Identifying factors causing cost overrun of the construction projects in India

被引:0
|
作者
Swapnil P Wanjari
Gaurav Dobariya
机构
[1] Visvesvaraya National Institute of Technology,Department of Civil Engineering
来源
Sādhanā | 2016年 / 41卷
关键词
Cost overrun in India; ANOVA; factor analysis; construction projects;
D O I
暂无
中图分类号
学科分类号
摘要
Delay and cost overrun are common phenomena in projects worldwide. However, these are especially severe in developing countries. In India as per MOSPI report, 235 projects out of 410 were severely affected cost overrun due to certain factors. A short questionnaire was conducted with 15 prominent factors responsible for cost overrun and forwarded to 190 constructional professionals across India. Total 85 responses were received and it was analyzed using various statistical tools such as analysis of variance (ANOVA) and factor analysis tool using SPSS. In this study, top three factors affecting cost overruns were identified such as price escalation of raw material, delay in planned activity and lack of co-ordination between construction parties which could be significantly responsible for cost overnun of construction project in India. Factor analysis method was also carried out to group the factors into three components of overall questionnaire. These components, such as client control component, project management component, and contractor control component, would be useful to the various parties involved in the construction activities. This paper also provides suggestive frameworks which have been framed after discussing with large number of construction professionals or expert.
引用
收藏
页码:679 / 693
页数:14
相关论文
共 50 条
  • [21] Cost overrun in the Malaysian construction industry projects: A deeper insight
    Shehu, Zayyana
    Endut, Intan Rohani
    Akintoye, Akintola
    Holt, Gary D.
    [J]. INTERNATIONAL JOURNAL OF PROJECT MANAGEMENT, 2014, 32 (08) : 1471 - 1480
  • [22] Cost Overrun Causes in Road Construction Projects: "Consultants' Perspective"
    Mahamid, Ibrahim
    Bruland, Amund
    [J]. CONSTRUCTION AND PROJECT MANAGEMENT, ICCPM 2011, 2011, 15 : 6 - 10
  • [23] Time Delay and Cost Overrun in Qatari Public Construction Projects
    Senouci, Ahmed
    Ismail, Alaa
    Eldin, Neil
    [J]. 5TH CREATIVE CONSTRUCTION CONFERENCE (CCC 2016), 2016, 164 : 368 - 375
  • [24] Managing Delays in Construction Projects Aiming at Cost Overrun Minimization
    Anysz, Hubert
    [J]. 4TH WORLD MULTIDISCIPLINARY CIVIL ENGINEERING-ARCHITECTURE-URBAN PLANNING SYMPOSIUM - WMCAUS, 2019, 603
  • [25] Research on Influencing Factors and Control Measures of Construction Cost Overrun in China's Expressway Projects
    Chen S.
    Fan X.
    Cai B.
    [J]. International Journal of Fuzzy System Applications, 2023, 12 (01)
  • [26] Significant factors causing cost overruns in large construction projects in Malaysia
    [J]. Memon, A. H., 1600, Asian Network for Scientific Information (13):
  • [27] UNEARTHING CAUSATIVE FACTORS OF COST OVERRUN ON GHANAIAN ROAD PROJECTS
    Akinradewo, Opeoluwa
    Aigbavboa, Clinton
    Oke, Ayodeji
    Coffie, Harrison
    Ogunbayo, Babatunde
    [J]. BALTIC JOURNAL OF ROAD AND BRIDGE ENGINEERING, 2022, 17 (04): : 171 - 188
  • [28] Contributing Factors of Time Overrun in Public Sector Construction Projects
    Akhund, Muhammad Akram
    Imad, Hafiz Usama
    Memon, Nafees Ahmed
    Siddiqui, Fida Hussain
    Khoso, Ali Raza
    Panhwar, Abbas Ali
    [J]. ENGINEERING TECHNOLOGY & APPLIED SCIENCE RESEARCH, 2018, 8 (05) : 3369 - 3372
  • [29] Assessing the Impact of Cost Overrun Causes in Transmission Lines Construction Projects
    Pham, Hai
    Luu, Truong-Van
    Kim, Soo-Yong
    Vien, Duc-Thinh
    [J]. KSCE JOURNAL OF CIVIL ENGINEERING, 2020, 24 (04) : 1029 - 1036
  • [30] Investigation on the Factors Influencing Construction Time and Cost Overrun for High-Rise Building Projects In Penang
    Haslinda, A. Nor
    Xian, T. Wei
    Norfarahayu, K.
    Hanafi, R. Muhamad
    Fikri, H. Muhammad
    [J]. INTERNATIONAL SEMINAR ON MATHEMATICS AND PHYSICS IN SCIENCES AND TECHNOLOGY 2017 (ISMAP 2017), 2018, 995