Minimum feasible tariff model for BOT water supply projects in Malaysia

被引:20
|
作者
Cheng Lianyu [1 ]
Tiong, Robert L. K. [2 ]
机构
[1] Henan Inst Finance & Econ, Zhengzhou, Henan, Peoples R China
[2] Nanyang Technol Univ, Sch Civil Environm Engn, Singapore, Singapore
关键词
BOT; water supply project; risk allocation; tariff-at-risk; minimum feasible tariff;
D O I
10.1080/0144619042000287778
中图分类号
F [经济];
学科分类号
02 ;
摘要
A key issue in implementing water supply projects based on the build, operate and transfer approach is risk allocation. Project risks should be allocated to the best competent party through proper contractual arrangements or through government support so as to achieve a low water tariff. The details of tariff design in BOT water supply projects are identified, and a minimum feasible tariff model is proposed for effective risk allocation arrangements. Risk analysis based on a real project in Malaysia is performed to demonstrate the application of the simulation model on the key factors of inflation, exchange rates and demand risk. The analysis shows that for inflation risk, a pre-set tariff adjustment formula is useful in lowering minimum feasible tariff. For exchange rate risk, the reference rate should be set lower than the best estimate. Lowering of minimum feasible tariff can also be achieved if the tariff for additional demand is lower than the tariff for guaranteed demand.
引用
收藏
页码:255 / 263
页数:9
相关论文
共 50 条
  • [1] Identifying risk factors of BOT for water supply projects
    Zeng, S. X.
    Wan, T. W.
    Tam, C. M.
    Liu, D.
    [J]. PROCEEDINGS OF THE INSTITUTION OF CIVIL ENGINEERS-WATER MANAGEMENT, 2008, 161 (02) : 73 - 81
  • [2] An investigation of Chinese BOT projects in water supply: a comparative perspective
    Chen, Chuan
    Messner, John I.
    [J]. CONSTRUCTION MANAGEMENT AND ECONOMICS, 2005, 23 (09) : 913 - 925
  • [3] New era / new solutions: The role of alternative tariff structures in water supply projects
    Silva Pinto, F.
    Cunha Marques, R.
    [J]. WATER RESEARCH, 2017, 126 : 216 - 231
  • [4] BOT CONTRACTS FOR WATER-SUPPLY
    MCCARTHY, SC
    PERRY, JG
    [J]. WORLD WATER 89: MANAGING THE FUTURE - LEARNING FROM THE PAST, 1989, : 215 - 220
  • [5] Estimation of minimum working capital for construction projects in Malaysia
    Hassim, S
    Kadir, MRA
    Lew, YL
    Sim, YC
    [J]. JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT-ASCE, 2003, 129 (04): : 369 - 374
  • [6] Valuation of the minimum revenue guarantee and the option to abandon in BOT infrastructure projects
    Huang, Yu-Lin
    Chou, Shih-Pei
    [J]. CONSTRUCTION MANAGEMENT AND ECONOMICS, 2006, 24 (04) : 379 - 389
  • [7] Shadow tolling model of expressway BOT projects
    Dai Dashuang
    Yang Weihua
    [J]. PROCEEDINGS OF 20TH IPMA WORLD CONGRESS ON PROJECT MANAGEMENT, VOLS 1 AND 2, 2006, : 101 - 105
  • [8] A grey evaluation model on bidders for BOT projects
    Yu, YH
    Shan, MY
    [J]. Proceedings of 2005 International Conference on Machine Learning and Cybernetics, Vols 1-9, 2005, : 3433 - 3437
  • [9] A LEGAL ANALYSIS OF SUCCESSFUL AND PROBLEMATIC BUILD OPERATE AND TRANSFER (BOT) PROJECTS IN MALAYSIA
    Markom, Ruzian
    Ali, Engku Rabiah Adawiah Engku
    [J]. INTERNATIONAL JOURNAL OF BUSINESS AND SOCIETY, 2012, 13 (02): : 133 - 150
  • [10] Unraveling of BOT scheme: Malaysia's Indah Water Konsortium
    Abdul-Aziz, AR
    [J]. JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT-ASCE, 2001, 127 (06): : 457 - 460