Significant factors causing delay in the UAE construction industry

被引:265
|
作者
Faridi, Arshi Shakeel [1 ]
El-Sayegh, Sameh Monir [2 ]
机构
[1] Amer Univ Sharjah, Dept Engn Syst & Management, Sharjah, U Arab Emirates
[2] Amer Univ Sharjah, Dept Civil Engn, Sharjah 26666, U Arab Emirates
关键词
Delay; project management; project controls; time; UAE;
D O I
10.1080/01446190600827033
中图分类号
F [经济];
学科分类号
02 ;
摘要
Construction delay is considered one of the most recurring problems in the construction industry. Delays have an adverse impact on project success in terms of time, cost, quality and safety. The effects of construction delays are not confined to the construction industry only, but influence the overall economy of a country like UAE, where construction plays a major role in its development and contributes 14% to the GDP. Thus, it is essential to define the most significant causes of delay in order to avoid or minimise their impact on construction projects. A detailed questionnaire was developed and used to get input from professionals associated with the UAE construction industry. The perspective of contractors and consultants has been analysed to rank the causes of delays based on their Relative Importance Index. Contractors and consultants were in agreement on the most significant causes of delays. The research revealed that 50% of the construction projects in UAE encounter delays and are not completed on time. The top 10 most significant causes of construction delays have been identified by this research. Approval of drawings, inadequate early planning and slowness of the owners' decision-making process are the top causes of delay in the UAE construction industry.
引用
收藏
页码:1167 / 1176
页数:10
相关论文
共 50 条
  • [11] Ranking of Delay Factors for Makkah's Construction Industry
    Al-Emad, Nashwan
    Rahman, Ismail Abdul
    Nagapan, Sasitharan
    Gamil, Yaser
    [J]. INTERNATIONAL SYMPOSIUM ON CIVIL AND ENVIRONMENTAL ENGINEERING 2016 (ISCEE 2016), 2017, 103
  • [12] Comparative Analysis of Factors Causing Delay in Residential Construction Projects in Pakistan
    Din, Zia Ud
    Raza, Ali
    Khan, Muhammad Babar
    [J]. CONSTRUCTION RESEARCH CONGRESS 2020: PROJECT MANAGEMENT AND CONTROLS, MATERIALS, AND CONTRACTS, 2020, : 640 - 648
  • [13] Assessment of the causes of delays in the UAE construction industry
    Faridi, AS
    El-Sayegh, SM
    [J]. PROCEEDINGS OF 2005 INTERNATIONAL CONFERENCE ON CONSTRUCTION & REAL ESTATE MANAGEMENT, VOLS 1 AND 2: CHALLENGE OF INNOVATION IN CONSTRUCTION AND REAL ESTATE, 2005, : 146 - 150
  • [14] The climate of innovation in the UAE and its construction industry
    Dulaimi, Mohammed
    [J]. ENGINEERING CONSTRUCTION AND ARCHITECTURAL MANAGEMENT, 2022, 29 (01) : 141 - 164
  • [15] SUPPLY CHAIN MANAGEMENT IN THE UAE CONSTRUCTION INDUSTRY
    Albaloushi, Helal
    Skitmore, Martin
    [J]. INTERNATIONAL JOURNAL OF CONSTRUCTION MANAGEMENT, 2008, 8 (01) : 53 - 71
  • [16] Comparative study of delay factors in Libyan and the UK construction industry
    Shebob, A.
    Dawood, N.
    Shah, R.
    Xu, Q.
    [J]. ENGINEERING CONSTRUCTION AND ARCHITECTURAL MANAGEMENT, 2012, 19 (06) : 688 - +
  • [17] Fuzzy assessment of the risk factors causing cost overrun in construction industry
    Savita Sharma
    Pradeep K. Goyal
    [J]. Evolutionary Intelligence, 2022, 15 : 2269 - 2281
  • [18] Fuzzy assessment of the risk factors causing cost overrun in construction industry
    Sharma, Savita
    Goyal, Pradeep K.
    [J]. EVOLUTIONARY INTELLIGENCE, 2022, 15 (04) : 2269 - 2281
  • [19] Use of Earned Value Management in the UAE Construction Industry
    Morad, Mohamed
    El-Sayegh, Sameh M.
    [J]. 2016 INTERNATIONAL CONFERENCE ON INDUSTRIAL ENGINEERING, MANAGEMENT SCIENCE AND APPLICATIONS (ICIMSA), 2016,
  • [20] Ranking of the Factors Causing Cost Overrun in Infrastructural Projects of UAE
    Alhammadi, Ahmed Salem Ahmed Marey
    Memon, Aftab Hameed
    [J]. INTERNATIONAL JOURNAL OF SUSTAINABLE CONSTRUCTION ENGINEERING AND TECHNOLOGY, 2020, 11 (02): : 204 - 211