Experimental Investigation of the Original Project of Yukari Kalekoy Dam and Hydroelectric Power Plant Spillway

被引:0
|
作者
Gogus, Mustafa [1 ]
Altan-Sakarya, A. Burcu [1 ]
Koken, Mete [1 ]
机构
[1] Middle East Tech Univ, Dept Civil Engn, Hydromech Lab, TR-06800 Ankara, Turkey
关键词
hydraulic model; spillway; spillway aerators; cavitation;
D O I
10.1016/j.proeng.2016.08.563
中图分类号
TU [建筑科学];
学科分类号
0813 ;
摘要
Hydraulic model tests of the spillway of Yukar Kalekoy Dam and Hydroelectric Power Plant (HPP) were carried out at Hydromechanics Laboratory of Middle East Technical University (METU), Ankara. In order to investigate the flow conditions in the approach channel, over the weir structure, around the spillway piers, along the spillway chute channels and after the flip buckets, and also to observe the performance of the aeration devices, a model of 1/70 length scale was constructed. The model area covers an about 400 m x 450 m section of the Yukar Kalekoy reservoir, the whole spillway structure and a part of the river area of about 150 m x 200 m downstream of the flip buckets. Experiments were carried out at various discharges; QPMF, Q(1000) and Q(100) with fully open radial gates as well as with partly open radial gates at Q(1000). Flow depths, pressure heads of the flows along the spillway structure were measured, cavitation indexes and air concentrations of the flows were determined. From the observations and experimental results, it was concluded that the flow conditions in the approach channel of the spillway, over the weir structure, around the spillway piers, along and after the flip buckets are quite good from the hydraulics point of view. However, the flows were not sufficiently aerated in the spillway chutes, in Channels I and II, after the available aerators presented in the original design of the spillway. After the experiments conducted on the "original model" it was decided that some modifications should be done. In order to improve the performance of the available aerators, the heights of the aerator deflectors were increased by 0.20 m by keeping their lengths in the flow direction almost as before. (C) 2016 The Authors. Published by Elsevier Ltd.
引用
收藏
页码:313 / 317
页数:5
相关论文
共 50 条
  • [31] Condition of the foundation bed for the concrete dam of the Boguchany hydroelectric power plant as determined from field observations
    Kalustyan E.S.
    Gorbushina V.K.
    Koryabin I.A.
    [J]. Hydrotechnical Construction, 2000, 34 (4) : 163 - 167
  • [32] Design and execution of reinforcement systems for the discontinuous rock masses underlying an intake dam for a hydroelectric power plant
    Mizokami, T
    Sasada, T
    Esaki, T
    Jiang, YJ
    [J]. FIELD MEASUREMENTS OF GEOMECHANICS, 1999, : 359 - 362
  • [33] Numerical and experimental investigation of optimum surge tank forms in hydroelectric power plants
    Kendir, Tarik Efe
    Ozdamar, Aydogan
    [J]. RENEWABLE ENERGY, 2013, 60 : 323 - 331
  • [34] Vladimirskaya hydroelectric pumped storage power plant as the first pilot power project of the 21st century
    Tikhomirova N.V.
    Novozhenin V.D.
    [J]. Power Technology and Engineering, 2004, 38 (6) : 309 - 314
  • [35] Seasonal Changes in the Parameters of the Normal Modes of the Chirkey Hydroelectric Power Plant Dam According to the Standing Waves Method
    Liseikin A.V.
    Seleznev V.S.
    Adilov Z.A.
    [J]. Power Technology and Engineering, 2020, 53 (06): : 681 - 686
  • [36] Condition of the Gotsatli Hydroelectric Power Plant Dam During Filling of the Reservoir According to Field Observations and Numerical Modeling
    Denisov G.V.
    Davydkin O.Y.
    Vorob’ev K.M.
    [J]. Power Technology and Engineering, 2017, 51 (3) : 267 - 273
  • [37] The hydroelectric in Brazil: a comparative analysis of planning and results with the Three Gorges Dam Hydro Electric Power Plant, China
    Bizawu, Sebastien Kiwonghi
    de Oliveira, Edson Rodrigues
    [J]. REVISTA DE DIREITO DA CIDADE-CITY LAW, 2022, 14 (03): : 1416 - 1461
  • [38] MALACOLOGICAL INVESTIGATION OF THE FULLY OPERATIONAL NAM THEUN 2 HYDROELECTRIC DAM PROJECT IN KHAMMOUANE PROVINCE, CENTRAL LAO PDR
    Sri-aroon, Pusadee
    Chusongsang, Phiraphol
    Chusongsang, Yupa
    Limpanont, Yanin
    Surinthwong, Pompimol
    Vongphayloth, Khamsing
    Brey, Paul T.
    [J]. SOUTHEAST ASIAN JOURNAL OF TROPICAL MEDICINE AND PUBLIC HEALTH, 2015, 46 (05) : 866 - 879
  • [39] Omsk Hydroelectric Power Plant Project in Economic History of Region in 1930s-1980s
    Mostovenko, Maxim S.
    [J]. NAUCHNYI DIALOG, 2024, 13 (01): : 431 - 447
  • [40] Hydraulic transient simulation and characteristic investigation on Kaplan type hydroelectric power Plant with open channel
    Chen, S.
    Zhang, J.
    Yu, X. D.
    [J]. 29TH IAHR SYMPOSIUM ON HYDRAULIC MACHINERY AND SYSTEMS, 2019, 240