Process-circuit and layout solutions for steam-turbine units and performance efficiency of thermal power plants

被引:1
|
作者
Gol’dberg A.A. [1 ]
Shibaev T.L. [1 ]
机构
[1] Ural Turbine Works, ul. Frontovykh Brigad 18, Yekaterinburg
来源
Gol’dberg, A.A. (skbt@utz.ru) | 1600年 / Izdatel'stvo Nauka卷 / 61期
关键词
Costs; Efficiency; Process-circuit and layout solutions; Steam-turbine units; Thermal power plants;
D O I
10.1134/S0040601514120027
中图分类号
学科分类号
摘要
Criteria for evaluating process-circuit and layout solutions adopted in designing steam-turbine units are presented together with their values for a number of steam-turbine units produced by the Ural Turbine Works. The presented values of the criteria are recommended for being used as tentative ones in designing new thermal power plants or in upgrading them with the use of steam turbine units operating both as basic power installations and as part of combined-cycle power plants. The influence of process-circuit and layout solutions adopted for steam-turbine units on the effectiveness of thermal power plant construction and plant performance efficiency is shown. © 2014, Pleiades Publishing, Inc.
引用
收藏
页码:873 / 879
页数:6
相关论文
共 50 条
  • [41] IMPROVEMENT OF THE THERMODYNAMIC CYCLE OF STEAM TURBINE INSTALLATIONS OF THERMAL POWER PLANTS
    Lavrenchenko, Georg K.
    Slinko, Alexey G.
    Kozlovskyi, Serhii V.
    Boychuk, Artem S.
    JOURNAL OF CHEMISTRY AND TECHNOLOGIES, 2024, 32 (02): : 498 - 508
  • [42] Experience gained at the Ural Turbine Works with retrofitting steam turbine units for thermal power stations
    Valamin A.E.
    Kultyshev A.Yu.
    Gol'Dberg A.A.
    Shibaev T.L.
    Paneque Aguilera H.C.
    Thermal Engineering, 2013, 60 (8) : 541 - 547
  • [43] Use of GTÉ-65 gas turbine power units in the thermal configuration of steam-gas systems for the refitting of operating thermal electric power plants
    Lebedev A.S.
    Kovalevskii V.P.
    Getmanov E.A.
    Ermaikina N.A.
    Power Technology and Engineering, 2008, 42 (4) : 236 - 246
  • [44] Improvement of efficiency of steam-turbine power-generating unit of coal-dust combined heat and power stations
    Schinnikov, P
    Nozdrenko, G
    Serant, F
    Lovtsov, A
    Zykova, N
    Kovalenko, P
    Vikhman, O
    Borodikhin, I
    Grigoryeva, O
    Egorova, E
    Terbish, T
    KORUS 2003: 7TH KOREA-RUSSIA INTERNATIONAL SYMPOSIUM ON SCIENCE AND TECHNOLOGY, VOL 4, PROCEEDINGS: LIFE SCIENCE, BIOTECHNOLOGY, MEDICINE ENVIRONMENTAL TECHNOLOGY, ARCHITECTURE ENGINEERING EDUCATION SOCIAL SCIENCE, 2003, : 151 - 156
  • [45] DEVELOPMENT OF EXPERIMENTAL DUAL HYDRO-AMMONIAC PLANTS BASED ON STEAM-TURBINE POWER-PLANTS WITH 50 MW CAPACITY
    VERESH, G
    SENTDERDI, I
    PERIODICA POLYTECHNICA-MECHANICAL ENGINEERING, 1978, 22 (04): : 361 - 368
  • [46] POSSIBLE IMPROVEMENTS OF THE MASS SIZE AND VIBRATION NOISE PARAMETERS OF NUCLEAR-POWER-PLANTS WITH A STEAM-TURBINE CYCLE
    DOLGOV, VN
    SOVIET ATOMIC ENERGY, 1990, 69 (06): : 1029 - 1033
  • [47] New steam power-generating units. Selection of parameters of steam and their influence on efficiency of steam turbine plant
    Ogurtsov, A.P.
    Tyazheloe Mashinostroenie, 1996, (08): : 23 - 28
  • [48] STEAM TURBINE MODERNIZATIONS AT OPERATING FOSSIL POWER PLANTS: AN APPROACH TO MAXIMIZE EFFICIENCY AND OPTIMIZE COAL POWER PLANTS
    Smiarowski, Michael W.
    PROCEEDINGS OF THE ASME POWER CONFERENCE - 2011, VOL 1, 2012, : 529 - 536
  • [49] Retrofitting the schematic and layout solutions of the condensate-feedwater path and its equipment of turbine units at thermal and nuclear power stations
    Trifonov N.N.
    Kovalenko E.V.
    Ignat'ev I.V.
    Shalkevich Yu.V.
    Therm Eng, 2006, 2 (110-112): : 110 - 112
  • [50] Impact of Fuels on Performance and Efficiency of Gas Turbine Power Plants
    Basha, Mehaboob
    Shaahid, S. M.
    Al-Hadhrami, Luai
    2011 2ND INTERNATIONAL CONFERENCE ON ADVANCES IN ENERGY ENGINEERING (ICAEE), 2012, 14 : 558 - 565