Investigating the challenges related to combining BIM and Last Planner System on construction sites

被引:0
|
作者
Conrad BOTON
Yaya PITTI
Daniel FORGUES
IvankaIORDANOVA
机构
[1] Department of Construction Engineering
[2] école de Technologie Supérieure
关键词
D O I
暂无
中图分类号
TU17 [电子计算机在建筑中的应用]; F426.92 []; TU71 [施工管理];
学科分类号
081304 ; 1201 ;
摘要
The construction industry is facing a gradual but important transformation toward more productivity and collaboration. In this framework, two major approaches are often cited in the literature as having the potential to improve the practices in the industry: Building Information Modeling(BIM) and Lean Construction. Several scientific studies have demonstrated the synergy of these two approaches and very recent research has reported positive results from the use of software applications as support for their implementation on construction sites. However, the stakes of such integration have been very little studied.This article presents the results of a research project conducted within a general contractor firm that decided to implement BIM and Last Planner System(LPS) on its construction sites. The research uses a four-stage action research approach, including the characterization of the research issue, the establishment of an action plan, its implementation and its evaluation. Compared to recent related studies, the research is less enthusiastic. While it highlights the need for new tools to improve production planning and control, it also points to a strong resistance to change by practitioners at the site. They emphasize the necessity for adequate pre-service training and the need for new resources that can work full-time on the ongoing training of site teams. In addition, some limitations of the tool lead workers to believe that it can quickly become a factor that slows down their daily work rather than improving it. Based on the advice of professionals, the paper formulates some recommendations to the industry,the researchers and the software developers.
引用
收藏
页码:172 / 182
页数:11
相关论文
共 50 条
  • [21] Predicting construction schedule performance with last planner system and machine learning
    Lagos, Camilo I.
    Herrera, Rodrigo F.
    Cawley, Alejandro F. Mac
    Alarcon, Luis F.
    AUTOMATION IN CONSTRUCTION, 2024, 167
  • [22] Development of Approach to Support Construction Stakeholders in Implementation of the Last Planner System
    Daniel, Emmanuel Itodo
    Pasquire, Christine
    Dickens, Graham
    JOURNAL OF MANAGEMENT IN ENGINEERING, 2019, 35 (05)
  • [23] THE LAST PLANNER SYSTEM OF CONSTRUCTION PLANNING AND CONTROL AS A TEACHING AND LEARNING TOOL
    Pellicer, Eugenio
    Cervero, Fernando
    Lozano, Alicia
    Luis Ponz-Tienda, Jose
    INTED2015: 9TH INTERNATIONAL TECHNOLOGY, EDUCATION AND DEVELOPMENT CONFERENCE, 2015, : 4877 - 4884
  • [24] Improving construction management practice with the Last Planner System: a case study
    AlSehaimi, Abdullah
    Fazenda, Patricia
    Koskela, Lauri
    ENGINEERING CONSTRUCTION AND ARCHITECTURAL MANAGEMENT, 2014, 21 (01) : 51 - +
  • [25] Survey of Motivations, Benefits, and Implementation Challenges of Last Planner System Users
    Fernandez-Solis, Jose L.
    Porwal, Vishal
    Lavy, Sarel
    Shafaat, Ali
    Rybkowski, Zofia K.
    Son, Kiyoung
    Lagoo, Nishi
    JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT, 2013, 139 (04) : 354 - 360
  • [26] Effective Implementation of Last Planner System in Construction Projects: A Case Study
    Gjerde, M. R. D.
    Ratnayake, R. M. C.
    Samarakoon, S. M. S. M. K.
    2019 IEEE INTERNATIONAL CONFERENCE ON INDUSTRIAL ENGINEERING AND ENGINEERING MANAGEMENT (IEEM), 2019, : 1139 - 1144
  • [27] Mitigating Making-Do Practices Using the Last Planner System and BIM: A System Dynamic Analysis
    Karaz, Mahmoud
    Teixeira, Jose Manuel Cardoso
    do Amaral, Tatiana Gondim
    BUILDINGS, 2024, 14 (08)
  • [28] Techniques and benefits of implementing the last planner system in the Gaza Strip construction industry
    Tayeh, Bassam A.
    Al Hallaq, Khalid
    Zahoor, Hafiz
    Al Faqawi, Abdulla H.
    ENGINEERING CONSTRUCTION AND ARCHITECTURAL MANAGEMENT, 2019, 26 (07) : 1424 - 1436
  • [29] Integration of BREEAM-NOR in construction projects: Utilizing the Last Planner System
    Nesteby, Ase I.
    Aarrestad, Marie E.
    Lohne, Jardar
    Bohne, Rolf A.
    SUSTAINABLE BUILT ENVIRONMENT TALLINN AND HELSINKI CONFERENCE SBE16 BUILD GREEN AND RENOVATE DEEP, 2016, 96 : 100 - 111
  • [30] Evaluating the Efficacy of a Dedicated Last Planner® System Facilitator to Enhance Construction Productivity
    Power, William
    Sinnott, Derek
    Lynch, Patrick
    CONSTRUCTION ECONOMICS AND BUILDING, 2021, 21 (03): : 142 - 158