学、安全科学];
学科分类号
08 ; 0830 ;
摘要
The rectangular pipe jacking method is an efficient, green, trenchless technology for constructing urban underground space. However, some problems, including the high jacking resistance, the instability of the tunneling face, and excessive ground settlement during the large-section rectangular pipe jacking for the underpass of national highways, seriously affect construction safety and traffic. Based on the engineering background of the large-section rectangular pipe jacking in constructing the subway entrance tunnel of Guangzhou Metro Line 7, this work adopts the methods of theoretical calculation, numerical simulation, and engineering application. Five kinds of mechanical models for pipe soil slurry interactions in rectangular pipe jacking are analyzed. An evaluation of the applicability of the jacking force prediction of the different models is conducted. Moreover, the ground settlement law for the large-section rectangular pipe jacking for the underpass of national highways under different influencing factors, including slurry sleeve thickness, grouting pressure, and earth chamber pressure, is revealed. The control countermeasures of the ground settlements, such as installing a waterproof rubber curtain for the tunnel portal, pipe jacking machine receiving techniques, thixotropic slurry for reducing friction resistance, and soil stability at the tunneling face, are carried out. The results show that there is no need to install an intermediate jacking station in the large-section rectangular pipe jacking project with a jacking distance of 63 m. The most reasonable thickness of the thixotropic slurry sleeve is about 150 mm. The most reasonable grouting pressure range is 600-700 kPa. An earth chamber pressure of about 153 kPa is more reasonable to control the soil stability of the tunneling face. The engineering practice shows that the maximum ground settlement of the national highway during jacking is 10 mm. The maintenance effect is excellent, and the traffic operates normally.
引用
收藏
页数:23
相关论文
共 49 条
  • [1] Application and analysis of forepoling and large-section box culvert jacking for underpass highway construction
    Zhengzhou Supervise Bureau of Highway, Zhengzhou 450015, China
    不详
    Tumu Gongcheng Xuebao, 2008, 4 (106-111):
  • [2] Model tests on large-section and shallow soil rectangular pipe jacking
    Pan, Yu-Qing
    Zhen, Liang
    Jiang, Hai-Li
    Li, Xiao-Jun
    Yantu Gongcheng Xuebao/Chinese Journal of Geotechnical Engineering, 2022, 44 : 125 - 129
  • [3] Soil Disturbance Analysis and Settlement Control of Rectangular Pipe Jacking with Super Large Section
    Jiang, Liutao
    Li, Hongbo
    Journal of Railway Engineering Society, 2023, 40 (03) : 64 - 70
  • [4] Frictional resistance calculation and jacking force prediction of rectangular pipe jacking
    Kong, Chao
    Guan, Guoqing
    Gu, Song
    Zhou, Zaiyan
    Wang, Haiyan
    SCIENTIFIC REPORTS, 2023, 13 (01)
  • [5] Frictional resistance calculation and jacking force prediction of rectangular pipe jacking
    Chao Kong
    Guoqing Guan
    Song Gu
    Zaiyan Zhou
    Haiyan Wang
    Scientific Reports, 13
  • [6] Pipe-Soil Contact State and Jacking Force Prediction of Rectangular Pipe Jacking
    Jiao C.-L.
    Zhao X.
    Niu F.-J.
    Dongbei Daxue Xuebao/Journal of Northeastern University, 2020, 41 (10): : 1459 - 1464
  • [7] Construction of a large-section long pedestrian underpass using pipe jacking in muddy silty clay: A case study
    Zhang, Dingwen
    Liu, Bo
    Qin, Yujun
    TUNNELLING AND UNDERGROUND SPACE TECHNOLOGY, 2016, 60 : 151 - 164
  • [8] Analysis of construction monitoring of large-section box culvert jacking process underpass expressway
    State Key Laboratory of Geomechanics and Geotechnical Engineering, Institute of Rock and Soil Mechanics, Chinese Academy of Sciences, Wuhan, Hubei 430071, China
    不详
    不详
    Yanshilixue Yu Gongcheng Xuebao, 2009, 9 (1790-1797):
  • [9] Frictional analysis of pipe-slurry-soil interaction and jacking force prediction of rectangular pipe jacking
    Wen, Kai
    Shimada, Hideki
    Zeng, Wei
    Sasaoka, Takashi
    Qian, Deyu
    EUROPEAN JOURNAL OF ENVIRONMENTAL AND CIVIL ENGINEERING, 2020, 24 (06) : 814 - 832
  • [10] Formulation optimization and performance analysis of the thixotropic slurry for large-section rectangular pipe jacking in anhydrous sand
    Liu, Shuo
    Zhang, Bin
    Zhang, Xue
    Fan, Dongsheng
    Wang, Hanxun
    Yu, Ming
    CONSTRUCTION AND BUILDING MATERIALS, 2022, 357