A stochastic optimization formulation for the transition from open pit to underground mining

被引:0
|
作者
James A. L. MacNeil
Roussos G. Dimitrakopoulos
机构
[1] McGill University,COSMO—Stochastic Mine Planning Laboratory, Department of Mining and Materials Engineering
[2] Group for Research in Decision Analysis (GERAD),undefined
来源
关键词
Mine production scheduling; Stochastic optimization; Stochastic mine planning;
D O I
暂无
中图分类号
学科分类号
摘要
As open pit mining of a mineral deposit deepens, the cost of extraction may increase up to a threshold where transitioning to mining through underground methods is more profitable. This paper provides an approach to determine an optimal depth at which a mine should transition from open pit to underground mining, based on managing technical risk. The value of a set of candidate transition depths is calculated by optimizing the production schedules for each depth’s unique open pit and underground operations which provide yearly discounted cash flow projections. By considering the sum of the open pit and underground mining portion’s value, the most profitable candidate transition depth is identified. The optimization model presented is based on a stochastic integer program that integrates geological uncertainty and manages technical risk. The proposed approach is tested on a gold deposit. Results show the benefits of managing geological uncertainty in long-term strategic decision-making frameworks. Additionally, the stochastic result produces a 9% net present value increase over a similar deterministic formulation. The risk-managing stochastic framework also produces operational schedules that reduce a mining project`s susceptibility to geological risk. This work aims to approve on previous attempts to solve this problem by jointly considering geological uncertainty and describing the optimal transition depth effectively in 3-dimensions.
引用
收藏
页码:793 / 813
页数:20
相关论文
共 50 条
  • [21] CHANGEOVER FROM OPEN PIT TO UNDERGROUND MINING AT KIRUNA
    BERGLUND, CB
    MINING CONGRESS JOURNAL, 1971, 57 (11): : 83 - &
  • [22] Numerical Simulation of Crown Pillar Behaviour in Transition from Open Pit to Underground Mining
    Dintwe, Tumelo K. M.
    Sasaoka, Takashi
    Shimada, Hideki
    Hamanaka, Akihiro
    Moses, Dyson N.
    Peng, Ma
    Meng Fanfei
    Liu, Seifei
    Ssebadduka, Ronald
    Onyango, Joan A.
    GEOTECHNICAL AND GEOLOGICAL ENGINEERING, 2022, 40 (04) : 2213 - 2229
  • [23] Numerical Simulation of Crown Pillar Behaviour in Transition from Open Pit to Underground Mining
    Tumelo K. M. Dintwe
    Takashi Sasaoka
    Hideki Shimada
    Akihiro Hamanaka
    Dyson N. Moses
    Ma Peng
    Meng Fanfei
    Seifei Liu
    Ronald Ssebadduka
    Joan A. Onyango
    Geotechnical and Geological Engineering, 2022, 40 : 2213 - 2229
  • [24] CHANGEOVER FROM OPEN PIT TO UNDERGROUND MINING AT KIRUNA
    BERGLUND, CB
    MINING CONGRESS JOURNAL, 1972, 58 (11): : 53 - &
  • [25] Study of Residual Slope Mining and its Stability during Transition from Open Pit to Underground Mining
    Nan Shiqing
    Guo Xianzhang
    Zhang Juanxia
    DISASTER ADVANCES, 2012, 5 (04): : 110 - 115
  • [26] EXPERIENCE IN ORE RESERVES EXTRACTION IN OPEN-PIT BORDERS AND BOTTOM IN TRANSITION FROM OPEN-PIT TO UNDERGROUND MINING
    Tankov, M. S.
    Shelkovy, I. S.
    JOURNAL OF MINING INSTITUTE, 2012, 198 : 37 - 42
  • [27] Stochastic modelling of the open pit to underground transition interface for gold mines
    Opoku, Seth
    Musingwini, Cuthbert
    INTERNATIONAL JOURNAL OF MINING RECLAMATION AND ENVIRONMENT, 2013, 27 (06) : 407 - 424
  • [28] Evaluating the impacts of the transition from open-pit to underground mining on sustainable development indexes
    Badakhshan, Naser
    Shahriar, Kourosh
    Afraei, Sajjad
    Bakhtavar, Ezzeddin
    JOURNAL OF SUSTAINABLE MINING, 2023, 22 (02): : 155 - 168
  • [29] Disposal methods on solid wastes from mines in transition from open-pit to underground mining
    Lu, Zengxiang
    Cai, Meifeng
    SEVENTH INTERNATIONAL CONFERENCE ON WASTE MANAGEMENT AND TECHNOLOGY (ICWMT 7), 2012, 16 : 715 - 721
  • [30] Optimization of the transition from open-pit to underground operation in combined mining using (0-1) integer programming
    Bakhtavar, E.
    Shahriar, K.
    Mirhassani, A.
    JOURNAL OF THE SOUTHERN AFRICAN INSTITUTE OF MINING AND METALLURGY, 2012, 112 (12) : 1059 - 1064