Construction and alignment control of the middle steel pylon of Taizhou Bridge

被引:2
|
作者
Ji Lin 1
2.CCCC Second Harbour Engineering Company Limited
机构
关键词
construction; alignment control; steel pylon; whole process;
D O I
暂无
中图分类号
U445.4 [施工技术];
学科分类号
摘要
The general construction procedure of the steel middle pylon is briefly introduced. The alignment control of the pylon is carried out during the whole process of the construction. The control concept is extended to the manufacture stage. The manufacturing alignment error is strictly controlled in the segments precast process in factory, and the error is recognized and predicted precisely during the installation stage. The adjusting joints are employed to amend the accumulated error, which ensure that the steel pylon alignment could satisfy the precision requirements after installation.
引用
收藏
页码:46 / 50
页数:5
相关论文
共 50 条
  • [41] USE OF STEEL IN BRIDGE CONSTRUCTION
    HARPER, WJ
    PHILOSOPHICAL TRANSACTIONS OF THE ROYAL SOCIETY A-MATHEMATICAL PHYSICAL AND ENGINEERING SCIENCES, 1976, 282 (1307): : 37 - +
  • [42] STEEL BRIDGE CONSTRUCTION IN JAPAN
    FUKUMOTO, Y
    JOURNAL OF CONSTRUCTIONAL STEEL RESEARCH, 1989, 13 (2-3) : 259 - 267
  • [43] Key Techniques for Construction of Pylon of Channel Bridge of Pingtan Straits Rail-cum-Road Bridge
    Wang, Dong-Hui
    Han, Bing
    Bridge Construction, 2019, 49 (03): : 1 - 5
  • [45] Construction Control Techniques for Superstructure of a Mono-pylon Single-Suspension-Span Earth Anchored Suspension Bridge
    Yu, Long
    Tao, Lu
    Zhang, Da-Bing
    Xu, Wei
    Wu, Yong-Hong
    Bridge Construction, 2022, 52 (02) : 141 - 148
  • [46] THE ALIGNMENT CONTROL OF LARGE-SPAN CONTINUOUS BEAM BRIDGE CANTILEVER CONSTRUCTION METHOD
    Peng Xiaotao
    Xiong Yi
    Wu Yong
    Meng Dan
    ADVANCES IN CIVIL STRUCTURES, PTS 1 AND 2, 2013, 351-352 : 1226 - 1230
  • [47] Appliance of inversion theory in alignment control of plane curved bridge by cantilever segmental construction
    Sun, Xue-Xian
    Zhang, Hui
    Gongcheng Lixue/Engineering Mechanics, 2007, 24 (12): : 135 - 139
  • [48] Analysis of dynamic parameters of steel truss girder cable-stayed bridge with single pylon and single cable plane at construction stage
    Zeng, Yong
    Zheng, Hui-Jun
    Liu, Yan
    Zhang, Da-Wei
    Bridge Construction, 2016, 46 (04) : 35 - 39
  • [49] Key Pylon Construction Techniques for Main Bridge of Lingang Changjiang River Rail-cum-Road Bridge
    Chen Z.
    Yu Z.-B.
    Xu D.-H.
    Han B.
    Chen B.
    Bridge Construction, 2023, 53 (01) : 123 - 129
  • [50] Key Pylon and Girder Construction Techniques for Cable-Stayed Bridge with Mono-columned Pylons and Two Separated Steel Boxes
    Chang, Da-Bao
    Bridge Construction, 2020, 50 : 121 - 126