Analyzing delay causes in Egyptian construction projects

被引:121
|
作者
Marzouk, Mohamed M. [1 ]
El-Rasas, Tarek I. [1 ]
机构
[1] Cairo Univ, Fac Engn, Dept Struct Engn, Giza, Egypt
关键词
Construction management; Construction delays; Disputes and litigation; Statistical analysis;
D O I
10.1016/j.jare.2012.11.005
中图分类号
O [数理科学和化学]; P [天文学、地球科学]; Q [生物科学]; N [自然科学总论];
学科分类号
07 ; 0710 ; 09 ;
摘要
Construction delays are common problems in civil engineering projects in Egypt. These problems occur frequently during project life-time leading to disputes and litigation. Therefore, it is essential to study and analyze causes of construction delays. This research presents a list of construction delay causes retrieved from literature. The feedback of construction experts was obtained through interviews. Subsequently, a questionnaire survey was prepared. The questionnaire survey was distributed to thirty-three construction experts who represent owners, consultants, and contractor's organizations. Frequency Index, Severity Index, and Importance Index are calculated and according to the highest values of them the top ten delay causes of construction projects in Egypt are determined. A case study is analyzed and compared to the most important delay causes in the research. Statistical analysis is carried out using analysis of variance ANOVA method to test delay causes, obtained from the survey. The test results reveal good correlation between groups while there is significant difference between them for some delay causes and finally roadmap for prioritizing delay causes groups is presented. (C) 2014 Cairo University. Production and hosting by Elsevier B.V. All rights reserved.
引用
收藏
页码:49 / 55
页数:7
相关论文
共 50 条
  • [21] Causes of Delay in Khuzestan Steel Company Construction Projects
    Saeb, Sajjad
    Khayat, Navid
    Telvari, Abdulrasoul
    [J]. INDUSTRIAL ENGINEERING AND MANAGEMENT SYSTEMS, 2016, 15 (04): : 335 - 344
  • [22] Causes of Delay in the Planning and Design Phases for Construction Projects
    Yang, Jyh-Bin
    Wei, Pei-Rei
    [J]. JOURNAL OF ARCHITECTURAL ENGINEERING, 2010, 16 (02) : 80 - 83
  • [23] Causes of Delay in Various Construction Projects: A Literature Review
    Mbala, Mbuyamba
    Aigbavboa, Clinton
    Aliu, John
    [J]. ADVANCES IN HUMAN FACTORS, SUSTAINABLE URBAN PLANNING AND INFRASTRUCTURE, 2019, 788 : 489 - 495
  • [24] Analysis of Causes of Delay and Time Performance in Construction Projects
    Gonzalez, Pablo
    Gonzalez, Vicente
    Molenaar, Keith
    Orozco, Francisco
    [J]. JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT, 2014, 140 (01)
  • [25] Analyzing Delays of Road Construction Projects in Cambodia: Causes and Effects
    San Santoso, Djoen
    Soeng, Sothy
    [J]. JOURNAL OF MANAGEMENT IN ENGINEERING, 2016, 32 (06)
  • [26] Delay causes in Kazakhstan's construction projects and remedial measures
    Hossain, Md Aslam
    Raiymbekov, Dinmukhambet
    Nadeem, Abid
    Kim, Jong Ryeol
    [J]. INTERNATIONAL JOURNAL OF CONSTRUCTION MANAGEMENT, 2022, 22 (05) : 801 - 819
  • [27] Analysis of causes of delay in Indian construction projects and mitigation measures
    Prasad, K. V.
    Vasugi, V.
    Venkatesan, R.
    Bhat, Nikhil
    [J]. JOURNAL OF FINANCIAL MANAGEMENT OF PROPERTY AND CONSTRUCTION, 2019, 24 (01) : 58 - 78
  • [28] Risk matrix for delay causes in building construction projects in KSA
    Alfraidi, Yahya Nasser
    [J]. INTERNATIONAL JOURNAL OF ADVANCED AND APPLIED SCIENCES, 2018, 5 (06): : 93 - 97
  • [29] Analysing delay causes and effects in Ghanaian state housing construction projects
    Amoatey, Charles Teye
    Ameyaw, Yaa Asabea
    Adaku, Ebenezer
    Famiyeh, Samuel
    [J]. INTERNATIONAL JOURNAL OF MANAGING PROJECTS IN BUSINESS, 2015, 8 (01) : 198 - 214
  • [30] Investigating the causes of delay in grain bin construction projects: the case of China
    Chen, Gui-Xiang
    Shan, Ming
    Chan, Albert P. C.
    Liu, Xu
    Zhao, Yi-Qing
    [J]. INTERNATIONAL JOURNAL OF CONSTRUCTION MANAGEMENT, 2019, 19 (01) : 1 - 14