Minimum feasible tariff model for BOT water supply projects in Malaysia

被引:20
|
作者
Cheng Lianyu [1 ]
Tiong, Robert L. K. [2 ]
机构
[1] Henan Inst Finance & Econ, Zhengzhou, Henan, Peoples R China
[2] Nanyang Technol Univ, Sch Civil Environm Engn, Singapore, Singapore
关键词
BOT; water supply project; risk allocation; tariff-at-risk; minimum feasible tariff;
D O I
10.1080/0144619042000287778
中图分类号
F [经济];
学科分类号
02 ;
摘要
A key issue in implementing water supply projects based on the build, operate and transfer approach is risk allocation. Project risks should be allocated to the best competent party through proper contractual arrangements or through government support so as to achieve a low water tariff. The details of tariff design in BOT water supply projects are identified, and a minimum feasible tariff model is proposed for effective risk allocation arrangements. Risk analysis based on a real project in Malaysia is performed to demonstrate the application of the simulation model on the key factors of inflation, exchange rates and demand risk. The analysis shows that for inflation risk, a pre-set tariff adjustment formula is useful in lowering minimum feasible tariff. For exchange rate risk, the reference rate should be set lower than the best estimate. Lowering of minimum feasible tariff can also be achieved if the tariff for additional demand is lower than the tariff for guaranteed demand.
引用
收藏
页码:255 / 263
页数:9
相关论文
共 50 条
  • [31] A supply model for nurse workforce projection in Malaysia
    Abas, Zuraida Abal
    Ramli, Mohamad Raziff
    Desa, Mohamad Ishak
    Saleh, Nordin
    Hanafiah, Ainul Nadziha
    Aziz, Nuraini
    Abidin, Zaheera Zainal
    Shibghatullah, Abdul Samad
    Rahman, Ahmad Fadzli Nizam Abdul
    Musa, Haslinda
    [J]. HEALTH CARE MANAGEMENT SCIENCE, 2018, 21 (04) : 573 - 586
  • [32] A new financial engineering model for analyzing the royalty of BOT projects: The Taiwan case
    Kang, Chao-Chung
    Feng, Cheng-Min
    Huang, Szu-Chi
    [J]. 2007 IEEE INTERNATIONAL CONFERENCE ON INDUSTRIAL ENGINEERING AND ENGINEERING MANAGEMENT, VOLS 1-4, 2007, : 277 - +
  • [33] A model for determining the optimal project life span and concession period of BOT projects
    Zhang, Xiaoling
    Bao, Haijun
    Wang, Hongdi
    Skitmore, Martin
    [J]. INTERNATIONAL JOURNAL OF PROJECT MANAGEMENT, 2016, 34 (03) : 523 - 532
  • [34] SELECTION OF WATER-SUPPLY PROJECTS UNDER DROUGHT
    RIDGLEY, MA
    [J]. JOURNAL OF ENVIRONMENTAL SYSTEMS, 1992, 21 (03): : 207 - 221
  • [35] Evaluating Externally Funded Water Supply Projects in Nigeria
    Okereke, P.
    Onyenechere, E.
    [J]. ASIAN JOURNAL OF WATER ENVIRONMENT AND POLLUTION, 2009, 6 (03) : 61 - 65
  • [36] The Application of Real Option in Model for Infrastructure BOT Projects Based on Option Game
    Zhang, Junsheng
    Shi, Shenxiang
    Wang, Shijing
    [J]. 2012 INTERNATIONAL CONFERENCE ON FUTURE INFORMATION TECHNOLOGY AND MANAGEMENT SCIENCE & ENGINEERING (FITMSE 2012), 2012, 14 : 580 - 585
  • [37] Alternative Model for Determining the Optimal Concession Period in Managing BOT Transportation Projects
    Lv, Junna
    Ye, Gui
    Liu, Wei
    Shen, Liyin
    Wang, Hongxia
    [J]. JOURNAL OF MANAGEMENT IN ENGINEERING, 2015, 31 (04)
  • [38] Study on the evaluation model of collaborative governance capacity of sustainable supply chain in water diversion projects
    Lu, Yali
    Ding, Wenwen
    Liu, Meng
    [J]. WATER POLICY, 2022, 24 (09) : 1366 - 1382
  • [39] GENDER MAIN STREAMING IN WATER SUPPLY AND SANITATION PROJECTS
    Frone, Simona
    Frone, Dumitru Florin
    [J]. SCIENTIFIC PAPERS-SERIES MANAGEMENT ECONOMIC ENGINEERING IN AGRICULTURE AND RURAL DEVELOPMENT, 2014, 14 (02) : 127 - 132
  • [40] DYNAMIC PROGRAMING FOR OPTIMAL SEQUENCING OF WATER SUPPLY PROJECTS
    BUTCHER, WS
    HAIMES, YY
    HALL, WA
    [J]. WATER RESOURCES RESEARCH, 1969, 5 (06) : 1196 - &