Analysis of Cost of Rework on Time and Cost Performance of Building Construction Projects in Abuja, Nigeria

被引:6
|
作者
Eze, Emmanuel Chidiebere [1 ]
Idiake, John Ebhohimen [1 ]
机构
[1] Fed Univ Technol, Quant Surveying Dept, Minna, Nigeria
来源
INTERNATIONAL JOURNAL OF BUILT ENVIRONMENT AND SUSTAINABILITY | 2018年 / 5卷 / 01期
关键词
Construction project; Cost overrun; Rework; Time overrun; Nigeria;
D O I
10.11113/ijbes.v5.n1.246
中图分类号
TU98 [区域规划、城乡规划];
学科分类号
0814 ; 082803 ; 0833 ;
摘要
Rework is a menace that leads to undesired and unnecessary loss of efforts, it degrades project cost and schedule performance of construction projects, both at design and construction phases. This study therefore, analyzed the impact of cost of rework on time and cost performance of building construction projects in Nigerian, using selected commercial building project within the country's capital. A pro forma was adopted for gathering data on rework cost, project cost and time of selected building projects, while structured questionnaire was used to collect information on the likely measures for reducing rework incidences from construction professionals that were involved in the delivery of the identified projects. Regression analysis, relative importance index and Kruskal-Walis test were employed for data analysis. The study revealed a significant relationship between the cost of rework and initial and final project cost of delivering commercial buildings, as an average of 3.53% impact on the initial project cost, 46.60% contribution to cost overrun, and p-value of 0.000 was observed on all assessed projects. For the project delivery time, a significant relationship between the cost of rework and initial and final project duration, as an average of 7.35% impact on the initial delivery time, extra 19 days and p-value of 0.000 was observed on all assessed projects. Team building and education, management commitment, employee involvement, were some of the best possible measures to minimized rework problems.
引用
收藏
页码:56 / 67
页数:12
相关论文
共 50 条
  • [1] Assessment of rework cost of selected building projects in Nigeria
    Oke, Ayodeji
    Ugoje, O.
    INTERNATIONAL JOURNAL OF QUALITY & RELIABILITY MANAGEMENT, 2013, 30 (07) : 799 - 810
  • [2] Time-cost model for building projects in Nigeria
    Ogunsemi, D. R.
    Jagboro, G. O.
    CONSTRUCTION MANAGEMENT AND ECONOMICS, 2006, 24 (03) : 253 - 258
  • [3] The impact of contractors' management capability on cost and time performance of construction projects in Nigeria
    Aje, O.
    Odusami, K.
    Ogunsemi, D.
    JOURNAL OF FINANCIAL MANAGEMENT OF PROPERTY AND CONSTRUCTION, 2009, 14 (02) : 171 - +
  • [4] Green Building Construction Projects in Singapore: Cost Premiums and Cost Performance
    Hwang, Bon-Gang
    Zhu, Lei
    Wang, Yinglin
    Cheong, Xinyi
    PROJECT MANAGEMENT JOURNAL, 2017, 48 (04) : 67 - 79
  • [5] Measuring the Impact of Rework on Construction Cost Performance
    Hwang, Bon-Gang
    Thomas, Stephen R.
    Haas, Carl T.
    Caldas, Carlos H.
    JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT, 2009, 135 (03) : 187 - 198
  • [6] Comparing contributors to time and cost performance in building projects
    Dissanayaka, SM
    Kumaraswamy, MM
    BUILDING AND ENVIRONMENT, 1999, 34 (01) : 31 - 42
  • [7] Time-cost relationships in Australian building construction projects
    Love, PED
    Tse, RYC
    Edwards, DJ
    JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT, 2005, 131 (02) : 187 - 194
  • [8] The contributions of construction material waste to project cost overruns in Abuja, Nigeria
    Saidu, Ibrahim
    Shakantu, Winston
    ACTA STRUCTILIA, 2016, 23 (01) : 99 - 113
  • [9] Cause analysis of cost increases in municipal building construction projects
    Bernat, G.
    Geppert, F.
    Jocher, S.
    Juenger, H. C.
    BAUINGENIEUR, 2023, 98 (09): : 296 - 303
  • [10] Subcontracting and rework cost sharing in engineering-procurement-construction projects
    Chen, Zhenzhen
    Zhu, Wanshan
    Crama, Pascale
    INTERNATIONAL JOURNAL OF PRODUCTION ECONOMICS, 2023, 262