Implementing earned value management using bridge information modeling

被引:0
|
作者
Mohamed Marzouk
Mohamed Hisham
机构
[1] Cairo University,Structural Engineering Department
[2] Nile University,Construction Engineering and Management Program
来源
关键词
building information modeling; infrastructure bridges; bridge information modeling; cost estimate; time and cost control;
D O I
暂无
中图分类号
学科分类号
摘要
Building Information Modeling (BIM) has widely become an effective tool in engineering and construction fields. It could be used in: generating shop drawings; detecting clashes; estimating quantities; and controlling documents. Applying BIM technology on bridges is named Bridge Information Modeling (BrIM). Bridge Information Modeling (BrIM) is an intelligent representation of bridges since it contains all information needed about bridges through their whole lifecycle. This paper presents the use of Building Information Modeling in cost and time management of infrastructure bridges. BIM-based cost estimation application is presented which is capable to carry out approximate cost estimate; and detailed cost estimate. The application is designed in a flexible manner to be used with default values, or user defined values. Different performance measurement indexes are used in order to control the cost and schedule during execution phase of construction projects. This application integrates BIM with Earned Value (EV) concept to determine the project status at specific reporting date. A case study is presented to demonstrate the use of the developed modules.
引用
收藏
页码:1302 / 1313
页数:11
相关论文
共 50 条
  • [21] Project Management Model: Integrating Earned Schedule, Quality, and Risk in Earned Value Management
    Miguel, Angelimarie
    Madria, Wira
    Polancos, Ronaldo
    2019 IEEE 6TH INTERNATIONAL CONFERENCE ON INDUSTRIAL ENGINEERING AND APPLICATIONS (ICIEA), 2019, : 622 - 628
  • [22] "KAIZEN" (Improvement) in Spacecraft Project Management using "Earned Value Analysis"
    Lakshman, Deepti
    Kannan, M. V.
    Bhojraj, H.
    JOURNAL OF SPACECRAFT TECHNOLOGY, 2011, 21 (01): : 21 - 30
  • [23] Using the Earned Value Management System to Improve Electrical Project Control
    Hanna, Awad S.
    JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT-ASCE, 2012, 138 (03): : 449 - 457
  • [24] Project Performance Analysis using Earned Value Management Method in Telecommunication
    Widiningrum, Adelia
    Pratami, Devi
    Haryono, Imam
    INTERNATIONAL JOURNAL OF INTEGRATED ENGINEERING, 2020, 12 (03): : 107 - 114
  • [25] Calculating cumulative inefficiency using earned value management in construction projects
    Lee, Jae-Seob
    CANADIAN JOURNAL OF CIVIL ENGINEERING, 2015, 42 (04) : 222 - 232
  • [26] Quality: the third element of earned value management
    Dodson, Marcelo
    Defavari, Guilherme
    de Carvalho, Vitor
    CONFERENCE ON ENTERPRISE INFORMATION SYSTEMS/INTERNATIONAL CONFERENCE ON PROJECT MANAGEMENT/CONFERENCE ON HEALTH AND SOCIAL CARE INFORMATION SYSTEMS AND TECHNOLOGIES, CENTERIS/PROJMAN / HCIST 2015, 2015, 64 : 932 - 939
  • [27] Development of a Bridge Maintenance System Using Bridge Information Modeling
    Samadi, D.
    Taghaddos, H.
    Nili, M. H.
    Noghabaei, M.
    CIVIL ENGINEERING INFRASTRUCTURES JOURNAL-CEIJ, 2021, 54 (02): : 351 - 364
  • [28] Earned value management in project time control
    Vakhrushkina A.V.
    Mishakova A.V.
    Borshcheva K.D.
    Magazine of Civil Engineering, 2017, 71 (03): : 30 - 38
  • [29] Earned value management in a data warehouse project
    Department of Information Technology, College of Information Technology, Georgia Southern University, Statesboro, GA, United States
    不详
    不详
    Inf Manage Comput Secur, 2006, 1 (37-50):
  • [30] Study of the Stability of Earned Value Management Forecasting
    Wauters, Mathieu
    Vanhoucke, Mario
    JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT, 2015, 141 (04)